IN THE HIGH COURT OF NEW ZEALAND WELLINGTON REGISTRY
CIV-2015-485-457 [2016] NZHC 211
UNDER the Judicature Amendment Act 1972 and
the Construction Contracts Act 2002
IN THE MATTER OF
an adjudication held pursuant to Part 3
Construction Contracts Act 2002BETWEEN
MANCHESTER INDUSTRIAL HOLDINGS LIMITED Applicant
AND
ANDREW G HAZELTON First Respondent
BUSSELL CONSTRUCTION LIMITED Second Respondent
Hearing: 26 January 2016 Counsel:
J R Grace for applicant
No appearance for first respondent (abiding the decision) F B Collins for second respondent
Judgment:
18 February 2016
RESERVED JUDGMENT OF DOBSON J
[1] This proceeding comprises an application for judicial review alleging errors of law by an adjudicator in a determination under the Construction Contracts Act
2002 (CCA). The applicant (MIH) owns a block of residential flats in Eva Street, central Wellington, including a penthouse on the top floor of the building. MIH concluded an oral contract with the respondent (Bussell) to do building work on the property. The work could be characterised as either part of earthquake strengthening work being undertaken by engineers at the property, or otherwise renovations being
undertaken contemporaneously with earthquake strengthening work.
MANCHESTER INDUSTRIAL HOLDINGS LTD v ANDREW G HAZELTON [2016] NZHC 211 [18 February
2016]
[2] The contract was not for a fixed price, but rather Bussell was to charge for the time its workers spent working at the premises, plus charges for the materials used. Invoices were to be presented on a monthly basis.
[3] Bussell undertook physical works between late 2012 and early 2013 and MIH paid the first five claims up to February 2013 for a total of some $103,000. Questions were raised on behalf of MIH and by its architect about the content of Bussell’s invoices after the first five payments. Those questions were not resolved and on 1 April 2013 Bussell issued a further payment claim for $27,499.05. MIH questioned the payment claim and its concerns remained unresolved.
[4] On 6 April 2013, MIH terminated its contract with Bussell and engaged an alternative builder to complete the works contemplated by the original contract with Bussell.
[5] On 13 April 2013, Bussell issued another payment claim for a further
$16,942.64. The following day, 14 April 2013, MIH emailed Bussell, disputing both of the April payment claims. That email stated that Bussell’s work had been defective and asked for particulars of the charges. Further information was sought including details of the areas of work to which the various components of the charges related. There was no timely response. However, some 15 months later on
31 July 2014, Bussell issued a payment claim for $40,648.15 plus GST. It described the claim as relating to work on the Eva Street project for the period from
26 November 2012 to 5 April 2013.
[6] The following day, MIH emailed back to Bussell in the following terms:
Dear Geoff
Your claim for payment is not accepted
As previously discussed this account is disputed
The matters raised in our correspondence to you last year have not been addressed
Keep reading for free
Create a free CaseChat account to read Manchester Industrial Holdings Limited v Hazelton and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2016] NZHC 211
- Decision Date
CaseChat Overview and Summary
The High Court examined whether Bussell's payment claim satisfied the statutory requirements under section 20 of the CCA. The Court found that the payment claim met the necessary criteria, despite MIH's contentions that it was insufficiently detailed. The Court also scrutinized MIH's response, specifically an email dated 1 August 2014, to determine if it qualified as a payment schedule under section 21 of the CCA. The adjudicator had ruled that MIH's email did not constitute a valid payment schedule because it failed to indicate the manner in which MIH had calculated the scheduled amount and the reasons for the difference between the scheduled amount and the claimed amount.
The Court agreed with the adjudicator's assessment that MIH's email did not sufficiently detail the required information to qualify as a payment schedule. While the Court acknowledged that the adjudicator's requirement for a payment schedule to be in a single document was an error of law, it concluded that MIH's communications were inadequate regardless. Therefore, the application for judicial review was dismissed, and Bussell was awarded costs.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi