CH2M Hill Australia Pty Limited v ABB Australia Pty Ltd

Link copied
Case Copied 64 min read

CH2M Hill Australia Pty Limited & Anor v ABB Australia Pty Ltd & Anor [2016] NTSC 42

PARTIES:CH2M Hill Australia Pty Limited

(ABN 42 050 070 892)

and

UGL Engineering Pty Limited

(ABN 96 096 365 972)

v

ABB Australia Pty Ltd

(ABN 68 003 337 611)

and

BOND, Colin

TITLE OF COURT:  SUPREME COURT OF THE NORTHERN TERRITORY

JURISDICTION:  SUPREME COURT OF THE NORTHERN TERRITORY EXERCISING TERRITORY JURISDICTION

FILE NO:64 of 2016 (21634407)

DELIVERED:  15 AUGUST 2016

HEARING DATES:  11 AUGUST 2016

JUDGMENT OF:  KELLY J

CATCHWORDS:

STATUTORY INTERPRETATION – s 27 of the Construction Contracts (Security of Payments) Act 2004 (NT) – word ‘dispute’ in s 27 refers to “payment dispute” as defined by s 8 – s 27 only precludes the making of an application for adjudication where a payment dispute within the meaning of s 8 has arisen in relation to a construction contract as defined in s 5 and an application for adjudication of that dispute has already been made by a party – s 27 does not preclude the making of an application for adjudication where “the substance of the dispute” has been the subject of a previous application for adjudication

ADMINISTRATIVE LAW –Construction Contracts (Security of Payments) Act 2004 (NT) ss 33 and 48 – decision of adjudicator not to dismiss an application without a determination on the merits under s 33(1)(a)(iv) not reviewable if the matter in fact too complex to fairly determine within prescribed time limits – Adjudicator must be satisfied it is not possible to fairly make a determination – decision of adjudicator reviewable if adjudicator’s satisfaction that the matter is not too complex is unreasonable

ADMINISTRATIVE LAW – Construction Contracts (Security of Payments) Act 2004 (NT) ss 38(d), 34(1)(a)(ii) and 33(1)(b) - Judicial review – availability of order in the nature of certiorari to quash decision of adjudicator – adjudicator must make a bona fide attempt to comply with essential requirements of the Act and comply with essential requirements of natural justice – adjudicator failed to comply with requirement in s 38(d) to provide reasons for determination – reasons failed to meaningfully engaged with the issues raised by the plaintiff - reasons failed to address material submitted by plaintiff - adjudicator failed to consider response to adjudication application as required by s 34(1)(a)(ii) - as a result adjudicator failed to make a bona fide attempt under s 33(1)(b) to determine on the balance of probabilities whether defendant liable to make a payment to the plaintiff – adjudicator also failed to comply with essential requirements of natural justice - purported adjudication determination a nullity – order in the nature of certiorari granted under O 56 of Supreme Court Rules quashing purported determination

Construction Contracts (Security of Payments) Act 2004(NT)

Supreme Court Rules 1987 (NT) O 56

Avopiling (NSW) Pty Ltd v Menard Bachy Pty Ltd [2012] NSWSC 1466; Bauen Constructions v Westwood Interiors [2010] NSWSC 1359; Brodyn Pty Ltd v Davenport (2004) 61 NSWLR 421; [2004]…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read CH2M Hill Australia Pty Limited v ABB Australia Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Find similar cases

Other decisions on the same topics. Each opens in a new tab.

Details

Case
[2016] NTSC 42
Decision Date

CaseChat Overview and Summary

The case of CH2M Hill Australia Pty Limited v ABB Australia Pty Ltd involved the interpretation of statutory provisions under the Construction Contracts (Security of Payments) Act 2004 (NT) and the judicial review of an adjudicator's determination. The plaintiff, CH2M Hill Australia Pty Limited, sought to challenge a determination made by an adjudicator appointed under the Act. The primary issues before the court were whether the adjudicator's decision to dismiss the application without a determination on the merits was reviewable, and if the adjudicator's determination was compliant with statutory requirements and the principles of natural justice.

The court first addressed the issue of whether the adjudicator's decision not to dismiss the application without a determination on the merits was reviewable. The court found that the decision was not reviewable if the adjudicator was satisfied that the matter was too complex to fairly determine within the prescribed time limits. The court emphasised that the adjudicator must be satisfied that it is not possible to fairly make a determination. However, the court held that the decision would be reviewable if the adjudicator's satisfaction that the matter was too complex was unreasonable. In this case, the court found that the adjudicator had not adequately engaged with the issues raised by the plaintiff and had failed to address the material submitted, leading to the conclusion that the decision was reviewable.

Further, the court examined whether the adjudicator's determination complied with the essential requirements of the Act and the principles of natural justice. The court found that the adjudicator had failed to provide reasons for the determination, which did not meaningfully engage with the issues raised by the plaintiff or address the material submitted. Additionally, the adjudicator had not considered the plaintiff's response to the adjudication application as required by the Act. The court concluded that these failures meant the adjudicator had not made a bona fide attempt to determine the dispute on the balance of probabilities, and had thereby failed to comply with the essential requirements of natural justice. As a result, the adjudicator's determination was a nullity.

Accordingly, the court granted the plaintiff's application for an order in the nature of certiorari under O 56 of the Supreme Court Rules, quashing the adjudicator's determination. The court also declared that the determination was of no effect. This outcome underscored the importance of adjudicators providing adequate reasons and engaging with the material submitted in adjudication proceedings.

