Cosmo Cranes and Rigging Pty Ltd v EQ Constructions Pty Ltd

Link copied
Case Copied 20 min read

District Court


New South Wales

Medium Neutral Citation: Cosmo Cranes & Rigging Pty Ltd v EQ Constructions Pty Ltd [2022] NSWDC 6
Hearing dates: 3 February 2022
Date of orders: 8 February 2022
Decision date: 08 February 2022
Jurisdiction:Civil
Before: Abadee DCJ
Decision:

See paragraph 42 – 43

Catchwords:

BUILDING AND CONSTRUCTION - two disputed payment claims issued - no payment schedules served within time - whether disputed payment claims claimed work under two or more construction contracts - whether, by reason of not serving payment schedules, respondent is prevented from asserting invalidity in payment claims

PRACTICE AND PROCEDURE - application for summary judgment - proceeding featured mixed claims of debt sourced under Security of Payment legislation, and alternative claims for breach of contract and a quantum meruit - respondent asserts work defective and involved delay - respondent pleads set-off (in statute and in equity) in answer to all claims and cross-claims for unliquidated damages - whether arguable equitable set off may arise against debt claim sourced in statute

Legislation Cited:

Building and Construction Industry Security of Payment Act 1999 (NSW) ss 13, 14, 15

Civil Procedure Act 2005 (NSW) s 21

Uniform Civil Procedure Rules 2002 (NSW) r 13.1

Cases Cited:

Ausipile Pty Ltd v Bothar Boring and Tunnelling (Australia) Pty Ltd [2021] QSC 39

Concut Pty Ltd v Worrell (2000) 176 ALR 693

HP Mercantile Pty Ltd v Dierickx (2013) 306 ALR 53; [2013] NSWCA 479

Southern Han Breakfast Point Pty Ltd v Lewence Construction Pty Ltd (2016) 260 CLR 340

TFM Epping Land Pty Ltd v Decon Australia Pty Ltd [2020] NSWCA 93

Ventia Australia Pty Ltd v BSA Advanced Property Solutions (Fire) Pty Ltd [2021] NSWSC 1534

Category:Procedural rulings
Parties: Cosmo Cranes & Rigging Pty Ltd (plaintiff/cross-defendant)
EQ Constructions Pty Ltd (defendant/cross-claimant)
Representation:

Counsel:
Mr M Langenheim for the plaintiff/cross-defendant
Mr D Hume for the defendant/cross-claimant

Solicitors:
Waring Legal for the plaintiff/cross-defendant
Vincent Young for the defendant/cross-claimant
File Number(s): 2021/00245698
Publication restriction: Nil

Judgment

INTRODUCTION

  1. This proceeding arises from the supply, under hire arrangements, of construction services between the plaintiff and the defendant entered into in and from April 2018. The services related to construction work performed by the defendant at a building site in Parramatta. The services were in the nature of crane hire and related services.

  2. By its statement of claim, the plaintiff pleaded three agreements; the first (pleaded at paragraph 3) being a subcontract (the ‘Hire Agreement’) through which a tower crane was supplied. This was a written agreement dated 20 April 2018. It is common ground that the Hire Agreement was a ‘construction contract’ for the purposes of the Building and Construction Industry Security of Payment Act 1999 (NSW) (the ‘Act’). The plaintiff alleged that the Hire Agreement was varied in April 2021 so that the plaintiff would supply a ‘Maeda’ mobile crane. The defendant denied the alleged variation. In the alternative, the plaintiff pleaded (at paragraph 5E) an agreement comprising the supply of a…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Cosmo Cranes and Rigging Pty Ltd v EQ Constructions Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2022] NSWDC 6
Decision Date

CaseChat Overview and Summary

Cosmo Cranes and Rigging Pty Ltd initiated proceedings against EQ Constructions Pty Ltd in the Queensland Civil and Administrative Tribunal, asserting claims for two disputed payment claims under the Security of Payment legislation. The respondent, EQ Constructions, argued that the payment claims were defective and invalid due to alleged defects and delays in the work. Additionally, EQ Constructions pleaded set-off in equity and under the statute against the claims, asserting unliquidated damages.

The primary legal issues before the court were whether the payment claims related to work performed under two or more construction contracts, and if the failure to serve payment schedules within the required time barred the respondent from asserting the invalidity of the payment claims. A further issue was whether an arguable equitable set-off could arise against the statutory debt claim.

The court found that the payment claims were valid and not invalid due to the respondent's failure to serve payment schedules within the stipulated time. The court held that the respondent was precluded from asserting the invalidity of the payment claims due to the late service of payment schedules. Additionally, the court found that an arguable equitable set-off could arise against the statutory debt claim. The respondent's claims for set-off were considered arguable, and the application for summary judgment was dismissed.

The court ordered that the application for summary judgment was dismissed, and the matter was to be determined at a hearing. The court further ordered that the respondent pay the applicant's costs of the application for summary judgment.

Orders

Orders of the court

See paragraph 42 – 43

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.