Thiess Contractors Pty Ltd v Placer (Granny Smith) Pty Ltd

Link copied
Case Copied 83 min read

JURISDICTION     :   SUPREME COURT OF WESTERN AUSTRALIA

CITATION:   THIESS CONTRACTORS PTY LTD -v- PLACER (GRANNY SMITH) PTY LTD [2000] WASCA 102

CORAM:   IPP J

STEYTLER J
WHEELER J

HEARD:   8-17 FEBRUARY 2000

DELIVERED          :   14 APRIL 2000

FILE NO/S:   FUL 55 of 1999

BETWEEN:   THIESS CONTRACTORS PTY LTD (ACN 010 221 486)

Appellant

AND

PLACER (GRANNY SMITH) PTY LTD (ACN 009 466 174)
Respondent

Catchwords:

Contracts - Partnering contract for mine exploitation - Termination - Whether respondent estopped from relying on termination clause - Turns on own facts

Contracts - Contract for agreement of rates based on "open book" system - Whether appellant breached duty of good faith - Turns on own facts

Damages - Breach of contract - Turns on own facts

Appeal - Retrial - Damages - Principles

Legislation:

Nil

Result:

Appeal allowed

Representation:

Counsel:

Appellant:     Mr W S Martin QC, Mr J A Clifford & Mr S J McComish

Respondent:     Mr J Gilmour QC & Mr R J Ainsley

Solicitors:

Appellant:     Hollingdales

Respondent:     Mallesons Stephen Jaques

Case(s) referred to in judgment(s):

Balenzuela v De Gail (1959) 101 CLR 226

Festic v Atkinson, unreported; FCt SCt of WA; Library No 8484 19 September 1990

Giannerelli & Shulkes v Wraith (1988) 165 CLR 543

Monaco v Arnedo Pty Ltd, unreported; FCt SCt of WA; Library No 940481; 6 September 1994

Transport & General Insurance Company Limited v Edmondson (1961) 106 CLR 23

Case(s) also cited:

Australian Broadcasting Commission v Australasian Performing Right Association Ltd (1973) 129 CLR 99

Beach Petroleum NL v Abbott Tout Russell Kennedy (1999) 33 ACSR 1

Codelfa Construction Pty Ltd v State Rail Authority (NSW) (1982) 149 CLR 337

Walker & Anor v Henville & Anor [1999] WASCA 117

Waltons Stores (Interstate) Ltd v Maher (1988) 164 CLR 387

Wardley Australia Ltd v Western Australia (1992) 175 CLR 514

  1. JUDGMENT OF THE COURT: 

The Granny Smith "partnering" contract

  1. In 1989, the appellant (to whom we shall refer as "Thiess") entered into a schedule‑of‑rates mining contract with the respondent (to whom we shall refer as "Placer").  By that contract Thiess undertook to carry out open‑cut mining at Placer's Granny Smith gold mine at Laverton, Western Australia.  As the 1989 contract was a schedule‑of‑rates contract, the rates which Thiess was entitled to charge included an allowance not only for the cost of the work but for profit. 

  2. Work proceeded under the 1989 contract, but by June 1991 unforeseen problems arose and Thiess was required to carry out work outside the scope of the contract.  A characteristic of a schedule‑of‑rates contract is that, if variations to the work occur, the contract sum is adjusted (whether by omission or addition) in accordance with the scheduled rates.  Variations of this kind may result in an unexpected increase in the cost of the work and allow the contractor to make windfall profits.  The unexpected difficulties Thiess had experienced with the work led to variations and an increase in Placer's cost per bank cubic metre ("BCM") of mined material.

  3. Placer thereupon…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Thiess Contractors Pty Ltd v Placer (Granny Smith) Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2000] WASCA 102
Decision Date

CaseChat Overview and Summary

The dispute between Thiess Contractors Pty Ltd and Placer (Granny Smith) Pty Ltd arose from a mining contract executed in 1989. Thiess had undertaken to carry out open-cut mining at Placer's Granny Smith gold mine in Laverton, Western Australia. The contract was a schedule-of-rates agreement, allowing Thiess to charge rates that included an allowance for cost and profit. However, unforeseen problems arose in 1991, leading to variations in the work scope and an increase in Placer's costs. Placer and Thiess then negotiated a new contract, which was to replace the 1989 contract and incorporate a risk-sharing principle. This new contract, referred to as the "partnering contract," was executed in July 1993. Placer terminated the contract in March 1995, relying on a termination clause that allowed it to terminate the contract at any time and for any reason.

