[2017] TASSC 71
COURT: SUPREME COURT OF TASMANIA
CITATION: Modscape Pty Ltd v Sive [2017] TASSC 71
PARTIES: MODSCAPE PTY LTD
v
SIVE, Jonathan
FILE NO: 50/2017
DELIVERED ON: 11 December 2017
DELIVERED AT: Hobart
HEARING DATE: 17 October 2017
JUDGMENT OF: Blow CJ
CATCHWORDS:
Contracts – Building, engineering and related contracts – Remuneration – Statutory regulation of entitlement to and recovery of progress payments – Adjudication of payment claims – Adjudicator deciding dispute on points not contended for by either party – Inadequate reasons – Denial of natural justice.
Building and Construction Industry Security of Payment Act2009 (Tas), s 25(2), (4)(b).
Musico v Davenport [2003] NSWSC 977; Coordinated Constructions Co Pty Ltd v Climatech (Canberra) Pty Ltd [2005] NSWCA 229, 21 BCL 364; Procorp Civil Pty Ltd v Napoli Excavations and Contracting Pty Ltd [2006] NSWSC 205; Brodyn Pty Ltd v Davenport [2004] NSWCA 394, 61 NSWLR 421; Timwin Construction v Facade Innovations [2005] NSWSC 548, 21 BCL 383; Laing O'Rourke Australia Construction Pty Ltd v H & M Engineering & Construction Pty Ltd [2010] NSWSC 818; Clyde Bergemann v Varley Power [2011] NSWSC 1039; Theiss Pty Ltd v Warren Brothers Earthmoving Pty Ltd [2012] QSC 373, referred to.
Aust Dig Contracts [279.6]
REPRESENTATION:
Counsel:
Applicant: C Groves
Fairbrother Pty Ltd: B J Murphy
Solicitors:
Applicant: Dobson Mitchell Allport
Fairbrother Pty Ltd: Tierney Law
Judgment Number: [2017] TASSC 71
Number of paragraphs: 62
Serial No 71/2017
File No 50/2017
MODSCAPE PTY LTD v JONATHAN SIVE
REASONS FOR JUDGMENT BLOW CJ
11 December 2017
This case concerns a dispute as to the validity of an adjudication determination made, or purportedly made, pursuant to the Building and Construction Industry Security of Payment Act 2009 ("the Act"). The determination related to a dispute between Modscape Pty Ltd, the applicant in these proceedings, and a company named Fairbrother Pty Ltd. The respondent to this application, Jonathan Sive, was the adjudicator who made the impugned determination. The applicant is seeking an order in the nature of certiorari for the quashing of the determination. Alternatively, it seeks a declaration that the determination is void.
On 22 February 2017, Holt AsJ made a general order requiring the respondent to show cause why the relief sought should not be granted. The respondent has advised that he does not intend to participate in the proceedings, and that he will submit to the orders of the Court, except in relation to costs. Fairbrother Pty Ltd was represented by counsel at the hearing before me. It contends that the determination was unimpeachable and that the proceedings should therefore be dismissed.
The background to this dispute can be summarised as follows:
· Some years ago the Tasmanian Government decided to redevelop the Royal Hobart Hospital.
· The State engaged Fairbrother Pty Ltd as a head contractor to construct a temporary building for the purpose of the redevelopment work.
· Fairbrother entered into a subcontract…
Continue reading Modscape Pty Ltd v Sive
Sign in free to access the full text
- AGLC
- Modscape Pty Ltd v Sive [2017] TASSC 71
- Case
- [2017] TASSC 71
- Decision Date
CaseChat Overview and Summary
The court examined whether the adjudicator's decision was in accordance with the statutory provisions under which it was made. The court noted that the adjudicator made findings on points that were not argued by either party and provided reasons that were inadequate and failed to address the specific contentions made by the parties. The court held that the adjudicator's failure to address the actual points of contention and provide adequate reasons amounted to a denial of natural justice. This failure rendered the adjudicator's decision invalid, as it did not comply with the statutory requirements for the adjudication process.
Consequently, the court found that the adjudicator's decision was not binding on the parties and could not be enforced. The court also noted that Modscape was not precluded from pursuing its claim for payment through other available legal processes. The court ordered that the matter be remitted to a new adjudicator for a fresh determination of the payment claim, in accordance with the statutory requirements.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.