Birchler v Homebuild Homes Limited

Link copied
Case Copied 30 min read

IN THE HIGH COURT OF NEW ZEALAND PALMERSTON NORTH REGISTRY

I TE KŌTI MATUA O AOTEAROA TE PAPAIOEA ROHE

CIV-2023-454-34

[2023] NZHC 2547

UNDER the Construction Contracts Act 2002

BETWEEN

COLIN ANDREW BIRCHLER and ROBYN KAYLENE BIRCHLER

Appellants

AND

HOMEBUILD HOMES LIMITED

Respondent

Hearing: 16 August 2023

Counsel:

Appellants in person

G P Mason for Respondent

Judgment:

13 September 2023


JUDGMENT OF RADICH J


Introduction

[1]                The appellants (Mr and Mrs Birchler) and the respondent (Homebuild) entered into a contract under which Homebuild was to build a house for Mr and Mrs Birchler just to the north of Feilding.

[2]                Payments under construction contracts are governed by the Construction Contracts Act 2002 (the Act). Under the Act, a builder1 may issue a “payment claim” relating to a payment sought for construction work carried out.2 A customer3 may


1      More particularly under the Act, a “payee” which, in s 19, is defined as “the party to a construction contract who is entitled to a payment”.

2 `    Section 20.

3      More particularly under the Act, a “payer” which, in s 19, is defined as “the party to a construction contract who is liable for that payment”.

BIRCHLER v HOMEBUILD HOMES LIMITED [2023] NZHC 2547 [13 September 2023]

respond to a payment claim by providing a “payment schedule” which, in essence, identifies the amount they will be paying and, if it is less than the amount sought in the payment claim, explains why.4 If a payment schedule is not provided by a certain date, the sum sought in the payment claim may be recovered as a due debt.5

[3]                The payment that is required under a payment claim does not prevent a builder’s customer from raising a dispute about, for example, the reasonableness of the claim or the quality of the builder’s work. But, if a payment schedule is not issued, they must pay first.

[4]                Homebuild issued one of its final payment claims to Mr and Mrs Birchler. It claimed just over $45,000, primarily for the cost of engineering work over and above a limited engineering estimate that was given in the contract document.  Mr and   Mrs Birchler did not issue a payment schedule in response and they did not pay the sum claimed in the payment claim. As a consequence, the sum claimed became a due debt and there were grounds for summary judgment to be entered for Homebuild – which the District Court did in the decision under appeal.

[5]                Mr and Mrs Birchler feel particularly aggrieved by the whole affair. They say that the sums claimed in the payment claim are not justified, that they have not received a proper breakdown or explanation of them and that they relate to substandard work. This was the focus of their appeal. While the Court acknowledges the detail the plaintiffs have provided on those points, and the intensity of their views on them, there is no place in this proceeding for substantive underlying issues of that sort to be considered. They…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Birchler v Homebuild Homes Limited and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2023] NZHC 2547
Decision Date

CaseChat Overview and Summary

Colin Andrew Birchler and Robyn Kaylene Birchler appealed against a decision of the District Court that granted summary judgment in favour of Homebuild Homes Limited. The appeal was out of time, but leave was granted to appeal out of time. The issue on appeal was whether the District Court had erred in granting summary judgment on Homebuild's claim. The Court held that the District Court was correct in its decision. The statutory scheme of the Construction Contracts Act 2002 requires a party to a construction contract to follow a strict procedure for making and responding to payment claims. Under this scheme, a party must respond to a payment claim by providing a payment schedule within the requisite time period. If a party does not provide a payment schedule within the requisite time period, the sum claimed becomes a debt due. The Birchlers did not provide a payment schedule within the requisite time period. Instead, they raised objections to the sums claimed in the payment claim. However, these objections did not comply with the statutory requirements for payment schedules. The Court held that the Judge was correct in concluding that the Birchlers were obliged to pay the sum sought in the payment claim and that the points made in their notice of opposition did not provide a tenable defence to that obligation. The appeal was dismissed.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.