Fullinfaw v Neil Fletcher Design Pty Ltd

Link copied
Case Copied 27 min read
IN THE SUPREME COURT OF VICTORIA Not Restricted

AT MELBOURNE
COMMON LAW DIVISION
JUDICIAL REVIEW AND APPEALS LIST

S CI 2018 01516

ENID FULLINFAW First Plaintiff
NIGEL FULLINFAW Second Plaintiff
v
NEIL FLETCHER DESIGN PTY LTD
(ACN 087 852 328)
Defendant

---

JUDGE:

GARDE J

WHERE HELD:

Melbourne

DATE OF HEARING:

14 February 2019

DATE OF JUDGMENT:

12 March 2019

CASE MAY BE CITED AS:

Fullinfaw v Neil Fletcher Design Pty Ltd

MEDIUM NEUTRAL CITATION:

[2019] VSC 142

---

DOMESTIC BUILDING CONTRACT – ‘No fault’ termination of major domestic building contract – Liquidated damages claim – Extension of time claim not proven – Builders entitlement – Effect of cap – Recovery of liquidated damages from builder – Domestic Building Contracts Act 1995 (Vic) ss 8(d), 41, 53.

---

APPEARANCES:

Counsel Solicitors
For the Plaintiffs Mr H Foxcroft QC Guymer Lawyers
For the Defendant Mr N Phillpott Macpherson Kelley

HIS HONOUR:

Introduction

  1. An innovative and important feature of the Domestic Building Contracts Act 1995 (Vic) (‘Act’) was the introduction of ‘no fault’ termination of major domestic building contracts by owners if the contract price rose by 15% or more after the contract was entered into, or if the contract was not completed within 1½ times the period by which it was to have been completed, and if the reason for the increased cost or time could not have been reasonably foreseen by the builder when the contract was made.[1]

    [1]Act s 41.

  1. In the present case, the plaintiffs (‘owners’) ended their major domestic building contract (‘building contract’) with the defendant (‘builder’) using the ‘no fault’ provision in s 41 of the Act. The main issue before the Court is whether the owners can deduct liquidated damages for delay, payable under s 8(d) of the Act and under the building contract, from the amount payable to the builder for the work already done before the contract ended.

  1. The owners seek leave to appeal under s 148(2) of the Victorian Civil and Administrative Tribunal Act 1998 (Vic) (‘VCAT Act’) and, if leave is granted, appeal from the decision of the Victorian Civil and Administrative Tribunal (‘Tribunal’) that rejected their claim for liquidated damages.[2] Before turning to the circumstances of the present case, it is appropriate to consider the applicable principles of statutory construction, and the purposes and objects of the Act.

Principles of statutory construction

  1. The principles of statutory construction are well established. In Project Blue Sky Inc v Australian Broadcasting Authority, McHugh, Gummow, Kirby and Hayne JJ said:

... the duty of a court is to give the words of a statutory provision the meaning that the legislature is taken to have intended them to have. Ordinarily, that meaning (the legal meaning) will correspond with the grammatical meaning of the provision. But not always. The context of the words, the consequences of a literal or grammatical construction, the purpose of the statute or the canons of construction may…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Fullinfaw v Neil Fletcher Design Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2019] VSC 142
Decision Date

CaseChat Overview and Summary

Fullinfaw commenced proceedings against Neil Fletcher Design Pty Ltd in the Supreme Court of Victoria, alleging breach of contract and seeking damages in relation to a domestic building contract. The dispute centred around the termination of the contract, the builder's claim for liquidated damages, and the homeowner's counter-claim for an extension of time. The primary issue for the court was whether the builder was entitled to terminate the contract without fault and to claim liquidated damages, and whether the homeowner was entitled to an extension of time due to alleged delays caused by the builder.

The court considered the statutory framework under the Domestic Building Contracts Act 1995 (Vic), particularly sections 8(d), 41, and 53, which provide for the termination of a contract without fault and the calculation of liquidated damages. The court found that the builder had valid grounds to terminate the contract without fault, as the homeowner had failed to make payments in accordance with the contract. The court further determined that the homeowner's claim for an extension of time was not substantiated, as there was no evidence of the builder's actions causing the delays. The cap on liquidated damages under section 41(1)(a) was also considered, and the court held that the builder was entitled to recover the full amount of the liquidated damages, subject to the statutory cap.

In conclusion, the court ruled in favour of the builder, granting the termination of the contract without fault and allowing the recovery of liquidated damages within the statutory cap. The homeowner's claim for an extension of time was dismissed, and the builder's claim for liquidated damages was upheld. The court ordered that the builder was entitled to the full amount of liquidated damages, subject to the statutory cap, and that the homeowner was liable for those damages. The homeowner's counter-claim for an extension of time was dismissed with costs.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.