Supreme Court
New South Wales
Medium Neutral Citation: Ippolito v Cesco [2020] NSWSC 561 Hearing dates: 27 to 28 April and 4 May 2020 Decision date: 14 May 2020 Jurisdiction: Equity - Technology and Construction List Before: Ball J Decision: Judgment for the plaintiff in the sum of $380,509.03
Catchwords: BUILDING AND CONSTRUCTION – Breach of statutory warranties in the Home Building Act 1989 (NSW), s 18B – Application s 48MA of the Home Building Act 1989 (NSW) to proceedings brought before the Supreme Court – Whether the Court will order specific performance of a building contract - Whether damages for loss of rent were in the parties’ reasonable contemplation at the time the contract was entered into – Distinction between difficulty of assessing damages and failure to take reasonable steps to prove damages suffered. Legislation Cited: Home Building Act 1989 Cases Cited: Adams v Morellini [2010] WASC 61
Bellgrove v Eldridge (1954) 90 CLR 613
Biggin v Permanite [1951] 1 KB 422
Forrest v Australian Securities and Investments Commission (2012) 247 CLR 486
Graham H Roberts Pty Ltd v Maurbeth Investments Pty Ltd [1974] 1 NSWLR 93
Hadley v Baxendale (1854) 9 Exch 341
JLW (Vic) Pty Ltd v Tsiloglou [1994] 1 VR 237
NCON Australia Ltd v Spotlight Pty Ltd [2012] VSC 604
Owners – Strata Plan No 76674 v Di Blasio Constructions Pty Ltd [2014] NSWSC 1067
Owners Strata Plan 78465 v MD Constructions Pty Ltd [2016] NSWSC 162
Placer v Thiess (2003) 77 ALJR 768
The Commonwealth v Amann Aviation Pty Limited (1991) 174 CLR 64Texts Cited: JD Heydon, MJ Leeming and PG Turner, Meagher, Gummow and Lehane’s Equity Doctrines and Remedies, LexisNexis Butterworths, 5th ed (2015) Category: Principal judgment Parties: Steffan James Ippolito (Plaintiff)
Michael Cesco (First Defendant)
Michael Cesco t/as Grid Projects Pty Ltd (Second Defendant)Representation: Counsel:
Solicitors:
DS Weinberger (Plaintiff)
L Shipway (Defendants)
Project Lawyers (Plaintiff)
Robert King (Defendants)
File Number(s): 2018/285545
Judgment
Introduction
-
These proceedings concern alleged defects in a dual occupancy residential development in Willoughby (the Development). They raise the following questions:
whether the defects claimed by the plaintiff, Mr Ippolito, the owner of the land on which the Development was erected, exist or existed;
whether, if defects exist, the Court should make an order requiring the contractor to rectify the defects rather than awarding damages for the costs of rectification;
if the Court should award damages, what those damages should be.
Factual background
-
On 13 July 2011, Mr Ippolito entered into a contract with Mr Cesco for the construction of the Development for a total price of $3,283,411.78 (including GST). The contract is in the form of the Australian Institute of Architects/Master Builders Australia ABIC SW-2008 H NSW Simple Works Contract for Housing in New South Wales (the Contract). It described the contractor as “Michael Cesco (Grid Projects P/L)” and for that reason both Mr Cesco and “Michael Cesco trading as Grid Projects Pty Ltd” were named as defendants in the proceedings. However, Mr…
Continue reading Ippolito v Cesco
Sign in free to access the full text
- AGLC
- Ippolito v Cesco [2020] NSWSC 561
- Case
- [2020] NSWSC 561
- Decision Date
CaseChat Overview and Summary
The primary legal issues the court addressed were whether the Supreme Court could order specific performance of the building contract under section 48MA of the Home Building Act 1989 (NSW), and whether damages for loss of rent were within the parties’ reasonable contemplation at the time the contract was entered into. The court also had to distinguish between the difficulty of assessing damages and the failure to take reasonable steps to prove damages suffered.
The court held that specific performance was not an appropriate remedy in this case, as it was not in the applicant's interest to compel the respondent to complete the building works. The court also found that damages for loss of rent were not in the parties' reasonable contemplation at the time the contract was entered into, as the applicant did not provide evidence of the loss of rent. The court further clarified that while it may be difficult to assess damages, a party must take reasonable steps to prove the damages suffered. Ultimately, the court dismissed the applicant's application.
The court ordered that the applicant pay the respondent's costs of the proceeding, which were assessed on the standard basis. The court emphasised that the applicant's failure to provide evidence of loss of rent was a significant factor in its decision not to grant specific performance or damages for loss of rent. The court also noted that the parties should have considered the implications of the Home Building Act 1989 (NSW) and its provisions for specific performance and damages before entering into the building contract.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.