IN THE COURT OF APPEAL OF NEW ZEALAND

CA83/2008
[2009] NZCA 35

BETWEENIAN LAYWOOD AND GARY REES


Appellants

ANDHOLMES CONSTRUCTION WELLINGTON LIMITED


Respondent

Hearing:2 October 2008

Court:Glazebrook, O'Regan and Arnold JJ

Counsel:R B Hucker for Appellant


D M Hughes and K A Van Houtte for Respondent

Judgment:25 February 2009 at 3 pm 

JUDGMENT OF THE COURT

A        The appeal is dismissed.

B We answer the questions on the appeal as set out at [67] below.

CThe appellants must pay the respondent costs for a standard appeal on a band A basis, plus usual disbursements.

REASONS OF THE COURT

(Given by Arnold J)

Background

[1]       The appellants, Messrs Laywood and Rees, were the directors of a company, Holmes & Willis Trust Company Limited (Willis Trust), which owned a substantial building in Wellington.  Willis Trust entered into a construction contract with the respondent, Holmes Construction Wellington Limited (Holmes Construction), for the redevelopment of the building into residential apartments.  The appellants entered into a separate contract with Holmes Construction to pay an additional amount for the same work.

[2]       Difficulties arose during the project.  Ultimately Holmes Construction submitted a final claim for payment in terms of the Construction Contracts Act 2002 (the CCA).  When payment was not made Holmes Construction referred the matter to adjudication under the CCA.

[3]       The adjudicator found that Willis Trust was liable to Holmes Construction for $1,324,165.22, and that the appellants were liable to Holmes for $322,387.27.  When neither sum was paid, Holmes Construction applied to the District Court under s 73(2) of the CCA for the adjudicator’s determinations to be entered as judgments.

[4]       The appellants and Willis Trust brought an application for judicial review of the determinations.  In conjunction with that application they sought interim orders prohibiting Holmes Construction from enforcing the determinations against them until the application for judicial review was determined.  Harrison J granted the interim orders on terms: HC AK CIV-2006-404-809 1 March 2006.  Willis Trust was, by a specified date, to pay the amount owing to a stakeholder, to be held pending the determination of the proceeding or further order of the Court.  Willis Trust did not make the payment, so the interim order in its favour lapsed.  Holmes Construction then proceeded to have judgment entered in the District Court against Willis Trust.

[5]       However, as the interim order in favour of the appellants remained in force, Holmes Construction withdrew its application for the entry of judgment against them.

[6]       By a decision dated 25 May 2006, Harrison J dismissed the application for judicial review, apart from correcting a miscalculation in the determination in relation to interest and GST, which reduced the amount payable by the appellants.  On 6 June 2006 Holmes Construction applied under s 73(2) to enforce the adjudicator’s determination against the appellants by entry as a judgment.  On 27 June 2006 the appellants filed a notice of application that the Holmes Construction application be refused (in effect, a…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Laywood v Holmes Construction Wellington Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2009] NZCA 35
Decision Date

CaseChat Overview and Summary

The Court of Appeal dismissed the appeal of Ian Laywood and Gary Rees against Holmes Construction Wellington Limited. The appeal concerned the enforcement of an adjudicator’s determination under the Construction Contracts Act 2002. The appellants, directors of a company that entered into a construction contract with Holmes Construction, argued that the District Court did not have jurisdiction to enforce adjudicator’s determinations for amounts exceeding $200,000, that they were entitled to a hearing, and that the District Court erred in not considering their payment argument. The Court held that the District Court’s jurisdiction was not limited by s 29 of the District Courts Act 1947, that the appellants were not entitled to an oral hearing, and that the District Court did not breach natural justice by not considering their payment argument. The Court also held that the judgment entered under s 74 of the Construction Contracts Act 2002 is final for the purposes of s 19(1)(d) of the Insolvency Act 1967. The appellants were ordered to pay the respondent’s costs for the appeal.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.