The primary legal issues in this case involved whether Placer was estopped from relying on the termination clause, whether Thiess breached its duty of good faith, and the assessment of damages for the breach of contract. The court had to determine whether Placer's conduct estopped it from terminating the contract, whether Thiess breached its duty of good faith by not disclosing certain information, and the appropriate measure of damages for the breach. The court's reasoning focused on the specific facts of the case, including the terms of the contract, the conduct of the parties, and the consequences of the termination. The court concluded that Placer was not estopped from terminating the contract, as the estoppel argument was based on the assumption that the contract would be renegotiated, which was not the case. The court also found that Thiess did not breach its duty of good faith, as the information in question was not material to the contract. Regarding damages, the court determined that the assessment should be based on the actual losses suffered by Placer due to the breach.

The court ordered that Thiess was not liable for damages arising from the breach of contract. The court also noted that the appeal would be remitted for a retrial to determine the quantum of damages, if any, that Placer was entitled to receive. The decision highlights the importance of the specific terms of a contract and the need for clear and precise communication between parties in complex contractual arrangements.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

STEYTLER J
JUDGMENT OF THE COURT: In 1989, the appellant (to whom we shall refer as "Thiess") entered into a schedule‑of‑rates mining contract with the respondent (to whom we shall refer as "Placer"). By that contract Thiess undertook to carry out open‑cut mining at Placer's Granny Smith gold mine at Laverton, Western Australia. As the 1989 contract was a schedule‑of‑rates contract, the rates which Thiess was entitled to charge included an allowance not only for the cost of the work but for profit. Work proceeded under the 1989 contract, but by June 1991 unforeseen problems arose and Thiess was required to carry out work outside the scope of the contract. A characteristic of a schedule‑of‑rates contract is that, if variations to the work occur, the contract sum is adjusted (whether by omission or addition) in accordance with the scheduled rates. Variations of this kind may result in an unexpected increase in the cost of the work and allow the contractor to make windfall profits. The unexpected difficulties Thiess had experienced with the work led to variations and an increase in Placer's cost per bank cubic metre ("BCM") of mined material. Placer thereupon negotiated with Thiess for a new contract intended to replace the 1989 contract. Placer suggested that the parties enter into a "partnering" contract that would incorporate principles different from a schedule‑of‑rates contract. In pre-contractual discussions and written communications Placer proposed that the new contract be based on a risk‑sharing principle (that is, that the risk of cost fluctuations be shared between Thiess and Placer), that the parties "work in good faith on all matters relating to the contract", and that the contract provide for a fixed profit to be earned by Thiess, being an agreed percentage on costs. These discussions culminated on 13 July 1992 when Thiess and Placer entered into a new contract that replaced the 1989 contract. The learned trial Judge found that on that date the parties agreed to terms that were to be incorporated in a formal contract to be prepared. That formal contract was executed in July 1993. His Honour accepted that subject to the 1993 formal contract being rectified on an aspect not presently material, that formal contract was the best evidence of the agreement reached on 13 July 1992. The learned Judge found that the contract so constituted came into effect (in accordance with its terms as rectified) on 1 August 1992. His Honour determined that the rights and obligations of the parties as from 1 August 1992 were to be determined by construing the formal contract as rectified. We were informed during the course of argument on appeal that neither party disputed these findings. In March 1995, Placer terminated the contract. It did so in reliance on a termination clause which entitled it, at its option, and at any time and for any reason it might deem advisable, to cancel and terminate the contract. In that event, Thiess was entitled to receive compensation for unit‑price items and demobilisation, as well as certain defined additional (but limited) compensation.

Ratio Decidendi

Legal Principle Established

Established by: STEYTLER J

Full text does not contain this section.