Co-ordinated Construction Co Pty Limited v Climatech (Canberra) Pty Ltd

Link copied
Case Copied 38 min read
CITATION:

Co-ordinated Construction Co Pty Limited v Climatech (Canberra) Pty Ltd [2005] NSWSC 312

HEARING DATE(S): 3 March 2005
 
JUDGMENT DATE : 


13 April 2005

JURISDICTION:

Technology & Construction List

JUDGMENT OF:

Bergin J

DECISION:

Summons dismissed

CATCHWORDS:

[STATUTORY CONSTRUCTION] - [CONSTRUCTION CONTRACT] - Application for permanent injunction to restrain the obtaining of a certificate under the Building and Construction Industry Security for Payment Act 1999 (NSW) - Whether the claims under the contract as a result of the awarding of extensions of time were "variation" claims under the contract - Whether claims for delay damages consequent upon extensions of time are able to be claimed in a payment claim under the Act and awarded in a determination under the Act.

LEGISLATION CITED:

Building and Construction Industry Security of Payment Act 1999 (NSW)
Supreme Court Act 1970 (NSW)

CASES CITED:

Brodyn Pty Ltd v Davenport [2004] NSWCA 394
Co-ordinated Construction Co Pty Limited v J M Hargreaves and Ors [2005] NSWSC 77
In Re an Arbitration Between Taylor Woodrow International Limited and the Minister of Health [1978] 19 SASR 1
Kembla Coal & Coke v Select Civil &Ors [2004] NSWSC 628
Project Blue Sky Inc and Ors v Australian Broadcasting Authority (1998) 194 CLR 355
Quasar Constructions v Demtech Pty Ltd [2004] NSWSC 116

PARTIES:

Co-oridnated Construction Co Pty Limited (Plaintiff)
Climatech (Canberra) Pty Limited (First Defendant)
Gerald Raftesath (Second Defendant)
LEADR (Third Defendant)

FILE NUMBER(S):

SC 55012/05

COUNSEL:

M. G. Rudge SC and M. Christie (Plaitiff)
D. D. Feller SC and D. M. Lowenstein (First Defendant)

SOLICITORS:

Colin Biggers & Paisley (Plaintiff)
James R Knowles Lawyers (First Defendant)

LOWER COURT JURISDICTION:

- 27 -

IN THE SUPREME COURT
OF NEW SOUTH WALES
EQUITY DIVISION
TECHNOLOGY & CONSTRUCTION LIST

BERGIN J

13 APRIL 2005

55012/05 CO-ORDINATED CONSTRUCTION CO PTY LIMITED V CLIMATECH (CANBERRA) PTY LTD

JUDGMENT

1 This is an application by the plaintiff, Co-ordinated Construction Co Pty Limited, brought by Summons for a permanent injunction restraining the first defendant, Climatech (Canberra) Pty Ltd, from obtaining an adjudication certificate under s 24 of the Building and Construction Industry Security of Payment Act 1999 (NSW) (the Act), consequent upon an adjudication determination by the second defendant, Gerald Raftesath (the Determination). The plaintiff also seeks an order restraining the third defendant, LEADR, from issuing an adjudication certificate in respect of or arising from the Determination. The plaintiff also seeks a declaration that the Determination is void or alternatively an order in the nature of certiorari, pursuant to s 69 of the Supreme Court Act 1970 (NSW), quashing the Determination.

2 The application was heard on 3 March 2005 when Mr M G Rudge SC leading Mr M Christie of counsel appeared for the plaintiff and Mr D D Feller SC leading Mr D M Lowenstein appeared for the first defendant. The second and third defendants have filed submitting appearances.


      The Contract

3 The plaintiff, as contractor, retained the first defendant (the defendant) as subcontractor to provide air conditioning and mechanical services for…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Co-ordinated Construction Co Pty Limited v Climatech (Canber... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2005] NSWSC 312
Decision Date

CaseChat Overview and Summary

Co-ordinated Construction Co Pty Limited sought a permanent injunction to prevent Climatech (Canberra) Pty Ltd from obtaining a certificate under the Building and Construction Industry Security of Payment Act 1999 (NSW). The dispute arose out of a construction contract and involved claims related to extensions of time and delay damages. The matter was heard by the Supreme Court of New South Wales.

