Case Title: Macmahon Mining Services v Cobar Management Medium Neutral Citation: [2014] NSWSC 731 Hearing Date(s): 30/05/2014 Decision Date: 30 May 2014 Jurisdiction: Equity Division - Technology and Construction List Before: McDougall J Decision: Application for summary judgment or strike-out dismissed with costs.
Catchwords: PROCEDURE - application for summary judgment on or to strike out some claims -whether claims are for "Consequential Loss" as defined by the contract between the parties - whether regard must be had to the facts to determine whether claims fall within "Consequential Loss" - whether appropriate case for strike out or summary disposal of claims
PROCEDURE - costs - general rule costs follow the event of the motionCases Cited: Macmahon Mining Services v Cobar Management [2014] NSWSC 502
Alstom Ltd v Yokogawa Australia Pty Ltd and Anor (No 7) [2012] SASC 49
GEC Alsthom Australia Ltd v City of Sunshine (FCA, 20 February 1996, unreported)
Regional Power Corporation v Pacific Hydro Group Two Pty Ltd (No 2) [2013] WASC 356
Environmental Systems Pty Ltd v Peerless Holdings Pty Ltd (2008) 19 VR 358
Saint Line Ltd v Richardsons, Westgarth & Co Ltd [1940] 2 KB 99
Hadley v Baxendale (1854) 9 Exch 341Category: Procedural and other rulings Parties: Macmahon Mining Services Pty Limited (Plaintiff)
Cobar Management Pty Limited (Defendant)Representation - Counsel: Counsel:
FF Corsaro SC (Plaintiff)
G Inatey SC / TJ Breakspear (Defendant)- Solicitors: Solicitors:
McCullough Robertson Lawyers (Plaintiff)
King, Wood & Mallesons (Defendant)File Number(s): 2013/343809
JUDGMENT (EX TEMPORE - REVISED 30 MAY 2014)
HIS HONOUR: I am concerned today with an application by the plaintiff/cross-defendant (Macmahon) to dismiss summarily or to strike out certain claims made by the defendant/cross-claimant (Cobar). To give context to what follows, I set out paras 1 to 8, 10 and 11 of reasons that I gave on 25 March 2014 ([2014] NSWSC 502) in respect of Cobar's application to strike out one aspect only of Macmahon's claim against it:
1. On 14 October 2011, the plaintiff (Macmahon) as contractor and the defendant (Cobar) as principal made a written agreement under which Macmahon undertook to design and construct certain works for the development of Cobar's copper mine at Cobar in this State.
2. On 4 June 2013, Cobar wrote to Macmahon giving what it said was notice of termination of the contract. Cobar relied on a contractual provision, cl 22.3(a), which entitled it to terminate forthwith for breach if, in its opinion, the breach was material and incapable of remedy. Cobar relied also on the two following paragraphs of cl 22.3. One of those grounds related to asserted breach of Occupation Health and Safety obligations. The other related to other asserted material breaches which, in Cobar's opinion (said to have been reasonably formed), could not be rectified without themselves causing further material breaches.
3. Macmahon says that the termination was invalid, however, and that the letter of termination constituted a repudiation of the contract. On 19 June 2013…
Keep reading for free
Create a free CaseChat account to read Macmahon Mining Services Pty Ltd v Cobar Management Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2014] NSWSC 731
- Decision Date
CaseChat Overview and Summary
The court was required to decide whether it was necessary to consider the facts to ascertain if the claims indeed fell within the definition of "consequential loss" as per the contract. Furthermore, the court had to determine if the circumstances of the case warranted the striking out or summary disposal of the claims. The court also had to consider the costs associated with the motion, applying the general rule that costs follow the event of the motion.
The court found that it was appropriate to consider the facts to determine whether the claims fell within the definition of "consequential loss" as outlined in the contract. The court reasoned that the nature of the claims and the specific contractual language necessitated a factual inquiry to properly classify the claims. Consequently, the application for summary judgment or to strike out was dismissed, as the court determined that a factual assessment was necessary to resolve the matter. The court also held that the costs of the motion should follow the event, with the applicant bearing the costs of the unsuccessful application.
Background
Background to the litigation
Decision
Reasons for decision
Ratio Decidendi