St Hilliers Contracting Pty Limited v Dualcorp Civil Pty Ltd

Link copied
Case Copied 18 min read
CITATION: St Hilliers Contracting Pty Limited v Dualcorp Civil Pty Ltd [2010] NSWSC 1468
HEARING DATE(S): 2 & 6 December 2010
JUDGMENT OF: Hammerschlag J
EX TEMPORE JUDGMENT DATE: 6 December 2010
DECISION: The Adjudicator’s Adjudication Determination dated 22 February 2010 be quashed and set aside. The money standing in Court forthwith to be paid out to the plaintiff. The first defendant to pay the plaintiff's costs of the proceedings
CATCHWORDS: CONTRACT – building, engineering and related contracts – Building and Construction Industry Security of Payment Act 1999 ss 10(1), 11(1), 11(1)-(2), 22(1)-(4) – the plaintiff challenged an adjudication determination in favour of the first defendant by the second defendant on grounds that the second defendant committed jurisdictional error and did not afford it natural justice because she did not have regard to material properly before her and determined the date for payment for the adjudicated amount on a basis which was not the subject of submission by either party – HELD – that both complaints were made out – there should be an order in the nature of certiorari quashing and setting aside the adjudication determination
LEGISLATION CITED: Building and Construction Industry Security of Payment Act 1999 (NSW)
CASES CITED: Chase Oyster Bar v Hamo Industries [2010] NSWCA 190
Bauen Constructions v Westwood Interiors [2010] NSWSC 1359
Laing O’Rourke Australia Construction v H&M Engineering & Construction [2010] NSWSC 818
Trysams Pty Ltd v Club Constructions (NSW) Pty Ltd [2008] NSWSC 399
PARTIES: St Hilliers Contracting Pty Limited [Plaintiff]
Dualcorp Civil Pty Ltd [First Defendant]
Helen Durham [Second Defendant]
FILE NUMBER(S): SC 2010/66117
COUNSEL: M.G. Rudge SC with D.A.C. Robertson [Plaintiff]
M.A. Ashhurst SC [First Defendant]
SOLICITORS: Colin Biggers & Paisley [Plaintiff]
Moray & Agnew [First Defendant]
- 1 -

IN THE SUPREME COURT
OF NEW SOUTH WALES
EQUITY DIVISION
TECHNOLOGY & CONSTRUCTION LIST

HAMMERSCHLAG J

6 DECEMBER 2010

2010/66117 ST. HILLIERS CONTRACTING PTY LTD V DUALCORP CIVIL PTY LTD

EX TEMPORE JUDGMENT

INTRODUCTION

1 HIS HONOUR: By its Further Amended Summons dated 24 May 2010 and its Further Amended Technology & Construction List Statement dated 13 October 2010, the plaintiff seeks a declaration that the second defendant’s adjudication determination (“the Adjudication”) under the Building and Construction Industry Security of Payment Act 1999 (NSW) (“the Act”) dated 22 February 2010 for $1,358,090.14 (including GST) is void. The recent decision of the Court of Appeal in Chase Oyster Bar v Hamo Industries [2010] NSWCA 190 (“Chase Oyster Bar”) makes it clear that the appropriate form of relief is an order in the nature of certiorari quashing or setting aside the adjudication.

2 In the alternative, the Summons seeks an order restraining the first defendant from acting upon the Adjudication on the grounds that it would have little prospect of recovering any money paid over to the first defendant because the first defendant is in a precarious financial position. During final submissions however, it was correctly accepted by the plaintiff that this relief was inapposite because if the plaintiff were to…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read St Hilliers Contracting Pty Limited v Dualcorp Civil Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Find similar cases

Other decisions on the same topics. Each opens in a new tab.

Details

Case
[2010] NSWSC 1468
Decision Date

CaseChat Overview and Summary

St Hilliers Contracting Pty Limited sued Dualcorp Civil Pty Ltd, challenging an adjudication determination by the second defendant in favour of the first defendant. The dispute arose under the Building and Construction Industry Security of Payment Act 1999, which governs payment claims in the construction industry. The plaintiff argued that the adjudicator made a jurisdictional error and did not afford natural justice by not considering material properly before her and by setting a payment date not submitted by either party.

The court had to decide whether the adjudicator's determination was legally flawed. The plaintiff contended that the adjudicator erred by not considering all relevant information and by imposing a payment date not proposed by either party. The plaintiff claimed this constituted a jurisdictional error and a breach of natural justice principles. The court had to determine if the adjudicator's actions warranted setting aside the adjudication determination.

The court found that the adjudicator indeed made a jurisdictional error and did not adhere to natural justice by not considering relevant material and setting a payment date not proposed by the parties. The court held that these errors were significant enough to warrant setting aside the adjudication determination. Consequently, the court ordered the determination to be quashed and set aside, allowing for a re-adjudication to ensure all proper material was considered and that any new payment date was agreed upon by the parties.

Background

Background to the litigation

Decision

Reasons for decision

Ratio Decidendi

Legal principle established