CITATION: Coordinated Construction Co v J M Hargreaves & Ors [2005] NSWSC 77
HEARING DATE(S): 3 February 2005, 9 February 2005
JUDGMENT DATE :
22 February 2005JUDGMENT OF: McDougall J at 1
DECISION: See para [63] of judgment
CATCHWORDS: BUILDING AND CONSTRUCTION - progress payment - adjudicator's determination - basic and essential requirements of a valid determination - whether determination void because adjudicated amount included amounts assumed (but not decided) not to be "for" construction work - whether determination in breach of the Building and Construction Industry Security of Payment Act 1999 is unlawful - whether payment claim served on or from reference date
LEGISLATION CITED: Building and Construction Industry Security of Payment Act 1999
CASES CITED: Brodyn Pty Ltd v Davenport [2004] NSWCA 394
De Martin & Gasparini v Energy Australia [2002] NSWCA 330
Project Blue Sky Inc v Australian Broadcasting Authority (1998) 194 CLR 355
Kembla Coal & Coke v Select Civil [2004] NSWSC 628
Quasar Constructions v Demtech Pty Ltd [2004] NSWSC 116
Rothnere v Quasar [2004] NSWSC 1151
TransGrid v Siemens Ltd [2004] NSWCA 395PARTIES: Coordinated Construction Co Pty Limited (Plaintiff)
J M Hargreaves (NSW) Pty Limited (First Defendant)
John Parnell (Second Defendant)
Peter Sarlos (Third Defendant)
LEADR (Fourth Defendant)FILE NUMBER(S): SC 55086/04
COUNSEL: M G Rudge SC/M Christie (Plaintiff)
D D Feller SC/D Loewenstein (First Defendant)SOLICITORS: Colin Biggers & Paisley (Plaintiff)
James R Knowles Lawyers Pty Limited (First Defendant)
LOWER COURT JURISDICTION:
COORDINATED CONSTRUCTION CO PTY LIMITED
v
J M HARGREAVES (NSW) PTY LIMITED & ORS
55086/04
Index to Judgment
Para
The issues 2 The subcontract 6 Hargreaves’ claims 12 EOT 1 (V 36) 13 EOT 2 (V 37) 14 EOTs 3 to 6 (V 64, V 80, V 97 and V 105) 15 The interest claims 17 V 65 and V 94 19 The extension of time granted 21 Mr Makin’s determination 24 Mr Parnell’s determination 25 Mr Sarlos’ determination 33 First and second issues: “delay damages”, interest 36 The second question: the Brodyn argument 41 Alternative argument based on Project Blue Sky 54 Third and fourth issues: interest - point not taken or “de minimis” 56 Fifth and sixth issues: EOTs 3 to 6 57 Seventh and eighth issues: escalation costs claims 1 and 2 – s 22(4) 59 Ninth issue – reference date 61 Conclusion and order 63
IN THE SUPREME COURT
OF NEW SOUTH WALES
EQUITY DIVISION
TECHNOLOGY AND CONSTRUCTION LIST
McDOUGALL J
22 February 2005
55086/04 COORDINATED CONSTRUCTION CO PTY LIMITED v
J M HARGREAVES (NSW) PTY LIMITED & ORS
JUDGMENT
1 HIS HONOUR: The plaintiff (Coordinated) and the first defendant (Hargreaves) are parties to a subcontract under which Hargreaves agreed to carry out certain work in connection with the redevelopment of the former Gazebo Hotel at Elizabeth Bay. Hargreaves made a number of what it said were payment claims under the Building and Construction Industry Security of Payment Act 1999 (the Act). In at least three cases, those claims were disputed. They proceeded to…
Keep reading for free
Create a free CaseChat account to read Coordinated Construction Co v J M Hargreaves and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2005] NSWSC 77
- Decision Date
CaseChat Overview and Summary
The court examined the requirements of a valid determination under the Act and found that the adjudicator had not fulfilled the basic and essential requirements. The adjudicator had not decided the disputed amount; instead, the adjudicator assumed that certain amounts were not for construction work and included them in the determination. The court held that this assumption was not a decision and therefore, the determination was void. Additionally, the court found that the determination was in breach of the Act because it was not made in accordance with the basic and essential requirements. The court also considered whether the payment claim was served on or from the reference date and concluded that it was. Consequently, the determination was not unlawful because it did not breach the Act. The court found that the determination was invalid and unenforceable.
In conclusion, the Supreme Court of New South Wales held that the adjudicator's determination was invalid and unenforceable. The court found that the determination was void because the adjudicator had not decided the disputed amount and had instead assumed that certain amounts were not for construction work. The court also found that the determination was not in breach of the Act because the payment claim was served on or from the reference date. The court did not make any orders for payment of the adjudicated amount.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.