CITATION: STUART v FETENI & ORS; COOGEE SANDS APARTMENTS v STUART & ANOR [2004] NSWSC 237 revised - 8/04/2004 HEARING DATE(S): 23/2/04, 24/2/04, 25/2/04, 26/2/04, 27/2/04, 1/3/04, 2/3/04, 3/3/04, 5/3/04 JUDGMENT DATE:
7 April 2004JUDGMENT OF: McDougall J at 1 DECISION: See para [341] of judgment CATCHWORDS: BUILDING AND CONSTRUCTION - contract - amended standard form Building Works Contract - whether entitled to extensions of time - determination of date for extended practical completion - whether entitled to liquidated damages - whether liquidated damages clause a penalty - whether unconditional guarantee of completion date given - whether any such guarantee relied upon - whether negligent certification that the design of works complied with relevant requirements - whether certification relied upon in deciding whether to enter into the contract - misrepresentation LEGISLATION CITED: Trade Practices Act 1974 (Cth) CASES CITED: AMEV-UDC Finance Ltd v Austin (1986) 162 CLR 170
Esanda Finance Corporation Ltd v Plessnig (1989) 166 CLR 131
Multiplex Constructions Pty Ltd v Abgarus Pty Ltd (1992) 33 NSWLR 504
Turner Corporation Pty Ltd (Receiver & Manager Appointed) v Austotel Pty Ltd (1994) 13 BCL 378PARTIES :
In proceedings 55021/01:
In proceedings No. 55010/02:
Stuart Pty Ltd (Plaintiff)
Feteni Pty Ltd (First Defendant)
Robin Edmiston & Associates Pty Ltd (Second Defendant)
Tatton Park Pty Ltd (Third Defendant)
Coogee Sands Apartments Pty Ltd (Plaintiff)
Stuart Pty Ltd (First Defendant)
Alexander Stuart (Second Defendant)FILE NUMBER(S): SC 55021/01; 55010/02 COUNSEL: F C Corsaro SC/M J Dawson (Stuart)
J B Simpkins SC/N J Kidd (Feteni & Coogee Sands)
G A Sirtes (Edmiston & Associates)
I G B Roberts (Tatton Park)
R A Cavanagh (Architects Haywood + Bakker - first cross-defendant in matter 55021/01)SOLICITORS: PricewaterhouseCoopers Legal (Stuart)
Snelgrove & Partners (Feteni & Coogee Sands)
Henry Davis York (Edmiston & Associates)
Phillips Fox (Tatton Park)
James Tuite & Assoc (Architects Haywood + Bakker)
INDEX
STUART PTY LTD v FETENI PTY LTD & ORS
55021/01
COOGEE SANDS APARTMENTS PTY LTD v STUART
PTY LTD & ANOR
55010/02
Paragraph
Introduction 1
Order under Pt 31 r 2 5
The issues for decision 7
The contract 12
Findings on credibility 30
The events leading up to 30 August 1999 49
The meeting of 30 August 1999 62
Extension of time claims: general matters 81
EOT 2: furniture delays 84
The facts 84
The expert evidence 117
Construction of clause 9.01 – critical path 126
The contractual requirements 144
Conclusion on EOT 2 161
EOT 3: planter boxes 162
The facts 162
The expert evidence 186
EOT 3: planter boxes 162
The contractual requirements 195
Conclusion on EOT 3 203
EOT 4: disabled access ramp 204
The facts 204
The expert evidence 241
Stuart’s design obligation 243
Analysis 250
The contractual requirements 265
Conclusion on EOT 4 266
The date for practical completion 267
The date of practical completion 268
Penalty 280
Liquidated damages – other issues 287
The notice argument 288
The grace period 292
The prevention principle 295
Conclusions on liquidated damages 298
Keep reading for free
Create a free CaseChat account to read Stuart v Feteni; Coogee Sands Apartments v Stuart and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2004] NSWSC 237
- Decision Date
CaseChat Overview and Summary
The court first examined the contractual provisions regarding extensions of time and practical completion. It found that Stuart was entitled to an extension of time due to Feteni's failure to provide necessary information, but Stuart was not entitled to an extension for other reasons. The court determined the date for extended practical completion by considering the contractual provisions and the circumstances of the case. Regarding liquidated damages, the court held that the clause was not a penalty as it represented a genuine pre-estimate of loss. However, Stuart was not entitled to liquidated damages due to his own delays. The court also found that no unconditional guarantee of completion date was given, and any guarantee provided was conditional and not relied upon. The court further held that there was no negligent certification and that the certification was not relied upon when deciding whether to enter into the contract. Lastly, the court found that there was no misrepresentation made by Feteni.
The court ordered that Stuart was entitled to an extension of time but not to an amended date for practical completion. Stuart was not entitled to liquidated damages. The court found that there was no negligent certification and no misrepresentation. The final orders were that Stuart was to be compensated for the extension of time, and the parties were to bear their own costs of the proceedings.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.