J-Corp Pty Ltd v Mladenis

Case [2009] WASCA 157


JURISDICTION     :   SUPREME COURT OF WESTERN AUSTRALIA

TITLE OF COURT :   THE COURT OF APPEAL (WA)

CITATION:   J-CORP PTY LTD -v- MLADENIS [2009] WASCA 157

CORAM:   BUSS JA

MILLER JA
NEWNES JA

HEARD:   3 JUNE 2009

DELIVERED          :   28 AUGUST 2009

FILE NO/S:   CACV 122 of 2008

BETWEEN:   J-CORP PTY LTD

Appellant

AND

MARK STEVEN MLADENIS
First Respondent

GRAHAM ATHLETIC PTY LTD
Second Respondent

ON APPEAL FROM:

Jurisdiction              :  DISTRICT COURT OF WESTERN AUSTRALIA

Coram  :SCHOOMBEE DCJ

Citation  :MLADENIS & ANOR -v- J CORP PTY LTD [2008] WADC 174

File No  :CIV 403 of 2007

Catchwords:

Contract - Construction of building contract - Liquidated damages - Amount of liquidated damages for delay specified as 'nil' - Whether intended to exclude claim for unliquidated damages for delay - Turns on own facts

Legislation:

Nil

Result:

Appeal dismissed

Category:    B

Representation:

Counsel:

Appellant:     Mr C G Colvin SC

First Respondent           :     Mr A Atkinson

Second Respondent      :     Mr A Atkinson

Solicitors:

Appellant:     Hotchkin Hanly

First Respondent           :     Solomon Brothers

Second Respondent      :     Solomon Brothers

Case(s) referred to in judgment(s):

Australian Broadcasting Commission v Australasian Performing Right Association Ltd (1973) 129 CLR 99

Baese Pty Ltd v RA Bracken Building Pty Ltd (1990) 6 BCL 137

Cellulose Acetate Silk Co Ltd v Widnes Foundry (1925) Ltd [1933] AC 20

Concut Pty Ltd v Worrell [2000] HCA 64; (2000) 75 ALJR 312

Décor Ceilings Pty Ltd v Cox Constructions Pty Ltd (No 2) [2005] SASC 483; (2007) 23 BCL 347

Diestal v Stevenson [1906] 2 KB 345

Gilbert‑Ash (Northern) Ltd v Modern Engineering (Bristol) Ltd [1974] AC 689

Pacific Carriers Ltd v BNP Paribas [2004] HCA 35; (2004) 218 CLR 451

Talley v Wolsley‑Neech (1978) 38 P & CR 45

Temloc Ltd v Errill Properties Ltd (1987) 39 BLR 30

Toll (FGCT) Pty Ltd v Alphapharm Pty Ltd [2004] HCA 52; (2004) 219 CLR 165

Waterways Authority of New South Wales v Coal And Allied (Operations) Pty Ltd [2007] NSWCA 276; (2008) Aust Contract R ¶90‑278

  1. BUSS JA:  I agree with Newnes JA that leave to appeal should be granted but that the appeal should be dismissed.  Subject to the following observations, I respectfully agree with his Honour's reasons.

  2. The critical issue in the appeal is whether the parties, by specifying the rate of liquidated damages in cl 11.9 of the contract as 'NIL DOLLARS ($00.00) per day' intended that the respondents/proprietors should not be entitled to recover any damages (either liquidated damages at an agreed rate or unliquidated common law damages) for breach of the appellant's/builder's obligation under cl 11.1 to complete the works by a specified date.

  3. It is well established that an intention to exclude the common law right to damages for breach of contract must be expressed in clear and unambiguous terms.  See, for example, Concut Pty Ltd v Worrell [2000] HCA 64; (2000) 75 ALJR 312 [23] (Gleeson CJ, Gaudron & Gummow JJ); Décor Ceilings Pty Ltd v Cox…

Continue reading J-Corp Pty Ltd v Mladenis

Sign in free to access the full text

Details
AGLC
J-Corp Pty Ltd v Mladenis [2009] WASCA 157
Case
[2009] WASCA 157
Decision Date

CaseChat Overview and Summary

In the case of J-Corp Pty Ltd v Mladenis, the Federal Court of Australia was asked to determine whether the contractual term specifying the amount of liquidated damages for delay as 'nil' was intended to exclude a claim for unliquidated damages for delay. The plaintiff, J-Corp Pty Ltd, was a contractor engaged by the defendant, Mladenis, to construct a building. The dispute arose when J-Corp sought to recover unliquidated damages for delay after the contract was breached by Mladenis.

The central legal issue before the court was whether the contractual term specifying 'nil' liquidated damages was intended to preclude a claim for unliquidated damages for delay. The court needed to consider the construction of the contract, the intentions of the parties, and the applicability of the principle that liquidated damages are intended to compensate for loss and not to act as a penalty.

The court held that the term specifying 'nil' liquidated damages did not preclude a claim for unliquidated damages for delay. The court found that the parties' intentions were not to exclude claims for unliquidated damages for delay, as the term was not clear and unambiguous in precluding such claims. The court emphasised that the principle of liquidated damages being compensatory and not penal played a significant role in its reasoning. Therefore, the plaintiff was entitled to recover unliquidated damages for the delay caused by the defendant's breach of contract. The court ordered that J-Corp Pty Ltd be compensated for the unliquidated damages incurred due to the delay.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.