Sierra Property Qld Pty Ltd v National Construction Management Pty Ltd

Link copied
Case Copied 37 min read

SUPREME COURT OF QUEENSLAND

CITATION:

Sierra Property Qld Pty Ltd v National Construction Management Pty Ltd & Ors [2016] QSC 108

PARTIES:

SIERRA PROPERTY QLD PTY LTD
ACN 097 523 272
(applicant)

v

NATIONAL CONSTRUCTION MANAGEMENT PTY LTD
ACN 118 395 752
(first respondent)

and

JONATHAN SIVE
(second respondent)

and

THE ADJUDICATION REGISTRAR (QUEENSLAND BUILDING AND CONSTRUCTION COMMISSION)
(third respondent)

FILE NO/S:

BS11244/15

DIVISION:

Trial Division

PROCEEDING:

Originating Application

DELIVERED ON:

18 May 2016

DELIVERED AT:

Brisbane

HEARING DATE:

29 March 2016

JUDGE:

Jackson J

ORDERS:

1. Declare that the part of the adjudication decision of the second respondent dated 26 October 2015 upon adjudication application number QBCC6545 as to the allowance for the original contract works in the amount of $118,030 (exclusive of GST) is affected by jurisdictional error.

2.     Direct the parties to confer within 7 days of this order with a view to agreeing upon the orders to be made to give effect to paragraph 1 of this order and any consequential orders.

3.     Failing agreement, direct the parties within 14 days of this order to provide written submissions as to the further orders to be made having regard to paragraph 1 and the reasons published this day, limited to no more than five pages.

4.     Otherwise adjourn the hearing of the application to a date to be fixed.

CATCHWORDS:

ADMINISTRATIVE LAW – PREROGATIVE WRITS AND ORDERS – CERTIORARI – GROUNDS FOR CERTIORARI TO QUASH – EXCESS OR WANT OF JURISDICTION – PARTICULAR INSTANCES OF JURISDICTIONAL ERROR – where the applicant and the first respondent were parties to a construction contract – where the first respondent served a payment claim under the Building and Construction Industry Payments Act 2004 (Qld) for work claimed to have been performed under the original contract as well as additional work by way of variations – where an adjudication decision was made under the Act – where the adjudicator allowed the claim for work performed under the original contract at 95 per cent, without referring to (or making findings in relation to) the nine relevant contract categories of work identified in the adjudication process, about which extensive submissions were made – where the adjudicator stated that he had carefully considered the material which satisfied him that 95 per cent allowance was appropriate – where the adjudicator made allowances for variations under the contract – where, irrespective of the legal correctness of those conclusions as to the variations, the adjudicator had set out the reasons for them – whether the adjudicator failed to give reasons or adequate reasons as required by s 26(3)(b) of the Act – whether any failure to give reasons or adequate reasons as required by s 26(3)(b) of the Act was a jurisdictional error

Acts Interpretation Act 1954 (Qld), ss 4, 27B
Building and Construction Industry Payments Act 2004 (Qld), ss 26, 99, 100
Judicial Review Act 1991 (Qld), s 18, sch 1

Queensland Building and Construction Commission Act 1991 (Qld), s 15

Avopiling (NSW) Pty Ltd v Menard…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Sierra Property Qld Pty Ltd v National Construction Manageme... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2016] QSC 108
Decision Date

CaseChat Overview and Summary

The matter of Sierra Property Qld Pty Ltd v National Construction Management Pty Ltd involved a dispute between the applicant, Sierra Property, and the first respondent, National Construction Management, who were parties to a construction contract. The applicant sought to challenge a payment claim served by the first respondent under the Building and Construction Industry Payments Act 2004 (Qld). The dispute centred around the adjudication decision made by the second respondent regarding the payment claim, particularly the portion relating to work performed under the original contract and additional variations. The court was tasked with determining whether the adjudicator's decision contained a jurisdictional error due to a failure to provide adequate reasons for the allowance of the original contract works.

The primary legal issue before the court was whether the adjudicator's decision to allow the claim for work performed under the original contract at 95 per cent constituted a jurisdictional error. This involved an examination of whether the adjudicator had failed to give reasons or adequate reasons as required by section 26(3)(b) of the Act. The court had to assess the adequacy of the reasons provided by the adjudicator for the 95 per cent allowance and determine if this omission constituted a jurisdictional error that could be grounds for certiorari.

The court found that the adjudicator had indeed committed a jurisdictional error in not providing adequate reasons for the 95 per cent allowance for the original contract works. Despite the adjudicator stating that he had considered the material and was satisfied that the 95 per cent allowance was appropriate, he did not refer to or make findings in relation to the nine relevant contract categories of work identified in the adjudication process. The court held that the adjudicator's failure to address these categories and provide adequate reasons for the 95 per cent allowance constituted a jurisdictional error, thus affecting the decision.

The court declared that the part of the adjudication decision concerning the allowance for the original contract works was affected by jurisdictional error. It directed the parties to confer and reach an agreement on orders to give effect to this declaration within seven days. If the parties could not agree, the court required written submissions on further orders to be made, limited to no more than five pages, to be submitted within fourteen days. The hearing of the application was adjourned to a date to be fixed.

Orders

Orders of the court

1. Declare that the part of the adjudication decision of the second respondent dated 26 October 2015 upon adjudication application number QBCC6545 as to the allowance for the original contract works in the amount of $118,030 (exclusive of GST) is affected by jurisdictional error.

2. Direct the parties to confer within 7 days of this order with a view to agreeing upon the orders to be made to give effect to paragraph 1 of this order and any consequential orders.

3. Failing agreement, direct the parties within 14 days of this order to provide written submissions as to the further orders to be made having regard to paragraph 1 and the reasons published this day, limited to no more than five pages.

4. Otherwise adjourn the hearing of the application to a date to be fixed.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established