QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION:
Rowan v Lead Constructions Pty Ltd [2021] QCAT 214
PARTIES: PETER ROWAN (applicant)
v
LEAD CONSTRUCTIONS PTY LTD (respondent)
APPLICATION NO/S:
BDL074-20
MATTER TYPE:
Building matters
DELIVERED ON:
17 June 2021
HEARING DATE:
On the papers
HEARD AT:
Brisbane
DECISION OF:
Senior Member Brown
ORDERS:
1. Lead Constructions Pty Ltd is to pay to Peter Rowan the amount of NINETEEN THOUSAND, TWO HUNDRED AND TWENTY-SEVEN DOLLARS AND SIXTY-EIGHT CENTS ($19,227.68) within 28 days of the date of this decision.
2. Lead Constructions Pty Ltd is to pay to Peter Rowan costs fixed in the amount of THREE HUNDRED AND FORTY-FIVE DOLLARS AND EIGHTY CENTS ($345.80) within 28 days of the date of this decision.
CATCHWORDS:
CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – PERFORMANCE OF WORK – REMEDIES FOR BREACH OF CONTRACT – DAMAGES – OTHER MATTERS – where the applicant hired the respondent builder to undertake building work – where the scope of works was “Enclosure of Patio to Store Room” – where work never progressed beyond framing stage – where no attempt to complete works made – whether applicant is entitled to damages
Queensland Building and Construction Commission Act 1991 (Qld), s 6, s 77, Sch 1B s 4, Sch 2
Queensland Civil and Administrative Tribunal Act 2009 (Qld), s 48
Baese Pty Ltd v R A Bracken Building Pty Ltd (1990) 6 BCL 137
Bellgrove v Eldridge (1954) 90 CLR 613
IPN Medical Centres Pty Ltd v Van Houten & Anor [2015] QSC 204
J-Corp Pty Ltd v Mladenis [2009] WASCA 157.Ventura v Svirac [1961] WAR 63.
APPEARANCES & REPRESENTATION:
Applicant:
Self represented
Respondent:
No appearance
This matter was heard and determined on the papers pursuant to s 32 of the Queensland Civil and Administrative Tribunal Act 2009 (Qld)
REASONS FOR DECISION
Mr Rowan engaged Lead Constructions to undertake building work. The parties fell into dispute and Mr Rowan commenced these proceedings. The proceeding is to be finally determined.
The background to the dispute
On 18 August 2019 the parties entered into a level 1 minor works contract for the performance of building work (the contract).
The contract price was $6,857.99. The contract described the scope of works as ‘Enclosure of Patio to Store Room’. The construction period was 9 days. The date of commencement of the works was set out in clause 8.1(b) of the contract and was within 10 days of the builder receiving certain stated documents and information. Lead Constructions was responsible under the contract for obtaining building approval. The date of practical completion was the last day of the construction period.
By clause 18 of the contract, if Lead Constructions did not bring the works to practical completion by the practical completion date, Mr Rowan was entitled to give to Lead Constructions a written claim for liquidated damages at the rate of $25.00 per day for each day after the date of practical completion the works remained incomplete until the date of practical completion or…
Continue reading Rowan v Lead Constructions Pty Ltd
Sign in free to access the full text
- AGLC
- Rowan v Lead Constructions Pty Ltd [2021] QCAT 214
- Case
- [2021] QCAT 214
- Decision Date
CaseChat Overview and Summary
The tribunal held that Lead Constructions had breached the contract by failing to complete the works within the stipulated period and by not making any attempt to complete the works after cessation. The tribunal further held that the damages were confined to the agreed liquidated damages as specified in the contract. Mr Rowan's claim for loss of rent was dismissed. The tribunal assessed the total damages payable by Lead Constructions to Mr Rowan, which included the liquidated damages and the filing fees, and ordered Lead Constructions to pay Mr Rowan $19,227.68 in damages and $345.80 in costs.
The tribunal's decision was based on the parties' agreement on the liquidated damages in the contract, which was the sole remedy for delay in completion. The tribunal found that Lead Constructions' failure to comply with directions to file a response had unnecessarily disadvantaged Mr Rowan, justifying the tribunal's power to make a final decision in the proceedings. The tribunal concluded that the damages should be limited to the liquidated damages specified in the contract, and dismissed Mr Rowan's claim for loss of rent. The final orders required Lead Constructions to pay Mr Rowan the assessed damages and costs within 28 days of the decision.
Orders
Orders of the court
1. Lead Constructions Pty Ltd is to pay to Peter Rowan the amount of NINETEEN THOUSAND, TWO HUNDRED AND TWENTY-SEVEN DOLLARS AND SIXTY-EIGHT CENTS ($19,227.68) within 28 days of the date of this decision.
2. Lead Constructions Pty Ltd is to pay to Peter Rowan costs fixed in the amount of THREE HUNDRED AND FORTY-FIVE DOLLARS AND EIGHTY CENTS ($345.80) within 28 days of the date of this decision.
Background
Background to the litigation
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.