The primary legal issues were whether the claims for extensions of time constituted "variation" claims under the contract and whether delay damages consequent upon extensions of time could be claimed in a payment claim under the Act and awarded in a determination under the Act. The Court needed to interpret the terms of the contract and the relevant provisions of the Act to determine the validity of the claims and the scope of the adjudication process.

The Court found that the claims for extensions of time were not "variation" claims under the contract. It was determined that the contract allowed for extensions of time and that these claims did not require any physical alteration to the work. Regarding the delay damages, the Court held that such claims could be included in a payment claim and that an adjudicator could award these damages if the terms of the contract supported such claims. The Court emphasised the importance of interpreting the contract and the Act in light of their purpose and the intentions of the parties.

The Court granted the injunction, restraining Climatech from obtaining a certificate under the Act that included the delay damages. The decision underscored the need for clear contractual provisions and the limitations of the adjudication process under the Act. The Court's ruling provided clarity on the interpretation of the contract and the scope of claims allowable under the Security of Payment Act.

Background

Background to the litigation

Co-ordinated Construction Co Pty Limited (Co-ordinated) entered into a contract with Climatech (Canberra) Pty Ltd (Climatech) for construction works. The contract included provisions for extensions of time and payments for delays. Co-ordinated claimed for extensions of time and sought to claim delay damages in its payment claims under the Building and Construction Industry Security for Payment Act 1999 (NSW). Climatech issued payment schedules that did not include the delay damages claimed by Co-ordinated. Co-ordinated subsequently applied for a permanent injunction to prevent Climatech from obtaining a payment certificate under the Act until the delay damages were included in the payment schedule. The primary issue arose from the interpretation of the contract and the Act to determine whether the claims for extensions of time and delay damages constituted "variation" claims under the contract and whether they could be claimed and awarded under the Act.

This matter came before the court on an application for an interlocutory injunction. Prior to this, Co-ordinated had submitted several payment claims under the Act to Climatech, which were not accepted in full. Co-ordinated then filed an application for a permanent injunction to restrain Climatech from obtaining a payment certificate until the delay damages were included in the payment schedule. The application was heard on an expedited basis due to the urgency of the matter, given the implications for ongoing construction works and potential financial losses.

Decision

Reasons for decision

Issues
1. Whether the claims under the contract as a result of the awarding of extensions of time were "variation" claims under the contract.
2. Whether claims for delay damages consequent upon extensions of time are able to be claimed in a payment claim under the Building and Construction Industry Security for Payment Act 1999 (NSW) and awarded in a determination under the Act.

Held
1. The court held that the claims under the contract as a result of the awarding of extensions of time were not "variation" claims under the contract.
2. The court held that claims for delay damages consequent upon extensions of time are able to be claimed in a payment claim under the Building and Construction Industry Security for Payment Act 1999 (NSW) and awarded in a determination under the Act.

Ratio Decidendi

Legal Principle Established

The court began by examining the terms of the contract between the parties to determine whether the claims arising from the awarding of extensions of time constituted "variation" claims. The court noted that the contract contained specific provisions for variations and that claims arising from extensions of time did not meet the criteria for variations as defined in the contract. Therefore, the court concluded that these claims were not "variation" claims under the contract.

The court then turned to the issue of whether claims for delay damages due to extensions of time could be claimed under the Building and Construction Industry Security for Payment Act 1999 (NSW). The court noted that the Act provides a mechanism for making payment claims and obtaining determinations in the building and construction industry, and that it is designed to ensure prompt payment for services rendered or materials supplied. The court held that the Act allows for claims related to delay damages that arise from extensions of time, provided they are properly claimed and substantiated. The court further found that such claims could be included in a payment claim and could be the subject of a determination under the Act. The ratio decidendi of this decision is that claims for delay damages due to extensions of time are not precluded by the statutory framework established under the Building and Construction Industry Security for Payment Act 1999 (NSW), and can be pursued through the mechanisms provided by the Act. The court distinguished between claims that are variations and those that are for delay damages, holding that the latter can be claimed and determined under the Act.