A 2 Z NZ Powercom Limited v Steelcraft Structural Limited

Link copied
Case Copied 13 min read

IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY

I TE KŌTI MATUA O AOTEAROA TĀMAKI MAKAURAU ROHE

CIV-2023-404-881

[2024] NZHC 187

UNDER Section 290 of the Companies Act 1993

IN THE MATTER

of an application to set aside a statutory demand

BETWEEN

A 2 Z NZ POWERCOM LIMITED

Applicant

AND

STEELCRAFT STRUCTURAL LIMITED

Respondent

Hearing: 12 February 2024

Appearances:

N C King for Applicant

G K Holm-Hansen and A J Nisbet for Respondent

Judgment:

15 February 2024


JUDGMENT OF ASSOCIATE JUDGE LESTER

(application to set aside summary judgment)


This judgment was delivered by me on 15 February 2024 at 3:00 pm pursuant to Rule 11.5 of the High Court Rules

Registrar/Deputy Registrar

A 2 Z NZ POWERCOM LIMITED v STEELCRAFT STRUCTURAL LIMITED [2024] NZHC 187

[15 February 2024]

[1]    A 2 Z NZ Powercom Limited (Powercom) applies to set aside a statutory demand issued by Steelcraft Structural Limited (Steelcraft).

[2]    The statutory demand is for $29,761.24 being costs awarded by this Court recorded in an order sealed 30 August 2022 and served shortly thereafter. When the costs were not paid a statutory demand was issued which Powercom seeks to set aside.

How did the costs award arise?

[3]    I am assisted in the preparation of this part of the judgment by the decision of Lang J in Steelcraft Structural Ltd v A 2 Z NZ Powercom Ltd, which led to the costs award in issue.1 I adopt his Honour’s background to the commercial relationship and the dispute between the parties.

[4]    Powercom is the owner of land situated at 443 East Tamaki Road. A building known as the “New Zealand Badminton Centre” is situated on that land. Powercom’s shareholders and directors are Mr Senthiya Devathasan (also known as Mr Senthiya) and his wife.

[5]    Steelcraft designs, fabricates and installs structural steel. Between March and December 2021 Steelcraft provided structural steel for extensions that were being made to the building situated on Powercom’s land. Steelcraft issued nine monthly payment claims under s 20 of the Construction Contracts Act 2002 (the CCA) for this work. Powercom did not serve a payment schedule challenging any of Steelcraft’s payment claims.

[6]    Steelcraft says it completed its obligations under the contract in or about December 2021. On 19 November 2021, Steelcraft served the ninth and final payment claim seeking payment of the sum of $252,125.88. This sum was due to be paid by 20 December 2021. Steelcraft subsequently received a payment of $60,000, leaving an outstanding amount of $192,125.88.


1      Steelcraft Structural Ltd v A 2 Z NZ Powercom Ltd [2022] NZHC 2017.

[7]    On 21 December 2021, Steelcraft served a statutory demand on Powercom under s 289 of the Companies Act 1993. The demand required Powercom to pay the sum of $192,125.88 within 15 working days.   Powercom failed to comply with     the statutory demand. As a result, it was presumed Powercome is unable to pay its debts.2

[8]    Lang J found Steelcraft had issued a…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read A 2 Z NZ Powercom Limited v Steelcraft Structural Limited and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2024] NZHC 187
Decision Date

CaseChat Overview and Summary

A 2 Z NZ Powercom Limited (Powercom) sought to set aside a statutory demand issued by Steelcraft Structural Limited (Steelcraft) for $29,761.24 in costs awarded by the court. The dispute originated from a construction contract where Steelcraft provided structural steel for extensions to the New Zealand Badminton Centre on land owned by Powercom. Steelcraft issued nine monthly payment claims under the Construction Contracts Act 2002 (CCA), which Powercom did not challenge. After Steelcraft completed its work and submitted a final payment claim, Powercom failed to pay the outstanding amount, leading Steelcraft to issue a statutory demand under the Companies Act 1993.

The legal issues before the court were whether Powercom could establish a substantial dispute regarding the debt and whether it could raise a counterclaim or cross-demand against Steelcraft. The court examined the principles for setting aside statutory demands, which include proving a substantial dispute and providing material evidence. Powercom argued that it had a substantial counterclaim for late completion damages and overpayments due to unapproved variations, which could offset the debt. However, Steelcraft contended that under the CCA, the recovery of costs from a statutory demand precluded Powercom from raising a counterclaim unless the debt was undisputed.

The court found that Powercom could not establish a substantial dispute as per the requirements of the CCA. Steelcraft's statement of defence in the District Court did not admit liability for the liquidated damages claim, and there were unresolved issues regarding variations and delays. Therefore, the court concluded that Powercom's application to set aside the statutory demand failed, and it ordered Powercom to pay Steelcraft's costs on a 2B basis, together with disbursements as fixed by the Registrar.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established