HIGH COURT OF AUSTRALIA
GLEESON CJ,
McHUGH, KIRBY, HAYNE AND CALLINAN JJPLACER (GRANNY SMITH) PTY LTD APPELLANT
AND
THIESS CONTRACTORS PTY LTD RESPONDENT
Placer (Granny Smith) Pty Ltd v Thiess Contractors Pty Ltd
[2003] HCA 10
11 March 2003
P60/2001ORDER
1. Appeal allowed with costs.
2. Set aside the whole of the order of the Full Court of the Supreme Court of Western Australia made on 14 April 2000 and, in lieu thereof, order that the respondent's appeal to that Court be dismissed with costs.
On appeal from the Supreme Court of Western Australia
Representation:
J Gilmour QC with C M Duncan for the appellant (instructed by Mallesons Stephen Jaques)
D F Jackson QC with P G Clifford for the respondent (instructed by Hollingdales)
Notice: This copy of the Court's Reasons for Judgment is subject to formal revision prior to publication in the Commonwealth Law Reports.
GLEESON CJ, McHUGH AND KIRBY JJ. This appeal arises out of complex and protracted litigation in the Supreme Court of Western Australia in relation to a contract pursuant to which the respondent agreed to carry out mining operations for the appellant at rates based on genuine estimates, reviewed from time to time, of the cost of such operations. After relations between the parties broke down, the appellant alleged that, in breach of a contractual obligation of good faith, the respondent had inflated its cost estimates and, in consequence, had been overpaid. By way of counterclaim in proceedings commenced by the respondent, the appellant sought to recover the overpayments. The trial judge awarded the appellant $4,853,000.
The contractual provisions, and the relevant facts, appear from the reasons for judgment of Hayne J and Callinan J.
The Full Court of the Supreme Court of Western Australia rejected an argument that the appellant had failed to make out a case of overpayment. Accepting that the best evidence of the respondent's true estimates of its costs was to be found in its internal plant department rates, the Full Court said:
"In consequence of Thiess' breaches of contract, Placer paid Thiess remuneration based on rates higher than those that would otherwise have been agreed. Placer is therefore entitled to damages for breach of contract represented by the difference between the remuneration paid by it to Thiess and the remuneration it would have paid had Thiess not breached the contract. On the evidence, the remuneration Placer would have paid had Thiess not breached the contract is to be calculated by reference to the plant department rates. Placer is entitled to its damages for breach of contract, calculated on this basis."
The Full Court then went on to consider the evidence, and the method of calculation of damages adopted by the trial judge. The Court concluded that the trial judge's method was erroneous, and that there was insufficient evidence to enable a calculation on proper principles to be made. In the result, the Court held that there "was a critical lacuna in [Placer's] damages formula", that "Placer did not…
Keep reading for free
Create a free CaseChat account to read Placer (Granny Smith) Pty Ltd v Thiess Contractors Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2003] HCA 10
- Decision Date
CaseChat Overview and Summary
The legal issues before the High Court were whether there was sufficient evidence for Placer to prove its damages arising from Thiess Contractors' breach, and whether the trial judge had correctly applied the principles for calculating those damages. Specifically, the court had to determine if Placer had adequately demonstrated the amount by which it had been overcharged due to Thiess Contractors' inflated cost estimates and whether the method used by the trial judge to calculate these damages was legally sound, despite criticisms from the Full Court of the Supreme Court of Western Australia.
The High Court reasoned that once Placer established a significant discrepancy between Thiess Contractors' inflated estimated costs and its actual costs, and demonstrated that any purported productivity gains were not substantial, the onus shifted to Thiess Contractors to justify any further adjustments to the calculation of damages. The court found that the trial judge's method of calculating damages, which involved deducting the profit actually earned by Thiess Contractors from the amount paid by Placer, thereby arriving at the actual costs incurred, was appropriate. This approach, coupled with the trial judge's adjustments for cost overruns and productivity gains based on evidence, led to a finding that Placer had overpaid $4.853 million. The High Court concluded that the Full Court had erred in setting aside the trial judge's findings and calculation of damages.
Consequently, the High Court allowed Placer's appeal with costs. It set aside the order of the Full Court of the Supreme Court of Western Australia and ordered in its place that Thiess Contractors' appeal to that Court be dismissed with costs.
Orders
Orders of the court
1. Appeal allowed with costs.
2. Set aside the whole of the order of the Full Court of the Supreme Court of Western Australia made on 14 April 2000 and, in lieu thereof, order that the respondent's appeal to that Court be dismissed with costs.
Background
Background to the litigation
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
Established by: HUGH AND KIRBY JJ, HAYNE J, CALLINAN J
In order to deal with those questions it is necessary to refer to first, how payments to be made for work done by Thiess Contractors were calculated; secondly, the way in which Placer sought, at trial, to prove its damage; thirdly, the trial judge's findings about damage; and, finally, the Full Court's criticisms of the case Placer had sought to make and the findings made by the trial judge.Calculating Thiess Contractors' remuneration As is apparent from what has been said already, calculating the amount to be paid by Placer to Thiess Contractors under the contract began with identifying Thiess Contractors' bona fide estimates of costs it would incur in performing work under the contract. Those costs included the costs of owning and operating various pieces of equipment, some of it large earthmoving equipment. To obtain a cost that could be expressed as an amount of money per unit of material moved, or unit of time worked, it was necessary to take account of such matters as the type of material that was being moved, how far it was being moved, how difficult the trip from loading to unloading would be, how long that trip would take and other similar considerations. The contract stipulated that those calculations would be made using an identified computer program. Because the calculations were made periodically (in some cases monthly) and were made for several different pieces of equipment executing different kinds of work over the period of alleged overpayments by Placer, calculating the amount due from Placer to Thiess Contractors was a large task requiring many separate calculations. All of those calculations required the identification of an amount properly identified as Thiess Contractors' bona fide estimate of costs, but many required the identification of other factors determined by reference to the work that was to be done. On its face, a recalculation of the amount properly payable by Placer to Thiess Contractors would appear to have required prolonged examination of documents or matters of account of a kind that might properly have been referred[9] to a referee. No order of that kind was made and Placer did not attempt to adduce evidence of the result of such a recalculation. Rather, Placer sought to arrive at the amount which it had overpaid by, in effect, working backwards from the amount which it had paid.[9]Supreme Court Act 1935 (WA), s 51(1).Placer's proof of damage at trial At trial, Placer sought to arrive at the amount it had overpaid as a result of Thiess Contractors' breach, by deducting from the amount of money which it had paid the amount of profit that Thiess Contractors had, in fact, made in performing the contract during the relevant period. This, so it was alleged, would leave the amount of cost which Thiess Contractors had, in fact, incurred during the period. Under the contract, the agreed profit allowance of 5 per cent was to be calculated on estimated costs. Placer's calculation of its damages at trial took 5 per cent of actual rather than estimated costs and treated the difference between the profit actually earned and profit calculated as 5 per cent of the actual costs as the amount which it had overpaid.