SUPREME COURT OF QUEENSLAND
CITATION:
Fulton Hogan Construction Pty Ltd v QH & M Birt Pty Ltd & Ors [2019] QSC 23
PARTIES:
FULTON HOGAN CONSTRUCTION PTY LTD (ACN 010 240 758)
(applicant)
v
QH & M BIRT PTY LTD (ACN 009 963 222)(first respondent)
and
KENNETH SPAIN (ADJUDICATOR J55780)
(second respondent)
and
THE ADJUDICATION REGISTRAR, QUEENSLAND BUILDING AND CONSTRUCTION COMMISSION
(third respondent)FILE NO:
BS 8527 of 2018
DIVISION:
Trial Division
PROCEEDING:
Originating Application
ORIGINATING COURT:
Supreme Court of Queensland at Brisbane
DELIVERED ON:
15 February 2019
DELIVERED AT:
Brisbane
HEARING DATE:
4 September 2018: hearing;
29 October 2018: Parties referred Court to additional decisions;
9 January 2019: Court advised parties that one of those additional decisions had been overturned on appeal (on 21 December 2018);
16 January 2019: further submissions received from applicant;
30 January 2019: further submissions received from first respondent.
JUDGE:
Ryan J
ORDER:
It is declared that one part of the adjudication decision of the Second Respondent, dated 30 July 2018, in relation to adjudication application number 367263 is void for jurisdictional error – that is the part identified as 1(a) in the Originating Application.
The parties are to confer, within 14 days of this order, with a view to agreeing upon the orders to be made to give effect to the declaration, including orders for injunctive relief and for costs.
Failing agreement, the parties are to provide written submissions as to the further orders to be made, including orders for injunctive relief and for costs, within 21 days of this order.
The hearing of the application is adjourned to a date to be fixed.
CATCHWORDS:
CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – REMUNERATION – STATUTORY REGULATION OF ENTITLEMENT TO AND RECOVERY OF PROGRESS PAYMENTS – ADJUDICATION OF PAYMENT CLAIMS – GENERALLY – Where it was argued that the adjudicator had exceeded his jurisdiction by adjudicating claims which were not included in the payment claim – where it was argued that the adjudicator had not valued work in accordance with the contract; denied natural justice or failed to give sufficient reasons
Australia Avenue Developments Pty Ltd v Icon Co (NSW) Pty Ltd [2018] NSWSC 1578
Avopiling (NSW) Pty Ltd v Menard Bachy Pty Ltd [2012] NSWSC 1466
Bauen Constructions v Westwood Interiors [2010] NSWSC 1359
BM Alliance Coal Operations Pty Ltd v BGC Contracting Pty Ltd [2012] QSC 346
Brookhollow Pty Ltd v R & R Consultants Pty Ltd [2006]
NSWSC 1
City of Ryde v AMFM Constructions Pty Ltd & Anor [2011]
NSWSC 1469
Coordinated Construction Co Pty Ltd v Climatech (Canberra) Pty Ltd (2005) 21 BCL 364
Cragcorp Pty Ltd v Qld Civil Engineering Pty Ltd & Ors
Creative Building Services Pty Ltd v TIO Air-conditioning Pty Ltd [2016] ACTSC 367
Downer Construction (Australia) Pty Ltd v Energy Australia (2007) 69 NSLWR 72
Futurepower Developments Pty Ltd v TJ & RF Fordham Pty
Ltd [2017] NSWSC 232
Halkat Electrical Contractors Pty Ltd v Holmwood Holdings
Pty Ltd [2007]…
Keep reading for free
Create a free CaseChat account to read Fulton Hogan Construction Pty Ltd v QH and M Birt Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2019] QSC 23
- Decision Date
CaseChat Overview and Summary
The legal issues before the court involved the validity of the adjudication decision made by the adjudicator, specifically whether the adjudicator had exceeded his jurisdiction by adjudicating claims not included in the payment claim, whether the adjudicator had valued the work in accordance with the contract, and if the adjudicator denied natural justice or failed to provide sufficient reasons. The court needed to determine whether the errors made by the adjudicator were of such a nature that they amounted to a constructive failure to exercise jurisdiction, thereby rendering the adjudication decision void.
The court examined the nature, gravity, and effect of the errors made by the adjudicator and assessed whether these errors were sufficient to cause practical injustice to the applicant, thereby vitiating the adjudication. The court concluded that the adjudicator had indeed made errors in his decision, which amounted to a jurisdictional error, leading to the part of the adjudication decision being void. The court ordered the parties to confer to agree on the orders to be made to give effect to the declaration, including orders for injunctive relief and for costs. If the parties could not agree, they were required to provide written submissions within 21 days.
The court issued a declaration that a part of the adjudication decision made by the second respondent was void for jurisdictional error. The parties were directed to confer within 14 days to agree on further orders to be made, including injunctive relief and costs. If they could not agree, written submissions were to be provided within 21 days. The hearing of the application was adjourned to a date to be fixed.
Orders
Orders of the court
It is declared that one part of the adjudication decision of the Second Respondent, dated 30 July 2018, in relation to adjudication application number 367263 is void for jurisdictional error – that is the part identified as 1(a) in the Originating Application.
The parties are to confer, within 14 days of this order, with a view to agreeing upon the orders to be made to give effect to the declaration, including orders for injunctive relief and for costs.
Failing agreement, the parties are to provide written submissions as to the further orders to be made, including orders for injunctive relief and for costs, within 21 days of this order.
The hearing of the application is adjourned to a date to be fixed.
Background
Background to the litigation
Decision
Reasons for decision
1. Whether the adjudicator had exceeded his jurisdiction by adjudicating claims which were not included in the payment claim.
2. Whether the adjudicator had not valued work in accordance with the contract.
3. Whether the adjudicator denied natural justice or failed to give sufficient reasons.
Held
1. The court held that the adjudicator had exceeded his jurisdiction by adjudicating claims which were not included in the payment claim. Specifically, the part of the adjudication decision identified as 1(a) in the Originating Application was declared void for jurisdictional error.
2. The court did not address whether the adjudicator had not valued work in accordance with the contract as this issue was not pursued during the hearing.
3. The court did not address whether the adjudicator denied natural justice or failed to give sufficient reasons as this issue was not pursued during the hearing.
Ratio Decidendi
Legal Principle Established
The court considered the nature, gravity, and effect of the errors made by the adjudicator, assessing whether they constituted a practical injustice to the plaintiff sufficient to vitiate the adjudication. The court noted that the adjudicator's failure to adhere to the scope of the payment claim and to consider all the submissions made by the parties constituted a breach of a basic and essential requirement of the Act. The court found that the adjudicator had not made a bona fide attempt to exercise his powers under the Act and that the plaintiff was denied natural justice to a degree sufficient to void the jurisdiction. The court thus declared that the part of the adjudication decision in question was void for jurisdictional error. The binding legal principle established by this decision is that an adjudicator must strictly adhere to the scope of the payment claim and consider all relevant submissions made by the parties in order to exercise his jurisdiction validly. The court did not distinguish, follow, or depart from prior authority in this regard.