Background

Background to the litigation

This is an application for judicial review of a purported adjudication determination of an adjudicator appointed under the Construction Contracts (Security of Payments) Act (“the Act”). The plaintiffs seek an order in the nature of certiorari under O 56 of the Supreme Court Rules quashing the determination or, alternatively, a declaration that the determination is of no effect. In accordance with the principles in R v Australian Broadcasting Tribunal; Ex parte Hardiman[1] the second defendant has taken no part in these proceedings. (In this judgment the first defendant is referred to as “the defendant”.)Background On 17 July 2014, the plaintiffs, as joint venturers, and the defendant entered into a construction contract (“the Contract”) under which the defendant was to supply to the joint venture major equipment for the combined cycle power plant at the Ichthys Onshore LNG Facilities at Bladin Point near Darwin[2] for the contract price of $19,112,000.[3] (The plaintiffs as joint venturers [referred to in the Contract as “CH2-UGL JV”] are referred to in this judgment as “the plaintiff”.) On 7 March 2016, the defendant served on the plaintiff a payment claim [PC009 Rev 2] claiming payment of $2,418,603.99 for certain work within the scope of the Contract and for “Change Orders”[4] two to six. On 15 March 2016 the plaintiff issued a payment certificate under the Contract for $908,047.14 of that amount which it then set off against its claim for liquidated damages.[5] On 10 June 2016 the defendant made application under s 28 of the Act to have the payment dispute adjudicated (“Application 1”) and Mr Neil Kirkpatrick was appointed as the adjudicator (“Adjudication 1”).[6] By application dated 15 June 2016, the defendant made a second application for adjudication under s 28 of the Act relating to payment claim PC-10 claiming payment of $6,478,840.50 (“Application 2”)[7] and another adjudicator, Mr Colin Bond, was appointed (“Adjudication 2”). On 11 July 2016, Mr Kirkpatrick dismissed Application 1 under s 33(1)(a) of the Act on the ground that the payment dispute had in fact arisen on 2 March 2016 and Application 1 had not been made within 90 days as required by s 28(1) (“Determination 1”). On 27 June 2016, the plaintiff submitted its Response to Application 2 and, after an extension of time under s 34(3)(a), Mr Bond handed down his determination on Adjudication 2 on 18 July 2016 determining that an amount of $3,372,045.80 was owing by the plaintiff to the defendant (“Determination 2”). On 25 July 2016 the plaintiff filed (and served on 26 July 2016) the originating motion in this proceeding seeking judicial review of Determination 2 and an interim injunction restraining the defendant from enforcing Determination 2. On 27 July 2016 Grant CJ granted an injunction restraining the defendant from taking steps pursuant to s 45 of the Act or otherwise to enforce Determination 2 except on two days’ written notice to the plaintiff and the Construction Registrar; made procedural directions in relation to the filing of submissions; and listed the substantive matter for hearing before me on 11 August 2016.

Decision

Reasons for decision

In Public Service Association and Professional Officers’ Association Amalgamated Union of New South Wales v Secretary of the Treasury[74] Basten JA considered the content of the obligations of the full bench of the Industrial Relations Commission to provide reasons for its decisions in the following terms:The content of reasons sufficient to satisfy the obligation will vary, depending on the issues in dispute, the subject matter of the dispute, the urgency in reaching a decision and a variety of other factors. However, some guidance may be obtained from standard statutory provisions which require that written reasons “set out the findings on material questions of fact and refer to the evidence or other material on which those findings were based”: cf Acts Interpretation Act 1901 (Cth), s 25D. Generally, the concept of “reasons” requires an explanation connecting any findings of fact with the ultimate decision.[75] [emphasis added] In Shell Refining (Australia) Pty Limited v A J Mayr Engineering Pty Limited[76] Bergin J in the Supreme Court of New South Wales considered the effect of a “catch-all” phrase in an adjudication determination to this effect: “I have considered all the material. The fact that I do not specifically refer to any submission or document must not be taken as any indication that I have not considered it.” Bergin J commented:It is perhaps understandable that some adjudicators whose determinations have been the subject of administrative law challenge may regard it as appropriate to utilise a catch-all statement, similar to the one used in the Determination, to fend off an allegation that they have failed to consider a relevant matter. Notwithstanding the somewhat pressure cooker environment in which adjudicators provide their determinations, it seems to me that it would be unhelpful for adjudicators to develop such a practice. It is assumed that adjudicators will comply with their statutory duties under s 22(2) of the Act, which sets out the matters to which they are to give consideration. A consideration of whether they have so complied is made from the content of their determinations rather than from a statement or claim by the adjudicator in the determination that he/she has so complied. I am not persuaded that the defendant is able to obtain any assistance or support for its submissions from this statement by the adjudicator on the first page of the determination.[77] It seems to me that, viewed objectively, Determination 2 does not give reasons for the adjudicator’s determinations that the defendant is entitled to EOTs under the Contract, in particular in relation to the delay issue, the notice issue and the James Engineering issue. It certainly does not rise to the standard set out in Pittwater Council v Keystone Projects, and fails even to set out findings of fact let alone connect findings of fact with the ultimate decision. The statement at par 148 “Based on the information provided to me by the applicant in the adjudication application, I am satisfied that the notice provisions of clause 7.1(a) and clause 7.1(b) have been satisfied” is the functional equivalent of saying, “I am satisfied” without more in relation to the notice issue.[78]

Ratio Decidendi

Legal principle established