Regional Power Corporation v Pacific Hydro Group Two Pty Ltd (No 2)

Link copied
Case Copied 41 min read

JURISDICTION     :   SUPREME COURT OF WESTERN AUSTRALIA

IN CIVIL

CITATION:   REGIONAL POWER CORPORATION -v- PACIFIC HYDRO GROUP TWO PTY LTD [No 2] [2013] WASC 356

CORAM:   KENNETH MARTIN J

HEARD:   1 MAY 2013

DELIVERED          :   26 SEPTEMBER 2013

FILE NO/S:   CIV 1925 of 2012

BETWEEN:   REGIONAL POWER CORPORATION

Plaintiff

AND

PACIFIC HYDRO GROUP TWO PTY LTD
First Defendant

ENERGIS AUSTRALIA PTY LTD formerly known as PACIFIC HYDRO GROUP THREE PTY LTD
Second Defendant

NORTH WESTERN ENERGY PTY LTD formerly known as ORD ENERGY PTY LTD
Third Defendant

Catchwords:

Preliminary issues - Contract - Breach - Common law damages - Exclusive code of breach relief - Indirect and consequential loss and damage excluded - Limitation clause - Scope of exclusion clause - Direct loss - Foreseeability of damage - Economic loss

Legislation:

State Energy Commission Act 1979 (WA) (No 111 of 1979)

Result:

Preliminary issues answered

Category:    A

Representation:

Counsel:

Plaintiff:     Mr S K Dharmananda SC & Mr L N Firios

First Defendant             :     Mr M Howard SC & Mr W C J Zappia

Second Defendant         :     Mr M Howard SC & Mr W C J Zappia

Third Defendant           :     Mr M Howard SC & Mr W C J Zappia

Solicitors:

Plaintiff:     Ashurst Australia

First Defendant             :     Lavan Legal

Second Defendant         :     Lavan Legal

Third Defendant           :     Lavan Legal

Case(s) referred to in judgment(s):

Allianz v Waterbrook [2009] NSWCA 224

Alstom v Yokogawa Australia (No 7) [2012] SASC 49

Australian Broadcasting Commission v Australasian Performing Right Association Ltd [1973] HCA 36; (1973) 129 CLR 99

Castlemaine Tooheys Ltd v Carlton & United Breweries Ltd (1987) 10 NSWLR 468

Concut Pty Ltd v Worrell [2000] HCA 64; (2000) 176 ALR 693

Croudace Construction Ltd v Carwoods Concrete Products Ltd [1978] 2 Lloyds Reports 55 (CA)

Darlington Futures Ltd v Delco Australia Pty Ltd [1986] HCA 82; (1986) 161 CLR 500

Electricity Generation Corporation t/as Verve Energy v Woodside Energy Ltd [2013] WASCA 36

Environmental Systems Pty Ltd v Peerless Holdings Pty Ltd [2008] VSCA 26; (2008) 19 VR 358

GEC Alsthom Australia Ltd v City of Sunshine (Unreported, FCA, Library No BC9600288, 20 February 1996)

Hadley v Baxendale (1854) 9 Exch 341; (1854) 156 ER 145

Hungerfords v Walker [1989] HCA 8; (1989) 171 CLR 125

J‑Corp Pty Ltd v Mladenis [2009] WASCA 157

JR Marine Systems Pte Ltd v Wavemaster International Pty ltd (in liq) [2011] WASCA 16

Koufos v C Czarnikow Ltd [1969] 1 AC 350

Matthew Maxwell v Highway Hauliers Pty Ltd [2013] WASCA 115

Perth Airport Pty Ltd v Ridgepoint Corporation [2013] WASC 33

Project Blue Sky Inc v Australian Broadcasting Authority [1998] HCA 28; (1998) 194 CLR 355

Regional Power Corporation v Pacific Hydro Two Pty Ltd [2013] WASC 46

SMEC Australia Pty Ltd v Valentine Falls Estate Pty Ltd [2011] WASCA 138

Valentine Falls Estate Pty Ltd v SMEC Australia Pty Ltd [2010] WASC 319

Wavemaster International Pty Ltd (In liq) v JR Marine Systems Pte Ltd [2009] WASC…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Regional Power Corporation v Pacific Hydro Group Two Pty Ltd... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2013] WASC 356
Decision Date

CaseChat Overview and Summary

In the case of Regional Power Corporation v Pacific Hydro Group Two Pty Ltd, the dispute centered on the extent of damages that could be claimed by the plaintiff following a flooding incident at the Ord Hydro Power Station. The court was tasked with determining whether the plaintiff could claim common law damages for losses that were indirect or consequential, in addition to the damages available under an exclusive code of breach relief stipulated in the Power Purchase Agreement (PPA) between the parties. The plaintiff argued that the defendants' breach of the PPA had led to significant economic loss due to the flooding, and sought to claim these losses under common law.

