CH2M Hill Australia Pty Limited & Anor v ABB Australia Pty Ltd & Anor [2016] NTSC 42
PARTIES:CH2M Hill Australia Pty Limited
(ABN 42 050 070 892)
and
UGL Engineering Pty Limited
(ABN 96 096 365 972)
v
ABB Australia Pty Ltd
(ABN 68 003 337 611)
and
BOND, Colin
TITLE OF COURT: SUPREME COURT OF THE NORTHERN TERRITORY
JURISDICTION: SUPREME COURT OF THE NORTHERN TERRITORY EXERCISING TERRITORY JURISDICTION
FILE NO:64 of 2016 (21634407)
DELIVERED: 15 AUGUST 2016
HEARING DATES: 11 AUGUST 2016
JUDGMENT OF: KELLY J
CATCHWORDS:
STATUTORY INTERPRETATION – s 27 of the Construction Contracts (Security of Payments) Act 2004 (NT) – word ‘dispute’ in s 27 refers to “payment dispute” as defined by s 8 – s 27 only precludes the making of an application for adjudication where a payment dispute within the meaning of s 8 has arisen in relation to a construction contract as defined in s 5 and an application for adjudication of that dispute has already been made by a party – s 27 does not preclude the making of an application for adjudication where “the substance of the dispute” has been the subject of a previous application for adjudication
ADMINISTRATIVE LAW –Construction Contracts (Security of Payments) Act 2004 (NT) ss 33 and 48 – decision of adjudicator not to dismiss an application without a determination on the merits under s 33(1)(a)(iv) not reviewable if the matter in fact too complex to fairly determine within prescribed time limits – Adjudicator must be satisfied it is not possible to fairly make a determination – decision of adjudicator reviewable if adjudicator’s satisfaction that the matter is not too complex is unreasonable
ADMINISTRATIVE LAW – Construction Contracts (Security of Payments) Act 2004 (NT) ss 38(d), 34(1)(a)(ii) and 33(1)(b) - Judicial review – availability of order in the nature of certiorari to quash decision of adjudicator – adjudicator must make a bona fide attempt to comply with essential requirements of the Act and comply with essential requirements of natural justice – adjudicator failed to comply with requirement in s 38(d) to provide reasons for determination – reasons failed to meaningfully engaged with the issues raised by the plaintiff - reasons failed to address material submitted by plaintiff - adjudicator failed to consider response to adjudication application as required by s 34(1)(a)(ii) - as a result adjudicator failed to make a bona fide attempt under s 33(1)(b) to determine on the balance of probabilities whether defendant liable to make a payment to the plaintiff – adjudicator also failed to comply with essential requirements of natural justice - purported adjudication determination a nullity – order in the nature of certiorari granted under O 56 of Supreme Court Rules quashing purported determination
Construction Contracts (Security of Payments) Act 2004(NT)
Supreme Court Rules 1987 (NT) O 56
Avopiling (NSW) Pty Ltd v Menard Bachy Pty Ltd [2012] NSWSC 1466; Bauen Constructions v Westwood Interiors [2010] NSWSC 1359; Brodyn Pty Ltd v Davenport (2004) 61 NSWLR 421; [2004]…
Keep reading for free
Create a free CaseChat account to read CH2M Hill Australia Pty Limited v ABB Australia Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2016] NTSC 42
- Decision Date
CaseChat Overview and Summary
The court first addressed the issue of whether the adjudicator's decision not to dismiss the application without a determination on the merits was reviewable. The court found that the decision was not reviewable if the adjudicator was satisfied that the matter was too complex to fairly determine within the prescribed time limits. The court emphasised that the adjudicator must be satisfied that it is not possible to fairly make a determination. However, the court held that the decision would be reviewable if the adjudicator's satisfaction that the matter was too complex was unreasonable. In this case, the court found that the adjudicator had not adequately engaged with the issues raised by the plaintiff and had failed to address the material submitted, leading to the conclusion that the decision was reviewable.
Further, the court examined whether the adjudicator's determination complied with the essential requirements of the Act and the principles of natural justice. The court found that the adjudicator had failed to provide reasons for the determination, which did not meaningfully engage with the issues raised by the plaintiff or address the material submitted. Additionally, the adjudicator had not considered the plaintiff's response to the adjudication application as required by the Act. The court concluded that these failures meant the adjudicator had not made a bona fide attempt to determine the dispute on the balance of probabilities, and had thereby failed to comply with the essential requirements of natural justice. As a result, the adjudicator's determination was a nullity.
Accordingly, the court granted the plaintiff's application for an order in the nature of certiorari under O 56 of the Supreme Court Rules, quashing the adjudicator's determination. The court also declared that the determination was of no effect. This outcome underscored the importance of adjudicators providing adequate reasons and engaging with the material submitted in adjudication proceedings.
Background
Background to the litigation
Decision
Reasons for decision
Ratio Decidendi