IN THE HIGH COURT OF NEW ZEALAND PALMERSTON NORTH REGISTRY
I TE KŌTI MATUA O AOTEAROA TE PAPAIOEA ROHE
CIV-2023-454-34
[2024] NZHC 534
UNDER the Construction Contracts Act 2002 BETWEEN
COLIN ANDREW BIRCHLER and ROBYN KAYLENE BIRCHLER
Appellants
AND
HOMEBUILD HOMES LIMITED
Respondent
Hearing: 12 March 2024 Counsel:
Appellants in person
G P Mason for Respondent
Judgment:
13 March 2024
JUDGMENT OF RADICH J
(Leave to appeal)
[1] Mr and Mrs Birchler seek leave, out of time, to appeal against my decision of 13 September 2023 in which I dismissed their appeal against a decision of the District Court.1
[2] In the District Court decision, summary judgment was entered against them and in favour of Homebuild for $45,613.26 plus interest and costs2 being the sum due by them to Homebuild under a Construction Contracts Act 2002 payment claim.
1 Birchler v Homebuild Homes Ltd [2023] NZHC 2547.
2 Homebuild Homes Ltd v Birchler [2023] NZDC 1320.
BIRCHLER v HOMEBUILD HOMES LIMITED [2024] NZHC 534 [13 March 2024]
[3] Mr and Mrs Birchler say that the Construction Contracts Act regime should not prevail over what they see as being unwarranted charges on Homebuild’s part and that their arguments on those charges still need to be addressed substantively in this proceeding.
[4] Homebuild says that there is no point of sufficient importance raised by Mr and Mrs Birchler to outweigh the cost and delay of a second appeal. Because Mr and Mrs Birchler did not challenge the payment claim under the relevant provisions of the Construction Contracts Act, it became a due debt. Issues about building quality or costs can, it is said, be raised in separate proceedings, but not in this proceeding. Moreover, Homebuild says, the application for leave has been filed well out of time and there is no adequate explanation for the delay.
Construction Contracts Act scheme – as applied in the District Court and High Court decisions
[5]As was discussed in the September 2023 decision:
(a)Homebuild issued a payment claim to Mr and Mrs Birchler under s 20 of the Construction Contracts Act. It related to charges for engineering works in the house that Homebuild was building for Mr and Mrs Birchler.
(b)Under s 21 of the Construction Contracts Act, if items in a payment claim are disputed, a lesser amount of money may be paid, within a statutory time frame, as long as it is provided with a payment schedule which explains why.
(c)Mr and Mrs Birchler did not pay a lesser amount and did not provide a payment schedule. Their relationship with Homebuild came to an end at that point and their house was completed by other builders.
(d)Had Mr and Mrs Birchler paid what they thought was due, with a payment schedule, then processes are prescribed under the
Construction Contracts Act for the dispute to be determined. Otherwise, the sum must be paid and any underlying dispute can be raised in separate proceedings.
(e)Summary judgment for the payment claim was entered by the District…
Keep reading for free
Create a free CaseChat account to read Birchler v Homebuild Homes Limited and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2024] NZHC 534
- Decision Date
CaseChat Overview and Summary
The court examined the principles guiding the exercise of the court’s discretion to grant leave to appeal. For leave to be granted, the appeal must raise a question of law or fact that was capable of genuine and serious argument in a case involving a public or private interest of sufficient importance to outweigh the cost and delay of an appeal. The court had to consider if the appeal raised a point of sufficient importance to justify a second appeal. The court acknowledged the lengths to which the Birchlers had gone to express their views and the intensity of those views. However, the court was constrained by the Construction Contracts Act scheme, which was described as a "pay now, argue later" scheme. The court concluded that the ability of the Court to consider the points that the Birchlers wished to raise was constrained by the Construction Contracts Act scheme. The Birchlers could use separate proceedings or dispute resolution processes to address the points that concerned them.
The application for leave was also made out of time. The judgment was delivered on 13 September 2023. The application for leave to appeal was filed on 21 December 2023, 45 days after the 20 working day period prescribed by r 20.22(2) for the bringing of an application for leave expired. The court had the discretion to extend the time for making the application for leave. The court acknowledged that the Birchlers were struggling with the procedural aspects of the proceeding and had not allowed the timing issue to get in the way of the court's consideration of the application itself.
For the reasons given, the application for leave to appeal was declined.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.