IN THE SUPREME COURT OF VICTORIA Not Restricted AT MELBOURNE
COMMERCIAL COURT
TECHNOLOGY ENGINEERING AND CONSTRUCTION LISTS ECI 2017 00163
WESTBOURNE GRAMMAR SCHOOL Plaintiff v GEMCAN CONSTRUCTIONS PTY LTD & ORS Defendants ---
JUDGE:
ROBSON J
WHERE HELD:
Melbourne
DATE OF HEARING:
2 October 2017
DATE OF JUDGMENT:
26 October 2017
CASE MAY BE CITED AS:
Westbourne Grammar School v Gemcan Constructions Pty Ltd
MEDIUM NEUTRAL CITATION:
[2017] VSC 645
---
BUILDING AND CONSTRUCTION – Application for certiorari by the principal under a building contract – Determination by an adjudicator in favour of builder under an adjudication under the Building and Construction Industry Security of Payment Act 2002 (Vic) – Whether ‘show cause’ validly given to builder – Whether s 48 of the Building and Construction Security of Payment Act 2002 (Vic) rendered void a clause entitling the principal to take over the balance of the works and to suspend builder’s entitlement to payment under the contract – Section 48 of the Building and Construction Industry Security of Payment Act 2002 (Vic) not enlivened – Southern Han Breakfast Points Pty Ltd v Lewence Constructions Pty Ltd [2016] HCA 52 applied – Whether show cause notice validly specified the date and time in which the builder was to show cause – Application granted.
---
APPEARANCES:
Counsel Solicitors For the Plaintiff Mr R Andrew Champions Lawyers For the Defendants Mr L J Connolly Maddocks Lawyers HIS HONOUR:
Introduction
1 A builder, Gemcan Constructions Pty Ltd (Gemcan), obtained an adjudication determination under the Building and Construction Industry Security of Payment Act 2002 (Vic) (the Act) that it be paid by the principal, Westbourne Grammar School (Westbourne), $241,073.33 for work done under a construction contract between Gemcan and Westbourne. Westbourne seeks an order quashing the adjudication on the grounds of jurisdictional error by the adjudicator and errors of law on the record.
2 For the following reasons, the Court allows the application and quashes the adjudication.
The Background facts
3 On 25 July 2016, Gemcan was engaged by Westbourne under a contract, to construct alterations to Westbourne’s Williamstown campus (the contract).
4 Under clause 39 of the contract, if Gemcan committed a substantial breach of the contract, Westbourne could by hand, or by certified post, give to Gemcan a written notice to show cause.
5 Clause 39 of the contract provided that a show cause notice was to state, inter alia, that Gemcan was required to show cause, in writing, as to why Westbourne should not exercise a right conferred by subclause 39.4, and the date and time by which Gemcan must show cause, which should not be less than 7 clear days after the notice was received by the Contractor.
6 Subclause 39.4 provided that if Gemcan failed to show reasonable cause by the stated date and time, Westbourne could by written notice to Gemcan, take out of Gemcan’s hands the whole or part of the work remaining to be completed and suspend payment to Gemcan until such payment becomes due and…
Keep reading for free
Create a free CaseChat account to read Westbourne Grammar School v Gemcan Constructions Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2017] VSC 645
- Decision Date
CaseChat Overview and Summary
The court considered whether the 'show cause' notice was validly issued under the Act. It examined if section 48 of the Act rendered void a clause in the contract that allowed the principal to take over the balance of the works and suspend payment. The court applied the principles from the case Southern Han Breakfast Points Pty Ltd v Lewence Constructions Pty Ltd [2016] HCA 52 to assess the validity of the 'show cause' notice and the contractual clause. The court found that section 48 of the Act did not render void the clause allowing the principal to take over the works. Additionally, the court determined that the 'show cause' notice was validly issued as it correctly specified the date and time for Gemcan to show cause.
The Supreme Court granted the application for certiorari, thereby quashing the adjudication decision. The court held that the 'show cause' notice was validly issued, and the clause allowing the principal to take over the balance of the works and suspend payment remained enforceable. The court's decision was based on the proper interpretation of the Building and Construction Industry Security of Payment Act 2002 (Vic) and the relevant case law. The final orders included the quashing of the adjudication decision and the enforcement of the contractual clause allowing the principal to take over the works and suspend payment.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.