SUPREME COURT OF QUEENSLAND
CITATION:
Civmec Electrical & Instrumental Pty Ltd v Southern Cross Electrical Engineering Limited & Ors [2019] QSC 300
PARTIES:
CIVMEC ELECTRICAL & INSTRUMENTAL PTY LTD
ABN 20 153 261 511(applicant)
v
SOUTHERN CROSS ELECTRICAL ENGINEERING LIMITED
ABN 92 009 307 046(first respondent)
RUSSELL WELSH ADJUDICATOR NO. J79539
(second respondent)
THE ADJUDICATION REGISTRAR, QUEENSLAND BUILDING AND CONSTRUCTION COMMISSION
(third respondent)FILE NO:
BS7233 of 2019
DIVISION:
Trial Division
PROCEEDING:
Originating application
DELIVERED ON:
13 December 2019
DELIVERED AT:
Brisbane
HEARING DATE:
13 September 2019
JUDGE:
Mullins J
ORDER:
1. Originating application is dismissed.
CATCHWORDS:
CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – REMUNERATION – STATUTORY REGULATION OF ENTITLEMENT TO AND RECOVERY OF PROGRESS PAYMENTS – ADJUDICATION OF PAYMENT CLAIMS – where the applicant challenges the adjudicator’s decision for jurisdictional error – where the adjudicator did not have regard to submissions made by the applicant in the adjudication response which he decided were outside the reasons given in the payment schedule – whether it was within the adjudicator’s jurisdiction to decide whether the submissions were properly made
CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – REMUNERATION – STATUTORY REGULATION OF ENTITLEMENT TO AND RECOVERY OF PROGRESS PAYMENTS – ADJUDICATION OF PAYMENT CLAIMS – where the applicant challenges the adjudicator’s decision for jurisdictional error – whether the adjudicator should have considered the pre-adjudication correspondence between the parties to give context to the reasons in the payment schedule for withholding payment
Building Industry Fairness (Security of Payment) Act 2017 (Qld), s 76, s 82, s 85, s 86, s 88, s 101
Bezzina Developers Pty Ltd v Deemah Stone (Qld) Pty Ltd [2008] 2 Qd R 495; [2008] QCA 213, considered
Clarence Street Pty Ltd v Isis Projects Pty Ltd (2005) 64 NSWLR 448; [2005] NSWCA 391, cited
Coordinated Construction Co Pty Ltd v Climatech (Canberra) Pty Ltd (2005) 21 BCL 364; [2005] NSWCA 229, considered
Craig v South Australia (1995) 184 CLR 163; [1995] HCA 58, considered
Façade Treatment Engineering Pty Ltd (in liq) v Brookfield Multiplex Constructions Pty Ltd (2016) 337 ALR 452; [2016] VSCA 247, cited
John Holland Pty Ltd v Roads & Traffic Authority of New South Wales (2007) 23 BCL 205; [2007] NSWCA 19, considered
Kirk v Industrial Court (NSW) (2010) 239 CLR 531; [2010] HCA 1, considered
Multiplex Constructions Pty Ltd v Luikens [2003] NSWSC 1140, considered
Northbuild Construction Pty Ltd v Central Interior Linings Pty Ltd [2012] 1 Qd R 525; [2011] QCA 22, considered
Pittwater Council v Keystone Projects Group Pty Ltd [2014] NSWSC 1791, considered
State Water Corporation v Civil Team Engineering Pty Ltd [2013] NSWSC 1879, considered
Thiess Pty Ltd v Warren Brothers Earthmoving Pty Ltd [2012] QSC 373, considered
Trysams Pty Ltd v Club Constructions (NSW) Pty Ltd [2007] NSWSC 941, citedCOUNSEL:
N Andreatidis QC and F J Chen for the applicant
M H Hindman QC and M J…
Keep reading for free
Create a free CaseChat account to read Civmec Electrical and Instrumental Pty Ltd v Southern Cross... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2019] QSC 300
- Decision Date
CaseChat Overview and Summary
The court examined the adjudicator's reasoning and found that the adjudicator did not consider certain submissions made by the applicant that went beyond the reasons given in the payment schedule. The adjudicator noted that these submissions were not contemplated in the statutory requirements and therefore were not considered. The court held that it was within the adjudicator's jurisdiction to decide whether these submissions were properly made and whether they should be considered. Additionally, the court concluded that the adjudicator should have taken into account the pre-adjudication correspondence to provide context to the reasons in the payment schedule, as this correspondence was relevant to the understanding of the claims and the reasons for withholding payment.
The court dismissed the originating application, affirming the adjudicator's decision. The adjudicator's approach to the claims was found to be consistent with the statutory requirements, and the reasons provided in the payment schedule were deemed sufficient for withholding payment. The court found no jurisdictional error in the adjudicator's decision, and thus, the application was unsuccessful.
Orders
Orders of the court
1. Originating application is dismissed.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
The submissions at the hearing in respect of the Group C claims were developed by reference to claim 9 in Group C. The applicant relied on the same arguments in relation to the other claims in the Group C. There is no basis to reach a different outcome on this application in relation to those other claims, than for claim 9 in Group C. Group D claims - acceleration Group D comprised acceleration claims. To illustrate the applicant’s complaints, submissions focused on claim 15 in Group D which was an acceleration claim for additional management personnel. The applicant’s response in the payment schedule for this claim (which was exactly the same response for all Group D claims) was as follows:“Non-compliance with Subcontract timeframes.No entitlement (See E105-CIV-SCE-131)Subcontractor has not accounted for its own delays and inefficiencies.Subcontractor has failed to demonstrate compliance with the Subcontract procedureSubcontractor failed to meet the requisite time limits as a precondition to any entitlement” The applicant had assessed all claims in Group D at an amount of nil in its payment schedule. The total amount for the Group D claims made by the respondent in its claim was $5,528,842 plus GST that was revised down to $4,643,116.74 plus GST in the adjudication application based on the respondent’s expert report of Mr Worthington. The adjudicator dealt with the generic reasons for the applicant’s refusal of the Group D claims at [1136] to [1139] of the adjudication decision. The adjudicator found at [1136] that “Non-compliance with Subcontract timeframes” was very general and non-specific and was not a valid reason for withholding payment. The same conclusions were applied at [1138] to the reason “Subcontractor has not accounted for its own delays and inefficiencies”. The adjudicator noted at [1139] that in asserting “Subcontractor failed to meet the requisite time limits as a precondition to any entitlement” the applicant had not detailed which provision in the Subcontract upon which it relied to reject the claims and it was therefore not a valid reason for withholding payment. As for the same reasons relied on for the Group C claims, the adjudicator treated the fifth reason in the payment schedule as the detail for the fourth reason. At [1137], the adjudicator observed that, in respect of the reason “No entitlement (See E105-CIV-SCE-131)”, the applicant had provided its response to the respondent’s acceleration claim in which it rejected the claim entirely. It is apparent therefore that the adjudicator had regard to the contents of letter #131 to the extent that it dealt with the applicant’s position on why the respondent had no entitlement to make the acceleration claim. The adjudicator then analysed the Group D claims by reference to entitlement and quantum. The adjudicator noted at [1142] the respondent’s position that:“… it is entitled to acceleration costs for the respondent’s direction to accelerate the performance of the Works pursuant to GCS clause 48.1, which it says falls under the definition of ‘variation’ under GCS clause 1 and for which it is entitled to an adjustment of the subcontract price pursuant to GCS clause.”