For a Court ready (fee required) version please follow this link
IN THE COURT OF APPEAL OF NEW ZEALAND
CA454/2014 [2014] NZCA 539
BETWEEN SOL TRUSTEES LIMITED
Appellant
AND
GILES CIVIL LIMITED Respondent
Hearing: 1 October 2014 Court:
French, Venning and Dobson JJ
Counsel:
B P Molloy and R W H Kirwan-Jones for Appellant
D M Hughes and E E Cowle for RespondentJudgment:
10 November 2014 at 3.00 pm
JUDGMENT OF THE COURT
A The appeal is dismissed.
BThe appellant is to pay the respondent costs for a standard appeal on a band A basis with usual disbursements. Allowance for one counsel only.
REASONS OF THE COURT
(Given by Venning J)
Introduction
[1] SOL Trustees Ltd (SOL) appeals a decision of Associate Judge Sargisson dismissing its application to set aside two statutory demands issued by Giles Civil
Ltd (Giles).1 The primary issue on appeal is whether Associate Judge Sargisson was
SOL TRUSTEES LTD v GILES CIVIL LTD CA 454/2014 [2014] NZCA 539 [10 November 2014]
correct to find SOL had failed to provide a valid payment schedule,2 with the effect that Giles was entitled to serve its statutory demands to recover two outstanding payments as due debts.
Background
[2] SOL and Giles were parties to a construction contract in relation to a 20 lot subdivision at 258–272 Okura River Road, Auckland. SOL was the principal and Giles was the contractor. The contract terms included the terms in New Zealand Standard 3910:2003 Conditions of Contract for Building and Civil Engineering Construction.
[3] Airey Consultants Ltd (Airey Consultants) was appointed as engineer under the contract. Airey Consultants had two roles, to act as advisor to and representative of SOL as principal, and, independently of both SOL and Giles, to make decisions under the contract, value work and issue certificates.
[4] The parties also agreed a process for the certification of progress payments. Giles was to send its payment claims to both SOL and Airey Consultants. Airey Consultants would then issue a provisional progress payment schedule certifying the amount due. SOL then had three working days to respond.
[5] Construction commenced on 17 December 2012. The original scheduled completion date under the contract was 17 May 2013. The work was not completed by that date.
[6] Issues arose when Airey Consultants sent a provisional progress payment
schedule certifying Giles’ payment claim 10 for $565,366 to SOL on 19 October
2013. By email of 22 October to Airey Consultants, SOL’s director Mr Hamilton advised the claim was disputed. He also prepared a spreadsheet claiming “Project Overrun Costs”, being costs SOL claimed it had incurred because of the delays. On SOL’s calculations the total loss attributed to the delayed completion was
$1,121,747.
2 Construction Contracts Act 2002, s 21.
[7] Although Mr Hamilton initially asked Airey Consultants to keep the spreadsheet confidential, all parties met on 25 October 2013 to discuss the contract. At the meeting Mr Hamilton provided a copy…
Keep reading for free
Create a free CaseChat account to read SOL Trustees Ltd v Giles Civil Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2014] NZCA 539
- Decision Date
CaseChat Overview and Summary
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.