Civil and Administrative Tribunal
New South Wales
Medium Neutral Citation: Llamas v Rockwall Constructions Pty Ltd; Rockwall Constructions Pty Ltd v Llamas [2019] NSWCATCD 75 Hearing dates: 14 March 2019 Date of orders: 1 November 2019 Decision date: 01 November 2019 Jurisdiction: Consumer and Commercial Division Before: G.J. Sarginson, Senior Member Decision: 1. In Matter HB 18/47941 Rockwall Constructions Pty Ltd is to pay Rafael Llamas and Kay Llamas the sum of $58,908.85 immediately.
2. In Matter HB 18/47932, the proceedings are dismissed.
3. In both Matter HB 18/47941 and HB 18/47932 Rockwall Constructions Pty Ltd is to pay Rafael Llamas and Kay Llamas costs as agreed or assessed.
4. If either party seeks an alternative or varied costs order, written application must be made to the Tribunal by 14 days from the date of this decision. If such an application is made, the Tribunal will issue further directions regarding the disposition of any costs issues.
Catchwords: BUILDING AND CONSTRUCTION---Repudiation of contract by homeowner---Type of damages available—Defective work---Incomplete work---Appropriate remedy---Assessment of damages
Legislation Cited: Civil and Administrative Tribunal Rules 2014 (NSW)
Home Building Act 1989 (NSW)
Home Building Amendment Act 2014 (NSW)
Australian Consumer Law 2010
Cases Cited: Bellgrove v Eldridge [1954] HCA 36; (1954) 90 CLR 613
David Securities Pty Ltd v Commonwealth Bank of Australia [1992] HCA 48; (1992) 175 CLR 353
DB Homes Australia Pty Limited v Kes [2019] NSWCATAP 221
Deacon v National Strategic Constructions Pty Ltd; National Strategic Constructions Pty Ltd v Deacon [2017] NSWCATAP 185
Grace v Pepe [2016] NSWCATAP 157
Kurmond Homes Pty Ltd v Marsden [2018] NSWCATAP 23
Mann v Paterson Constructions Pty Ltd [2009] HCA 32
McCrohon v Harith [2010] NSWCA 67
McDonald v Dennys Lascelles Ltd (1933) 48 CLR 457
Poulos v Eberstaller [2013] NSWSC 1849
Rockwall Constructions Pty Ltd v Nayak [2017] NSWCATAP 226
Rockwell Constructions Pty v Llamas [2018] NSWCATAP 262
Signature Security v Western Suburbs District Leagues [2002] NSWCA 140
Southern Cross Constructions (NSW) Pty Limited (administrators appointed) v Busasia Pty Limited [2012]
Tabcorp Holdings Ltd v Bowen Investments Pty Ltd [2009] HCA 8 ;(2009) 236 CLR 272
Waltons Stores (Interstate) Pty Ltd v Maher [1988] HCA 7; (1988) 164 CLR 387
Texts Cited: Cheshire and Fifoot 9th Edition
Category: Principal judgment Parties: Matter HB 18/47932
Rockwall Constructions Pty Ltd (Applicant)
Kaye Llamas and Rafael Llamas (Respondent)
Matter HB 18/47941
Rafael Llamas and Kay Llamas (Applicant)
Rockwall Constructions Pty Ltd (Respondent)Representation: Counsel:
J. Gatland (Mr and Ms Llamas)
M. Sneddon (Rockwall Constructions Pty Ltd)
Solicitors:
Adams & Partners (Mr & Ms Llamas)
Fox & Staniland (Rockwall Constructions Pty Ltd)
File Number(s): HB 18/47932; HB 18/47941 Publication restriction: Nil
REASONS FOR DECISION
-
The dispute has a long procedural history in the Tribunal, but the factual issues in dispute in the proceedings are of narrow compass.
-
There is a significant dispute between the parties regarding the legal principles to be applied to the claim by Mr and Ms…
Keep reading for free
Create a free CaseChat account to read Llamas v Rockwall Constructions Pty Ltd; Rockwall Constructi... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2019] NSWCATCD 75
- Decision Date
CaseChat Overview and Summary
The tribunal found that the homeowners were justified in repudiating the contract due to the contractor's failure to complete the work to an acceptable standard. It was determined that the homeowners were entitled to damages for the cost of completing the work to an acceptable standard and for any diminution in the value of the property. The tribunal held that the homeowners were entitled to the full contract price minus the value of the work completed to an acceptable standard. The tribunal assessed the damages and ordered the contractor to pay the homeowners the sum of $58,908.85. The tribunal also dismissed the contractor's cross-claim against the homeowners for non-payment of the contract price. The contractor was ordered to pay the homeowners' costs as agreed or assessed. If either party sought an alternative or varied costs order, a written application was required to be made to the tribunal within 14 days of the decision.
Orders
Orders of the court
1. In Matter HB 18/47941 Rockwall Constructions Pty Ltd is to pay Rafael Llamas and Kay Llamas the sum of $58,908.85 immediately.
2. In Matter HB 18/47932, the proceedings are dismissed.
3. In both Matter HB 18/47941 and HB 18/47932 Rockwall Constructions Pty Ltd is to pay Rafael Llamas and Kay Llamas costs as agreed or assessed.
4. If either party seeks an alternative or varied costs order, written application must be made to the Tribunal by 14 days from the date of this decision. If such an application is made, the Tribunal will issue further directions regarding the disposition of any costs issues.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.