Ma & SK Jokovich Pty Ltd v Garland

Link copied
Case Copied 42 min read

QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL


CITATION:

MA & SK Jokovich Pty Ltd v Garland [2025] QCAT 191

PARTIES:

MA & SK JOKOVICH PTY LTD 

(applicant)

v

LUCY GARLAND

(first respondent)

and

NICHOLAS GARLAND

(second respondent)

APPLICATION NO/S:

BDL271-22

MATTER TYPE:

Building matters

DELIVERED ON:

19 May 2025

HEARING DATE:

13 November 2024
14 November 2024

15 November 2024

HEARD AT:

Mackay

DECISION OF:

Member Taylor

ORDERS:

1.     The applicant’s claim is dismissed.

2.     The respondents’ claim by counterapplication is dismissed.

3.     Subject to Order 4 herein, costs are reserved.

4.     Subject to Order 5 herein, should the parties not agree on the issue of costs within 21 days of the date of this order, costs will be determined by this Tribunal in accordance with the following directions:

(a)     Within 28 days of the date of this order, the parties are to each file their respective submissions on costs (if any).

(b)     Within 14 days of being served with the other party’s submissions, each party is to file their submissions on costs in reply (if any).

(c) Unless either party requests a hearing on costs within their submissions filed as per (a) and (b) herein, the issue of costs will thereafter be determined on the papers pursuant to s 32 of the Queensland Civil and Administrative Tribunal Act 2009 (Qld).

5.     In the event that neither party makes any submission on costs in compliance with Order 4(a) herein, the order on costs will be that each party is to bear their own costs of this proceeding.

CATCHWORDS:

CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – REMUNERATION – EXTRAS AND ALTERATIONS – where a contractor performed work said not to be part of the contract – where the contractor did not put any variations as allegedly directed into writing nor have any written agreement with the owners to pay for such variations – where the contractor made a final claim under the contract and was paid in full under the contract, and only thereafter made a claim for payment of the alleged variations

Queensland Building and Construction Commission Act 1991 (Qld), s 77, s108D, Schedule 1B s 4, s 40, s 44

Queensland Building and Construction Commission Regulations 2018 (Qld), s 54

Boys v Imperial Homes [2024] QCATA 35

Chittick v Taylor (1954) 12 WWR (NS) 653
Munro v Camdun Pty Ltd t/as Asset Carpentry & Building Supplies [2024] QCAT 452
MWB Everton Park Pty Ltd as trustee for MWB Everton Park Unit Trust v Devcon Building Co Pty Ltd [2024] QCA 94
Neil v Nott (1994) 68 ALJR 509

Peak Construction (Liverpool) Ltd v McKinney Foundation Ltd (1970) 1 BLR 114

Penfold v Firkn & Balvius [2023] QCATA 11

Thallon Mole Group Pty Ltd v Morton [2022] QDC 224

APPEARANCES & REPRESENTATION:

Applicant:

Self-represented – Mrs S. Jokovich

First Respondent:

Mr T. Randall instructed by McKays Solicitors

Second Respondent:

No appearance

REASONS FOR DECISION

  1. The applicant (Jokovich) built a house for the respondents (the Garlands). The original contract…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Ma & SK Jokovich Pty Ltd v Garland and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2025] QCAT 191
Decision Date

CaseChat Overview and Summary

The case of Ma & SK Jokovich Pty Ltd v Garland involved a dispute between the contractor, Ma & SK Jokovich Pty Ltd, and the property owners, Garland. The contractor had performed additional work beyond what was specified in the contract, and subsequently sought compensation for these extra tasks. The matter was heard in the Queensland Civil and Administrative Tribunal, which had jurisdiction to adjudicate disputes under the Building and Construction Industry Payments Act 2004 (Qld).

The primary legal issues before the Tribunal were whether the additional work performed by the contractor constituted extras or variations under the contract, and if the owners were obligated to pay for these extras given the lack of a written agreement or variation orders. The Tribunal had to determine if the contractor was entitled to additional payment beyond what was stipulated in the original contract and if the owners' obligation to pay was affected by the absence of formal documentation regarding the additional work.

The Tribunal dismissed the contractor's claim, holding that the additional work was not authorised as variations or extras. It found that the contractor had not provided any written variation orders or agreements with the owners for the extra work performed. Furthermore, the fact that the contractor received full payment under the original contract and only subsequently sought compensation for the extras was deemed significant. The Tribunal concluded that the contractor's claim was not supported by the evidence and the applicable legislation. The respondents' counter-claim was also dismissed. The issue of costs was reserved for further determination according to the stipulated process, with an option for the Tribunal to decide costs if the parties could not agree within a set period.

Orders

Orders of the court

1. The applicant’s claim is dismissed.

2. The respondents’ claim by counterapplication is dismissed.

3. Subject to Order 4 herein, costs are reserved.

4. Subject to Order 5 herein, should the parties not agree on the issue of costs within 21 days of the date of this order, costs will be determined by this Tribunal in accordance with the following directions:

(a) Within 28 days of the date of this order, the parties are to each file their respective submissions on costs (if any).

(b) Within 14 days of being served with the other party’s submissions, each party is to file their submissions on costs in reply (if any).

(c) Unless either party requests a hearing on costs within their submissions filed as per (a) and (b) herein, the issue of costs will thereafter be determined on the papers pursuant to s 32 of the Queensland Civil and Administrative Tribunal Act 2009 (Qld).

5. In the event that neither party makes any submission on costs in compliance with Order 4(a) herein, the order on costs will be that each party is to bear their own costs of this proceeding.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.