| IN THE SUPREME COURT OF VICTORIA | Not Restricted |
AT MELBOURNE
COMMON LAW DIVISION
JUDICIAL REVIEW AND APPEALS LIST
S CI 2013 4192
| J G KING PTY LTD | Applicant |
| v | |
| YOGENDRAKUMAR BIPINCHANDRA PATEL and NIHARIKABEN PATEL | Respondents |
---
JUDGE: | KYROU J |
WHERE HELD: | Melbourne |
DATE OF HEARING: | 13 February 2014 |
DATE OF JUDGMENT: | 28 February 2014 |
CASE MAY BE CITED AS: | JG King Pty Ltd v Patel |
| MEDIUM NEUTRAL CITATION: JUDGMENT APPEALED FROM: | [2014] VSC 58 Patel v J G King Pty Ltd [2013] VCAT 1272 (Senior Member M Lothian) |
---
ADMINISTRATIVE LAW — Application for leave to appeal from a decision of the Victorian Civil and Administrative Tribunal — Whether the Tribunal erred in law in finding that a builder was not entitled to charge for rocks excavated and removed from the building site for a new home in excess of the volume of rocks allowed under a major domestic building contract — Whether the clauses in the contract providing for the excess charge complied with provisions of the contract and the Domestic Building Contracts Act 1995 dealing with variations and escalations in the cost of footings — Whether the Tribunal denied the builder natural justice by relying on a statutory provision that was not pleaded by the owners — Whether the Tribunal erred in relation to the method of calculating the volume of rock — Leave to appeal granted — Appeal allowed.
---
APPEARANCES: | Counsel | Solicitors |
| For the Applicant | Mr K C Oliver | Champions Lawyers |
| For the Respondents | Ms S Kirton with Mr T J Guthridge | Brian Williams |
TABLE OF CONTENTS
Introduction and summary............................................................................................................... 1
Execution of Contract and dispute over cost of excavating and removing rock.................... 3
VCAT proceeding.............................................................................................................................. 6
Overarching provisions of the Act................................................................................................ 12
Legal principles for interpreting contracts.................................................................................. 16
Overview of proposed grounds of appeal................................................................................... 17
Did VCAT err in finding Builder’s Claim was not payable under cl 14 of Contract?........ 18
Provisions of Act and Contract dealing with charges for excavations and footings........ 18
VCAT’s decision that the Builder’s Claim was not payable under cl 14 of Contract....... 19
Grounds of appeal relating to VCAT’s decision on the cl 14 issue..................................... 24
Parties’ submissions on the cl 14 issue.................................................................................... 25
Decision on the cl 14 issue......................................................................................................... 26
Did VCAT err in finding that the Builder’s Claim was a variation?...................................... 29
Provisions of Act and Contract dealing with variations to plans or specifications.......... 30
VCAT’s decision that the Claim was a variation.................................................................... 32
Grounds of appeal relating to VCAT’s decision on the variation issue............................. 32
Parties’ submissions on the variation issue............................................................................ 33
Decision on the variation issue................................................................................................. 35
Did VCAT err in deciding how the volume of rock is to be measured?............................... 40
VCAT’s decision that the excavated rock is to be measured in situ................................... 40
Grounds of appeal relating to VCAT’s decision on the measurement issue.................... 42
Parties’ submissions on the measurement issue.................................................................... 43
Decision on the measurement issue......................................................................................... 44
Conclusion: Grant leave to appeal and allow the appeal......................................................... 49
Proposed order.................................................................................................................................. 49
HIS…
Continue reading JG King Pty Ltd v Patel
Sign in free to access the full text
- AGLC
- JG King Pty Ltd v Patel [2014] VSC 58
- Case
- [2014] VSC 58
- Decision Date
CaseChat Overview and Summary
The court was required to decide whether the Tribunal erred in law in finding that the builder was not entitled to charge for the excess rock, whether the contract clauses provided for the excess charge, whether the Tribunal denied the builder natural justice, and whether the Tribunal erred in relation to the method of calculating the volume of rock. The court held that the Tribunal had erred in law in finding that the builder was not entitled to charge for the excess rock. The court found that the contract clauses provided for the excess charge and that the Tribunal had denied the builder natural justice by relying on a statutory provision that was not pleaded by the owners. The court also found that the Tribunal had erred in relation to the method of calculating the volume of rock.
The court granted leave to appeal and allowed the appeal. The court held that the builder was entitled to charge for the excess rock removed from the building site, and that the contract clauses provided for the excess charge. The court also held that the Tribunal had denied the builder natural justice by relying on a statutory provision that was not pleaded by the owners, and that the Tribunal had erred in relation to the method of calculating the volume of rock. The court remitted the matter to the Tribunal for reconsideration in light of the court's findings.
The final orders of the court were that leave to appeal was granted, the appeal was allowed, and the matter was remitted to the Tribunal for reconsideration in light of the court's findings. The builder was entitled to charge for the excess rock removed from the building site, and the contract clauses provided for the excess charge. The Tribunal had denied the builder natural justice and had erred in relation to the method of calculating the volume of rock. The matter was to be reconsidered by the Tribunal in light of the court's findings.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.