The primary legal issue before the court was whether the exclusion clause in the PPA, which limited the damages recoverable to those directly caused by the breach, precluded the plaintiff from claiming for indirect and consequential economic losses. The court had to examine the scope of the exclusion clause and whether the economic losses incurred by the plaintiff were direct or indirect. The court also needed to determine whether the economic losses were foreseeable and thus recoverable under the terms of the contract.

The court found that the exclusion clause in the PPA was clear and unambiguous in limiting the recoverable damages to those directly caused by the breach. The court held that the economic losses suffered by the plaintiff, including loss of revenue and increased costs, were not direct losses caused by the breach but were rather indirect and consequential losses. The court further determined that these losses were not foreseeable and therefore were not recoverable under the terms of the contract. As a result, the plaintiff was precluded from claiming common law damages for these losses. The court's interpretation of the exclusion clause and the nature of the losses was consistent with the principles of contract law and the specific terms agreed upon by the parties.

The court ordered that the plaintiff could not claim common law damages for the indirect and consequential economic losses suffered due to the flooding incident. The defendants were thus not liable for these losses under common law. The plaintiff was limited to the damages recoverable under the exclusive code of breach relief stipulated in the PPA.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established

I advert to the generally uncontroversial underlying facts as set out in my previous reasons (see Regional Power Corporation v Pacific Hydro Two Pty Ltd [4] ‑ [9], [12]). Additionally, the parties provided a statement of agreed facts for the purposes of a determination of the preliminary issues. Hence, the background facts I briefly outline below, are not controversial. By the PPA of 1994, Pacific Hydro agreed to construct, then afterwards supply, power (electricity) from the Ord Hydro Power Station (the Power Station) to SECWA. In 1994, SECWA was under a statutory duty to provide and maintain an 'efficient, coordinated and economical supply of electricity in the form of electricity or gas' (see State Energy Commission Act 1979 (WA) (No 111 of 1979)). The PPA was thereafter novated to the first, second and third defendants, by a deed of novation entered by Horizon Power, Pacific Hydro and the defendants of 18 October 1994. By statute, the present plaintiff holds and enjoys all the rights of SECWA. In these reasons generally I refer to the plaintiff as SECWA, although of course Regional Power Corporation is the entity that now sits in its place. The Power Station was duly constructed by the defendants adjacent to Lake Argyle, near to the township of Kununurra in northern Western Australia. Pursuant to the PPA, the defendants were to sell and supply electricity generated from the operation of the Power Station to two customers, SECWA and Argyle Diamond Mines (ADM). The Power Station, as completed, was operated by two hydro generators, each driven by twin Francis turbines. On 27 August 2006, the Power Station suffered an outage. This resulted in flooding (the parties refer to this as the Flooding Incident) which in turn led to the Power Station becoming inoperative for a two‑month period. In due course, the defendants commissioned a report investigating the causes of the Flooding Incident. Details of the report remain confidential. The defendants accept, but only for the purposes of the trial and determination of these preliminary issues, that the information contained in the report is true. (I note, however, for the purposes of any future disputation, the defendants are not taken to admit any facts in the report.) According to the report, the Flooding Incident transpired (par 14 of the further amended statement of claim dated 27 February 2013 (FASOC)) this way:(a)there was a loss of load signal at the Power Station (the Load Loss);(b)the Load Loss caused a trip in one of the Hydro Generators leading to a subsequent trip in the second Hydro Generator;(c)as a result of the Hydro Generators losing power and going offline, the Power Station was de-energised;(d)the emergency generator failed to start automatically; and (e)as a result of the matters referred to in subparagraphs (a) to (d) above, no power supply was available to the pumping system. The report concluded (pars 15 ‑ 16 of the FASOC; par 17 of agreed statement of facts):(i)the emergency generator failed to start because the programmable logic controller used to start the emergency generator had been incorrectly wired, such that its batteries were not adequately charged at the time of the Flooding Incident; and (ii)if the emergency generator's programmable logic controller had been correctly wired, such that it would have been operational on 27 August 2006, the pumping system installed to prevent a flooding of the Power Station would have been functional such that flooding would not have occurred.