IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
I TE KŌTI MATUA O AOTEAROA TĀMAKI MAKAURAU ROHE
CIV-2022-404-85
[2022] NZHC 2017
BETWEEN STEELCRAFT STRUCTURAL LIMITED
Plaintiff
AND
A 2 Z NZ POWERCOM LIMITED
Defendant
Hearing: 11 and 15 August 2022 Appearances:
N Gillies and L Sharpe for Plaintiff N King for Defendant
Judgment:
15 August 2022
JUDGMENT OF LANG J
[on application for order placing defendant in liquidation]
This judgment was delivered by me on15 August 2022 at 3.30 pm, pursuant to Rule 11.5 of the High Court Rules.
Registrar/Deputy Registrar Date……………
Solicitors:
Hesketh Henry, Auckland
STEELCRAFT STRUCTURAL LTD v A 2 Z NZ POWERCOM LTD [2022] NZHC 2017 [15 August 2022]
[1] The issue to be determined in this proceeding is whether the Court should make an order under s 241 of the Companies Act 1993 (the Act) placing the defendant, A 2 Z NZ Powercom Limited (Powercom) in liquidation. The plaintiff, Steelcraft Structure Limited, (Steelcraft) contends such an order is appropriate because Powercom has failed to pay it the sum of approximately $192,000. It therefore says Powercom is insolvent because it is unable to pay its debts as they fall due. Steelcraft also contends it is just and equitable for such an order to be made.
[2] Powercom says the Court should not make an order placing it in liquidation. It contends there is a genuine dispute in relation to the debt that Steelcraft claims is owing to it. It also contends it is not insolvent.
Background
[3] Powercom is the owner of land situated at 443 East Tamaki Road. A building known as the “New Zealand Bandminton Centre” is situated on that land. Powercom’s shareholders and directors are Mr Senthiya Devathasan (also known as Mr Senthiya) and his wife.
[4] Steelcraft designs, fabricates and installs structural steel. Between March and December 2021 Steelcraft provided structural steel for extensions that were being made to the building situated on Powercom’s land. Steelcraft issued nine monthly payment claims under s 20 of the Construction Contracts Act 2002 (the CCA) for this work. Powercom did not serve a payment schedule challenging any of Steelcraft’s payment claims.
[5] Steelcraft says it completed its obligations under the contract in or about December 2021. On 19 November 2021 Steelcraft served the ninth and final payment claim seeking payment of the sum of $252,125.88. This sum was due to be paid by 20 December 2021. Steelcraft subsequently received a payment in the sum of $60,000, leaving an outstanding amount of $192,125.88.
[6] On 21 December 2021, Steelcraft served a statutory demand on Powercom under s 289 of the Companies Act 1993. This required Powercom to pay the sum of
$192,125.88 within 15 working days. Powercom failed to comply with the statutory demand. As a result, it is now presumed to be unable to pay its debts.1
[7] On 4 February 2022 Steelcraft filed the present proceeding in which it seeks an order placing Powercom in liquidation. Powercom filed a statement of defence on 8…
Keep reading for free
Create a free CaseChat account to read Steelcraft Structural Ltd v A 2 Z NZ Powercom Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2022] NZHC 2017
- Decision Date
CaseChat Overview and Summary
The court began by considering the identity of the contracting parties. Powercom contended that the contract was entered into by its director, Mr Senthiya Devathasan, in his personal capacity, and not by Powercom itself. The court rejected this argument, finding that the contract was entered into by Powercom and that Mr Devathasan had signed the contract on behalf of Powercom as its director. The court also noted that Mr Devathasan had not asserted that he was contracting in his personal capacity until Steelcraft filed the present proceeding, and that this assertion was a belated attempt to avoid Powercom being placed in liquidation.
The court then considered whether Steelcraft had served a valid payment claim. Powercom argued that the payment claim did not comply with the Construction Contracts Act 2002 because it was not accompanied by the prescribed advice regarding Powercom’s rights and obligations if it wished to dispute the claim. The court rejected this argument, finding that the payment claim was accompanied by a standard form that set out the required advice. The court also noted that Mr Devathasan had not objected to the form of the payment claim when he received it, and that he was now endeavouring to use a technical argument to avoid being placed in liquidation.
The court then considered whether the debt was genuinely disputed. Powercom argued that it had counterclaims and cross-demands against Steelcraft that should be taken into account at this stage. The court rejected this argument, finding that the only means by which the recipient of a payment claim can contest it is by serving a payment schedule in response. Powercom had not served a payment schedule in response to the payment claim, and it was therefore too late to raise any argument now. The court also found that Powercom could not rely upon an argument that Steelcraft had not yet provided it with all warranties, certifications and producer statements relating to the work it had carried out, because this argument was not pleaded in Powercom’s statement of defence or in the particulars of its defence that it provided at Steelcraft’s request. Nor did Mr Devathasan raise it when he received the payment claim.
Finally, the court considered whether Powercom was insolvent. Powercom had failed to comply with a statutory demand that Steelcraft served on it, and it was therefore presumed to be unable to pay its debts. Powercom had filed a copy of its financial statements for the year ended 31 March 2021, which showed that it had a surplus of assets over liabilities in the sum of approximately $189,000. However, this information related to the company’s position 17 months ago, and the court was therefore unable to make any finding that Powercom was solvent as at the present time. It followed that Powercom had not rebutted the presumption of insolvency that arose when it failed to comply with the statutory demand. The court was also satisfied that there was nothing oppressive in Steelcraft utilising liquidation proceedings to enforce payment of the debt, particularly when Powercom never responded either to the payment claim or the statutory demand. However, the court was prepared to give Powercom a final opportunity to pay the debt, and adjourned the proceeding to give it that opportunity. If the payment had not been made by the adjourned date, the court would make an order placing Powercom in liquidation.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.