Energy Plant Solutions Limited v Thermal Protection Services Limited

Link copied
Case Copied 22 min read

IN THE HIGH COURT OF NEW ZEALAND HAMILTON REGISTRY

I TE KŌTI MATUA O AOTEAROA KIRIKIRIROA ROHE

CIV-2025-419-61

[2025] NZHC 2849

BETWEEN

ENERGY PLANT SOLUTIONS LIMITED

Applicant

AND

THERMAL PROTECTION SERVICES LIMITED

Respondent

Hearing: 22 May 2025

Counsel:

D Sheppard for the Applicant

KA Lomas and JM Perry for the Respondent

Judgment:

30 September 2025


JUDGMENT OF ASSOCIATE JUDGE SUSSOCK


This judgment was delivered by me on 30 September 2025 at 4 pm pursuant to r 11.5 of the High Court Rules

Registrar/Deputy Registrar

Solicitors:

Braun, Bond & Lomas Limited, Hamilton Cooper Rapley Lawyers, Palmerston North

ENERGY PLANT SOLUTIONS LTD v THERMAL PROTECTION SERVICES LTD [2025] NZHC 2849 [30

September 2025]

Introduction

[1]    Energy Plant Solutions Limited (EPS) applies for an order setting aside a statutory demand served on it by Thermal Protection Services Limited (TPS) for

$425,519.00.

[2]    EPS engaged TPS as a subcontractor to complete insulation works on a biomass-fired boiler at a plant in Tokoroa.

[3]    Issues arose which led TPS to write to EPS on 23 May 2024 advising that TPS would not be completing part of the works as the scope of the project had changed from the original pricing.

[4]    Following correspondence between the parties’ solicitors, TPS issued a payment claim on 1 October 2024 for $387,105.38 which was its calculation of the total amount owing for the works completed (October Claim). EPS responded by letter on 11 October 2024 claiming the works carried out by TPS were defective and that EPS had an unquantified counterclaim, such that EPS “had no obligation to make any payment to [TPS] whatsoever”.

[5]    On 22 November 2024, TPS issued a further payment claim for $397,567.42 (November Claim). EPS did not respond to the November claim. This led to the issue of the statutory demand by TPS, relying on s 23 of the Construction Contracts Act 2002 (CCA). This section provides that failure to respond to a payment claim with a payment schedule means the amount claimed in the payment claim is recoverable as a debt due.

[6]EPS seeks to argue that:

(a)the October Claim was a valid payment claim under the CCA which triggered obligations on EPS to respond;

(b)the letter of 11 October 2024 issued by EPS’s lawyers in response was a valid payment schedule for the purposes of the CCA;

(c)TPS was not entitled to resend the payment claim as the November Claim; and

(d)EPS was therefore not required to respond to the November Claim with a payment schedule.

[7]    Essentially EPS submits that a claimed amount that has already been the subject of dispute in a previous payment schedule does not become a debt due and recoverable through the Court if the payment claim is simply resent and the respondent does not provide a payment schedule in response. EPS submits that rather than it owing TPS money, EPS has a claim for $664,419.02 (excluding GST) against TPS for the losses and costs that TPS has caused as a result of TPS’s alleged defaults.

[8]…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Energy Plant Solutions Limited v Thermal Protection Services... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2025] NZHC 2849
Decision Date

CaseChat Overview and Summary

Energy Plant Solutions Limited (EPS) applied to the High Court of New Zealand for an order setting aside a statutory demand served by Thermal Protection Services Limited (TPS) for $425,519.00. The dispute arose from a construction subcontract where TPS was engaged by EPS to complete insulation works at a Tokoroa plant. Issues surfaced, leading TPS to advise EPS on 23 May 2024 that it would not complete part of the works due to changes in the project scope. Following this, TPS issued two payment claims: an October Claim for $387,105.38 on 1 October 2024 and a November Claim for $397,567.42 on 22 November 2024. EPS responded to the October Claim but did not respond to the November Claim, leading TPS to issue the statutory demand. EPS argued that the November Claim was invalid, and that its response to the October Claim should be considered a valid payment schedule. TPS contended that the November Claim was valid and that EPS was required to respond with a payment schedule. The court held that TPS was entitled to issue the November Claim, as the failure to respond to it rendered EPS liable to pay the claimed amount. The application to set aside the statutory demand was declined. TPS was awarded costs, with the parties to confer on the amount, and if necessary, file memoranda.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established