Medium Neutral Citation: Southern Cross Constructions (NSW) Pty Limited (Administrators Appointed) v Bucasia Pty Limited [2012] NSWSC 1419 Hearing dates: 22 November 2012 Decision date: 22 November 2012 Jurisdiction: Equity Division - Technology and Construction List Before: Stevenson J Decision: Separate question answered "Yes"
Catchwords: BUILDING AND CONSTRUCTION -recourse to security
CONTRACTS - contract purportedly terminated - accrued rightsCases Cited: Kennedy Taylor (Vic) Pty Ltd v Baulderstone Hornibrook Pty Ltd [2000] VSC 43
Macquarie International Health Clinic Pty Ltd v Sydney South West Area Health Service [2010] NSWCA 268
McDonald v Dennys Lascelles Ltd [1933] HCA 25; (1933) 48 CLR 457
Pearson Bridge (NSW) Pty Limited v State Rail Authority of New South Wales [1982] 1 Aust Construction LR 81
Port Jackson Stevedoring Pty Ltd v Salmond & Spraggon (Aust) Pty Ltd (1980) 144 CLR 300Texts Cited: Seddon, Bigwood & Ellinghaus, Cheshire & Fifoot, Law of Contract, 10th ed (2012) Category: Separate question Parties: Southern Cross Constructions (NSW) Pty Limited (Administrators Appointed)
Bucasia Pty Limited
ACN 083 223 107
(plaintiff)
ACN 003 634 842
(defendant)Representation: Counsel:
M Orlov with D Hand (plaintiff)
F G Kalyk (defendant)
Solicitors:
Yates Beaggi Lawyers (plaintiff)
Hunt & Hunt (defendant)
File Number(s): SC 2012/340056 Publication restriction: Nil
Judgment
Introduction
This is the determination of a separate question relating to the proper construction of a contract ("the Contract") made in about late 2010 between the plaintiff, Southern Cross Constructions (NSW) Pty Limited ("Southern Cross") and the defendant, Bucasia Pty Limited ("Bucasia").
Pursuant to the Contract, Southern Cross undertook to design and construct a mixed-use development in Eastwood.
The Contract comprised a number of documents including a "Formal Instrument of Agreement" (which specified a "Contract Sum" of $26,296,634), AS4902-2000 General Conditions of Contract for Design and Construct ("the General Conditions") and various annexures including a document called annexure "Part E" which varied many of the provisions in the General Conditions.
The Contract obliged Southern Cross to provide "contractor's security" in the form of two unconditional insurance bonds each of 2.5 per cent of the Contract sum.
Clause 5.2 of the Contract provided that Bucasia could have "recourse" to that security in the following circumstances: -
"5.2 Recourse
The Principal may have recourse to Security after first giving not less than 5 Business Days [sic] notice to the Contractor where:
a) the Principal has become entitled to exercise a right or power under the Contract in respect of the Security;
b) the Contractor is in default or breach of the Contract;
c) the Contractor has repudiated or given notice of intention to repudiate the Contract;
d) the Contractor has failed to pay the Principal amount certified as owing by the Contractor to the Principal in accordance with clause 37.2A; or
e) the Contractor is otherwise indebted to the Principal and the Principal remains unpaid after 5 business days has [sic] elapsed since the Principal issued an invoice to the Contractor seeking payment of the debt."
On or about 5…
Keep reading for free
Create a free CaseChat account to read Southern Cross Constructions (NSW) Pty Limited (Administrato... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2012] NSWSC 1419
- Decision Date
CaseChat Overview and Summary
The legal issues before the court revolved around the validity of the termination of the contract, the accrued rights of the plaintiff under the contract, and the enforceability of the security deed. The court needed to determine if the termination of the contract negated the plaintiff's right to rely on the security deed and whether accrued rights could be preserved despite the contract's termination.
The court held that the termination of the building contract did not affect the accrued rights of the plaintiff under the contract. Consequently, the plaintiff was entitled to rely on the security deed to recover the amounts owed by the defendant. The court found that the accrued rights were preserved, and the termination of the contract did not nullify the plaintiff's entitlement to security. As a result, the plaintiff was granted recourse to the security provided.
The court's final orders recognised the plaintiff's right to pursue recourse to the security under the deed, affirming that the accrued rights under the contract remained intact despite the termination of the contract. This decision underscores the importance of security arrangements in building contracts and the preservation of rights even in the face of contract termination.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi