SUPREME COURT OF VICTORIA
COURT OF APPEAL
S APCI 2015 0099
| AUSTRALIAN DREAM HOMES PTY LTD | Applicant |
| v | |
| ILIJA STOJANOVSKI and ZAGORKA STOJANOVSKI | Respondents |
---
| JUDGES: | SANTAMARIA and McLEISH JJA |
| WHERE HELD: | MELBOURNE |
| DATE OF HEARING: | 4 March 2016 |
| DATE OF ORDERS: | 4 March 2016 |
| DATE OF REASONS: | 11 March 2016 |
| MEDIUM NEUTRAL CITATION: | [2016] VSCA 38 |
---
PRACTICE AND PROCEDURE – Application for security for costs – Equivocal evidence as to impecuniosity – Delay in bringing application – Genuinely arguable question of law of public importance – r 64.38(2) of the Supreme Court (General Civil Procedure) Rules 2015 – Application dismissed.
---
APPEARANCES: | Counsel | Solicitors |
| For the Applicant | Mr R de Meyrick | Lovegrove Smith & Cotton |
| For the Respondents | Mr R Andrew and Mr N Phillpott | Noble Lawyers Pty Ltd |
SANTAMARIA JA
McLEISH JA:
On 21 August 2011, the applicant (‘the builder’) entered into a domestic building contract to construct a new single storey brick veneer dwelling upon land in Reservoir owned by the respondents (‘the owners’). The contract was in the printed form of a Master Builders Association of Victoria New Homes Contract (HC-6 Edition 1-2007) (‘the contract’). The contract was a standard building contract governed by the Domestic Building Contracts Act 1995. Clause 20 of the contract conferred upon the owners the right to terminate the contract in certain circumstances.
Clause 20.1 provided, in part:
If the Builder:
…
· fails to proceed with the Works with due diligence or in a competent manner; OR
· unreasonably suspends the carrying out of the Works; OR
· refuses or persistently neglects to remove or remedy defective work or improper Materials, so that by the refusal or persistent neglect the Works are adversely affected; OR
· refuses or persistently neglects to comply with this Contract (including the requirements of municipal or other authorities); OR
· is unable or unwilling to complete the Works or abandons the Contract; OR
· is in substantial breach of this Contract;
THEN
the Owner may give written notice by registered post to the Builder:
· describing the breach or breaches of the Contract by the Builder; AND
· stating the Owner’s intention to terminate the Contract unless the Builder remedies the breach or breaches of this Contract within a period of fourteen (14) Days after the Builder’s receipt of the above notice.
Clause 20.2 of the contract provided that if the builder failed to remedy the breach the owner may terminate the contract by giving a further written notice to the builder. Clause 20.3 provided that the owner may not terminate the contract unreasonably or vexatiously or if the owner was in substantial breach of the contract.
In late October or early November 2011, the works commenced. In early November 2011, the concrete slab was poured. On or around 15 November 2011, the builder received a letter from the owners’ daughter raising a number of concerns regarding the construction of the works. On 13 April 2012,…
Keep reading for free
Create a free CaseChat account to read Australian Dream Homes Pty Ltd v Stojanovski and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2016] VSCA 38
- Decision Date
CaseChat Overview and Summary
The court considered whether the delay in bringing the application for security for costs was justified and whether there was equivocal evidence concerning the defendant's financial situation. The plaintiff argued that the delay prejudiced their case, while the defendant maintained that the delay was reasonable and the evidence regarding financial status was not equivocal. The court also had to assess if the application raised a genuinely arguable question of law of public importance, which could warrant the imposition of security for costs.
After evaluating the evidence and arguments presented, the court found that the delay in bringing the application was not justified and that there was equivocal evidence regarding the defendant's financial status. The court also determined that the application did not raise a genuinely arguable question of law of public importance. Consequently, the application for security for costs was dismissed. The court emphasised the importance of promptness in such applications and the need for clear evidence of financial hardship.
The final orders of the court included dismissing the plaintiff's application for security for costs and awarding costs of the application to the defendant. This decision underscores the significance of timely and well-supported applications for security for costs in civil litigation.
Background
Background to the litigation
The case initially came before the Supreme Court of Victoria for a hearing on ADHA's application for security for costs. This application was brought under r 64.38 of the Supreme Court (General Civil Procedure) Rules 2015. Prior to this application, there had been no prior determinations on the issue of security for costs in relation to this case. The hearing involved submissions from both parties on the evidence of impecuniosity, the delay in bringing the application, and whether there was a genuinely arguable question of law of public importance.
Decision
Reasons for decision
1. Whether the evidence was equivocal as to the impecuniosity of the respondent, Mr Stojanovski.
2. Whether there had been an unjustifiable delay in bringing the application for security for costs.
3. Whether there was a genuinely arguable question of law of public importance in relation to the application for security for costs.
Held
1. The court concluded that the evidence regarding the impecuniosity of the respondent, Mr Stojanovski, was equivocal.
2. The court found that there had been an unjustifiable delay in bringing the application for security for costs.
3. The court determined that there was no genuinely arguable question of law of public importance in relation to the application for security for costs.
Ratio Decidendi
Legal Principle Established
The court approached the application for security for costs by examining the three key issues. Firstly, regarding the impecuniosity of Mr Stojanovski, the court reviewed the evidence presented and found it to be equivocal. While some evidence suggested financial difficulties, other evidence pointed towards more substantial financial resources. This equivocal nature of the evidence meant that the court could not make a definitive finding on the respondent's financial standing.
Secondly, the court considered the delay in bringing the application for security for costs. The court noted that there had been a significant period between when the applicant became aware of the potential financial issues and when the application was made. This delay was deemed unjustifiable, impacting the applicant's case negatively. The court emphasised the importance of timely applications in ensuring the integrity of the legal process.
Finally, the court assessed whether there was a genuinely arguable question of law of public importance. It concluded that the issues raised did not meet the threshold for such a question, as the matters were not of broad public interest or did not present a novel legal issue warranting further examination. The court relied on established criteria under r 64.38(2) of the Supreme Court (General Civil Procedure) Rules 2015 in making its determination. Given the findings on equivocal evidence and unjustifiable delay, the court dismissed the application for security for costs.