SUPREME COURT OF QUEENSLAND

CITATION:

Transfield Services (Australia) Pty Limited v Nortask Pty Ltd and Anor [2012] QSC 306

PARTIES:

TRANSFIELD SERVICES (AUSTRALIA) PTY LIMITED

(Applicant)

v

NORTASK PTY LTD

(First Respondent)

and

PHILIP DAVENPORT

(Second Respondent)

FILE NO/S:

11836 of 2011

DIVISION:

Trial Division

PROCEEDING:

Application

DELIVERED ON:

9 October 2012

DELIVERED AT:

Brisbane

HEARING DATE:

10 April 2012

JUDGE:

Douglas J

ORDER:

Application dismissed

CATCHWORDS:

ADMINISTRATIVE LAW – JUDICIAL REVIEW – GROUNDS OF REVIEW – PROCEDURAL FAIRNESS – GENERALLY – where the first respondent made a payment claim to the applicant – where a claim was made for Variation 17a  relating to rock breaking – where an adjudicator’s decision was made pursuant to Building Construction Industry Payments Act 2004 (Qld) – where the applicant seeks a declaration that the adjudicator’s decision is void because the adjudicator breached the rules of procedural fairness in concluding that the first respondent had engaged another firm as a nominated subcontractor under the building contract when it was neither the applicant nor the respondent – where the first respondent conceded a breach of the rules of procedural fairness – where the first respondent argued it was not a material denial of procedural fairness as it could not have made any difference to the outcome – whether a declaration ought be made that the adjudicator’s decision is void

Bauen Constructions v Westwood Interiors [2010] NSWSC 1359, cited
Northbuild Construction Pty Ltd v Central Interior Linings Pty Ltd [2011] QCA 22, cited
Rail Corporation of NSW v Nebax Constructions [2012] NSWSC 6, cited
Shorten v David Hurst Constructions Pty Ltd [2008] NSWSC 546, cited
Trysams Pty Ltd v Club Constructions (NSW) Pty Ltd [2007] NSWSC 941, cited
Trysams Pty Ltd v Club Constructions (NSW) Pty Ltd [2008] NSWSC 399, cited
Waterways Authority v Fitzgibbon [2005] HCA 57; 79 ALJR 1816, cited

COUNSEL:

M Christie SC with M Hindman for the applicant

J Bond SC with S Armitage for the first respondent

No appearance for the second respondent

SOLICITORS:

Thompsons as town agents for Baker McKenzie for the applicant

Clifford Gouldson for the first respondent

No appearance for the second respondent

Introduction

  1. This is an application for a declaration that an adjudicator’s decision pursuant to the Building Construction Industry Payments Act2004 (Qld) is void because the adjudicator breached the rules of procedural fairness in concluding that the first respondent had engaged another firm called Trenching Systems Australia (“TSA”) as a nominated subcontractor under the relevant building contract when it was not and neither the applicant, Transfield Services (Australia) Pty Limited (“Transfield”), nor the respondent, Nortask Pty Ltd (“Nortask”), having submitted to the adjudicator that it was.

  1. Nortask accepts that there has been a breach of the rules of procedural fairness but argues that it was not a material denial of procedural fairness as it could not have made any difference to the outcome.  There is also an argument whether the adjudicator’s decision was deficient in failing to…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Transfield Services (Australia) Pty Limited v Nortask Pty Lt... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2012] QSC 306
Decision Date

CaseChat Overview and Summary

The case of Transfield Services (Australia) Pty Limited v Nortask Pty Ltd involved a dispute between the applicant, Transfield Services, and the first respondent, Nortask, concerning a payment claim made by Nortask. The crux of the matter was a claim for Variation 17a, related to rock breaking, which was decided by an adjudicator under the Building Construction Industry Payments Act 2004 (Qld). Transfield Services sought a declaration that the adjudicator's decision was void, alleging that the adjudicator had breached the rules of procedural fairness by concluding that Nortask had engaged another firm as a nominated subcontractor under the building contract, despite it being neither Transfield Services nor Nortask. Nortask conceded the breach but argued that it was not a material denial of procedural fairness as it could not have affected the outcome.

The court was tasked with determining whether, despite the procedural error, a declaration should be made that the adjudicator's decision was void. The legal issue hinged on whether the procedural error was so significant as to render the adjudicator's decision invalid. The court considered whether the breach of procedural fairness materially affected the outcome of the adjudication, given that Nortask had conceded the error and the court had to weigh the impact of such error on the final decision.

After examining the evidence and arguments, the court concluded that the breach of procedural fairness did not materially affect the outcome of the adjudication. The court found that Nortask's concession did not alter the fact that the adjudicator's decision process was flawed, but the impact on the result was negligible. Therefore, the court dismissed Transfield Services' application for a declaration that the adjudicator's decision was void.

Orders

Orders of the court

Application dismissed

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.