DISTRICT COURT OF QUEENSLAND
CITATION:
Feenix Queensland Pty Ltd v Grocon Constructions (QLD) Pty Ltd [2012] QDC 346
PARTIES:
Feenix Queensland Pty Ltd ACN 007 940 170
(Applicant)v
Grocon Constructions (QLD) Pty Ltd ACN 120 476 495
(Respondent)FILE NO:
156/2012
PROCEEDING:
Application for Judgment
ORIGINATING COURT:
District Court, Southport
DELIVERED ON:
19 June 2012
DELIVERED AT:
Southport
HEARING DATE:
5 May 2012
JUDGE:
Judge C F Wall QC
ORDER:
Application for judgment dismissed with costs assessed on standard basis unless agreed
LEGISLATION:
Building & Constructions Industry Payments Act 2004, Sections 7, 8, 12, 13(a), 17, 18, 19,
CASES:
Trysams Pty Ltd v Club Constructions (NSW) Pty Ltd [2008] NSWSC 399
Nepean Engineering Pty Ltd v Total Process Services Pty Ltd (2005) 64 NSWLR 462
Brookhollow Pty Ltd v R & R Consultants Pty Ltd, unrep, [2006] NSWSC
Simcorp Developments & Constructions Pty Ltd v Gold Coast Titans (Property) Pty Ltd & Others, unrep, [2010] QSC 162CATCHWORDS:
BUILDING & CONSTRUCTION – application for judgment pursuant to s19 Building and Construction Industry Payments Act 2004 (Qld) – payment claims by applicant previously paid by respondent – whether applicant able to rely on further (second) payment claims for the same subject matter by using a different reference date in circumstances where respondent did not serve a payment schedule in respect of those claims – whether second payment claims valid.
COUNSEL:
Mr G Beacham for the applicant
Mr M Steele for the respondent
SOLICITORS:
Cronin Litigation for the applicant
Norton Rose Australia for the respondent
DISTRICT COURT OF QUEENSLAND
REGISTRY: SOUTHPORT
NUMBER: 156/12
Applicant: FEENIX QUEENSLAND PTY LTD
ACN 007 940 170
AND
Respondent: GROCON CONSTRUCTIONS (QLD) PTY LTD
ACN 120 476 495
JUDGMENT
Delivered the 19th day of June 2012
This is an application for judgment pursuant to s.19 of the Building & Construction Industry Payments Act 2004 (“the Act”) for $218,698.
The applicant relies on 3 payment claims served on the respondent on 14 December 2011 (the second payment claims). Leaving aside the plaintiff’s contention that the second payment claims lacked the particularity required by s.17(1) of the Act, payment claims by the applicant for the same subject matter and amounts dated 1 November 2010 (the first payment claims) had previously been served on the respondent and paid by the respondent. In respect of the first payment claims no payment schedule was served on the claimant applicant by the respondent.
The reference date for the first payment claims was end October 2010 and for the second payment claims, end November 2011.
Section 12 of the Act provides:
“12 Rights to progress payments
From each reference date under a construction contract, a person is entitled to a progress payment if the person has undertaken to carry out construction work or supply related goods and services, under the contract.”
The Dictionary in Schedule 2 of the Act provides:
“reference date, under a construction contract, means –
(a) a date stated in, or worked out under,…
Keep reading for free
Create a free CaseChat account to read Feenix Queensland Pty Ltd v Grocon Constructions (Qld) Pty L... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2012] QDC 346
- Decision Date
CaseChat Overview and Summary
The court had to determine if Feenix could legitimately use a different reference date for their second payment claims, and if these claims were valid in the absence of a payment schedule from Grocon. The court examined the statutory framework and relevant case law to understand the interaction between the Building and Construction Industry Payments Act 2004 (Qld) and the respondent's obligation to issue a payment schedule. The court found that the statutory provisions and existing precedents did not support Feenix's ability to rely on second payment claims without a payment schedule from Grocon. The court reasoned that the absence of a payment schedule precluded the validity of Feenix's second claims, as the statutory mechanism for resolving disputes requires such a document.
As a result, the court dismissed Feenix's application for judgment under section 19 of the Building and Construction Industry Payments Act 2004 (Qld). The court ordered that the costs of the proceedings be assessed on the standard basis, unless the parties could agree otherwise. This decision highlights the importance of timely and proper compliance with statutory requirements in the building and construction industry, particularly in relation to payment schedules and claims.
Orders
Orders of the court
Application for judgment dismissed with costs assessed on standard basis unless agreed
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.