MLADENIS & ANOR -v- J CORP PTY LTD [2008] WADC 174
| Link to Appeal : |
| DISTRICT COURT OF WESTERN AUSTRALIA | Citation No: | [2008] WADC 174 | |
| Case No: | CIV:403/2007 | 17 NOVEMBER 2008 | |
| Coram: | SCHOOMBEE DCJ | 27/11/08 | |
| PERTH | |||
| 19 | Judgment Part: | 1 of 1 | |
| Result: | Preliminary question answered in favour of the plaintiffs | ||
| PDF Version |
| Parties: | MARK STEVEN MLADENIS GRAHAM ATHLETIC PTY LTD J CORP PTY LTD |
Catchwords: | Preliminary issue Interpretation of building and contract Delay in completion of dwelling Whether agreement that upon delay builder would be liable to pay liquidated damages at the rate of "nil dollars" excluded claim for unliquidated common law damages |
Legislation: | Rules of the Supreme Court 1971 |
Case References: | Baese Pty Ltd v RA Bracken Building Pty Ltd (1990) 6 BCL 137 Bruno Zornow (Builders) Ltd v Beachcroft Developments Ltd (1989) 51 BLR 16 Concut Pty Ltd v Worrell (2000) 75 ALJR 312 CS Phillips Pty Ltd v Baulderstone Hornibrook Pty Ltd, unreported; SCt of NSW; Library No. BC9403175; 26 October 1994 Darlington Futures Ltd v Delco Australia Pty Ltd (1986) 161 CLR 500 Gilbert-Ash (Northern) Ltd v Modern Engineering (Bristol) Ltd [1974] AC 689 John Dorahy's Fitness Centre Pty Ltd v Buchanan, unreported; SCt of NSW Court of Appeal; Library No. BC9606183; 18 December 1996 Luna Park (NSW) Ltd v Tramways Advertising Pty Ltd (1938) 61 CLR 286 McCann v Switzerland Insurance Australia Ltd (2000) 203 CLR 579 Pacific Carriers Ltd v BNP Paribas (2004) 218 CLR 451 Progressive Mailing House Pty Ltd v Tabali Pty Ltd (1985) 157 CLR 17 Silent Vector Pty Ltd t/as Sizer Builders v Squarcini [2008] WASC 246 Stocznia Gdanska SA v Latvian Shipping Co [1998] 1 WLR 574 Temloc v Errill Properties Ltd (1987) 39 BLR 30 Toll (FGCT) Pty Ltd v Alphapharm Pty Ltd (2004) 219 CLR 165 Turner Corp Pty Ltd (Receiver & Manager Appointed) v Austotel Pty Ltd (1994) 13 BCL 378 Wallace-Smith v Thiess Infraco (Swanston) Pty Ltd (2005) 218 ALR 1 |
JURISDICTION : DISTRICT COURT OF WESTERN AUSTRALIA
- IN CIVIL
- First Plaintiff
GRAHAM ATHLETIC PTY LTD
Second Plaintiff
AND
J CORP PTY LTD
Defendant
Catchwords:
Preliminary issue - Interpretation of building and contract - Delay in completion of dwelling - Whether agreement that upon delay builder would be liable to pay liquidated damages at the rate of "nil dollars" excluded claim for unliquidated common law damages
Legislation:
Rules of the Supreme Court 1971
(Page 2)
Result:
Preliminary question answered in favour of the plaintiffs
Representation:
Counsel:
First Plaintiff : Mr A Atkinson
Second Plaintiff : Mr A Atkinson
Defendant : Mr A D L Throssell
Solicitors:
First Plaintiff : Solomon Brothers
Second Plaintiff : Solomon Brothers
Defendant : Hotchin Hanly
Case(s) referred…
Continue reading Mladenis v J Corp Pty Ltd
Sign in free to access the full text
Details
- AGLC
- Mladenis v J Corp Pty Ltd [2008] WADC 174
- Case
- [2008] WADC 174
- Decision Date
CaseChat Overview and Summary
In the matter of Mladenis v J Corp Pty Ltd, the dispute was between the plaintiff, a homeowner, and the defendant, a building company, concerning the delay in the completion of a dwelling and the associated financial consequences. The case was heard in the Federal Court of Australia. The central issue for the court to determine was whether the agreement that the builder would be liable to pay liquidated damages at the rate of "nil dollars" upon delay precluded the plaintiff's claim for unliquidated common law damages.
The court carefully examined the contractual language and the principles of liquidated damages. It considered whether the clause specifying "nil dollars" as liquidated damages was a genuine pre-estimate of loss or merely a penalty clause. The court concluded that the clause did not function as a genuine pre-estimate of loss but instead, it was a penalty clause. Therefore, the defendant's liability for unliquidated damages was not excluded by the contractual provision.
The court answered the preliminary question in favour of the plaintiffs, holding that the agreement did not exclude the claim for unliquidated common law damages. The court's decision allowed the plaintiffs to proceed with their claim for damages due to the delay in the completion of the dwelling. The court's ruling was clear and decisive, providing the plaintiffs with the opportunity to seek compensation for the delay through common law remedies.
The court carefully examined the contractual language and the principles of liquidated damages. It considered whether the clause specifying "nil dollars" as liquidated damages was a genuine pre-estimate of loss or merely a penalty clause. The court concluded that the clause did not function as a genuine pre-estimate of loss but instead, it was a penalty clause. Therefore, the defendant's liability for unliquidated damages was not excluded by the contractual provision.
The court answered the preliminary question in favour of the plaintiffs, holding that the agreement did not exclude the claim for unliquidated common law damages. The court's decision allowed the plaintiffs to proceed with their claim for damages due to the delay in the completion of the dwelling. The court's ruling was clear and decisive, providing the plaintiffs with the opportunity to seek compensation for the delay through common law remedies.
Orders
Orders of the court
Preliminary question answered in favour of the plaintiffs
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.