Ausipile Pty Ltd v Bothar Boring and Tunnelling (Australia) Pty Ltd

Link copied
Case Copied 73 min read

SUPREME COURT OF QUEENSLAND

CITATION:

Ausipile Pty Ltd v Bothar Boring and Tunnelling (Australia) Pty Ltd [2021] QSC 39

PARTIES:

AUSIPILE PTY LTD (ACN 101 402 322)
(Applicant)
v
BOTHAR BORING AND TUNNELLING (AUSTRALIA) PTY LTD (ACN 622 309 264)

(Respondent)

FILE NO:

SC No 8953 of 2019

DIVISION:

Trial Division

PROCEEDING:

Originating Application

ORIGINATING COURT:

Supreme Court of Queensland at Brisbane

DELIVERED ON:

5 March 2021

DELIVERED AT:

Brisbane

HEARING DATES:

19 October 2020

20 October 2020

JUDGE:

Wilson J

ORDERS:

1. The application for judgment pursuant to section 78(2)(a) of the Act is dismissed.

2.   The question of costs is adjourned to a date to be fixed.

CATCHWORDS:

CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – REMUNERATION – STATUTORY REGULATION OF ENTITLEMENT TO AND RECOVERY OF PROGRESS PAYMENTS – PAYMENT CLAIMS – where the respondent engaged the applicant under a subcontract agreement to construct and design a secant pile launch shaft – where the applicant applied for judgment pursuant to s 78(2)(a) of the Building Industry (Security of Payment) Act 2017 (Qld) to recover amounts owing under a payment claim – where the parties accept that the applicant is entitled to judgment unless the respondent can establish a defence

CONSUMER PROTECTION – MISLEADING OR DECEPTIVE CONDUCT OR FALSE REPRESENTATIONS – CHARACTER OR ATTRIBUTES OF CONDUCT OR REPRESENTATION – SILENCE AND NON-DISCLOSURE – where the applicant’s operations manager and the respondent’s project manager discussed defects in the secant piles –  where there was a misunderstanding about whether the parties had agreed that the respondent would withhold further payment claims – where the respondent sent the applicant a letter saying that it would withhold further payment claims “as discussed” – where the applicant’s operations manager discussed the letter with its commercial manager – where the respondent had never previously provided payment schedules – where the applicant was silent in the face of the letter – whether the applicant’s silence was misleading or deceptive or likely to mislead or deceive  

CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – REMUNERATION – STATUTORY REGULATION OF ENTITLEMENT TO AND RECOVERY OF PROGRESS PAYMENTS – OTHER MATTERS – where the respondent submits there was a variation in the payment due dates under the subcontract – where the respondent submits that, because of this variation, the applicant did not issue a warning notice within the timeframes stipulated by s 99 of the Building Industry (Security of Payment) Act 2017 (Qld) – where the subcontract, new supplier form, tax invoices and payment claims contained different payment due dates – where the respondent did not consistently make payments in accordance with any of these due dates – whether the payment terms under the subcontract were varied

CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – REMUNERATION – STATUTORY REGULATION OF ENTITLEMENT TO AND RECOVERY OF PROGRESS PAYMENTS – PAYMENT CLAIMS  – where the respondent hired the applicant’s crawler crane in order to complete works under the head contract – where the applicant’s works under the subcontract had been completed…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Ausipile Pty Ltd v Bothar Boring and Tunnelling (Australia)... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2021] QSC 39
Decision Date

CaseChat Overview and Summary

Ausipile Pty Ltd, a subcontractor, engaged in a dispute with Bothar Boring and Tunnelling (Australia) Pty Ltd, the principal contractor, over progress payments under a subcontract agreement. Ausipile applied for judgment to recover amounts owing under a payment claim, pursuant to section 78(2)(a) of the Building Industry (Security of Payment) Act 2017 (Qld). The parties agreed that Ausipile was entitled to judgment unless Bothar could establish a defence. Bothar raised several defences, including claims of misleading or deceptive conduct by Ausipile, a variation in the payment due dates, and a void payment claim due to the inclusion of a variation amount for the hire of a crawler crane.

The court examined whether Ausipile's silence in the face of Bothar's letter withholding further payment claims was misleading or deceptive. It concluded that there was no evidence to support a finding that Ausipile's silence was misleading or deceptive or likely to mislead or deceive. The court also considered whether the payment terms under the subcontract had been varied. It found that there was no evidence of an agreement to vary the payment terms, and the differing payment due dates in the various documents did not constitute a variation. Finally, the court examined whether the payment claim was void due to the inclusion of a variation amount for the crawler crane hire. It held that the claim was not void, as the hire of the crawler crane was necessary to complete works under the head contract and the payment claim was not in relation to two contracts.

The court dismissed Ausipile's application for judgment and adjourned the question of costs to a later date. The court held that Bothar had established a defence to the payment claim, and therefore Ausipile was not entitled to judgment. The court did not make any orders as to costs, as the question was adjourned to a later date.

Orders

Orders of the court

1. The application for judgment pursuant to section 78(2)(a) of the Act is dismissed.

2. The question of costs is adjourned to a date to be fixed.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established