IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
I TE KŌTI MATUA O AOTEAROA TĀMAKI MAKAURAU ROHE
CIV-2024-404-1196
CIV-2024-404-1653 [2024] NZHC 3421
BETWEEN CPB CONTRACTORS PTY LIMITED
Applicant
AND
FZ GROUP NZ LIMITED RESPONDENT
Hearing: 24 September 2024
Post-hearing submissions completed 30 October 2024
Appearances:
L M Van and R H Turi for the Applicant T J P Bowler for the Respondent
Judgment:
18 November 2024
JUDGMENT OF ASSOCIATE JUDGE SKELTON
This judgment was delivered by me on 18 November 2024 at 4.00 pm, pursuant to r 11.5 of the High Court Rules
Registrar/Deputy Registrar
[1] The applicant, CPB Contractors Pty Ltd (CPB) (as main contractor), and the respondent FZ Group Ltd (FZ Group) (as subcontractor) entered into a construction contract on 14 October 2020 for partitions, linings and other works at Waikeria Prison (contract).
CPB CONTRACTORS PTY LIMITED v FZ GROUP NZ LIMITED [2024] NZHC 3421 [18 November 2024]
[2] Issues arose between the parties in 2022. Ultimately, the parties issued a statutory demand against each other. Each party now applies to set aside the statutory demand issued by the other party under s 290 of the Companies Act as follows:
(a)FZ Group has issued a statutory demand against CPB for the sum of
$443,179.75 (including GST) relating to payment claim 20 under the contract. CPB has applied to set aside the statutory demand on the basis that FZ Group is a solvency risk and CPB will be irretrievably prejudiced if the statutory demand is upheld; payment claim 20 was invalid and in any event, superseded by payment claim 21; it has a counterclaim in the sum of $3,553,748.19 (including GST) relating to the contract; the statutory demand is therefore an abuse of process (first application).
(b)CPB has issued a statutory demand against FZ Group for the amount of
$3,553,748.19 (including GST). FZ Group has applied to set aside that statutory demand on the basis that the parties agreed that additional costs of completion would be claimed from the Department of Corrections and there would be no claim against FZ Group (second application).
What happened?
[3] On 14 April 2022, FZ Group submitted payment claim 20 for $443,179.75 under the Construction Contracts Act 2002 (CCA) (payment claim 20).1
[4] CPB contends that the parties were in ongoing discussions about payment claim 20 in the period following the issue of the claim.
[5] On 13 May 2022, FZ Group submitted payment claim 21, for what CPB says was an identical sum and scope of work (payment claim 21). CPB contends that payment claim 21 superseded payment claim 20. FZ Group disputes this.
1 Construction Contracts Act 2002, s 20.
[6] No payment schedule was issued in response to payment claim 20 as required by the Act.2
[7] FZ Group issued a statutory demand for payment claim 20 on 20 May 2022. Following discussions between the parties, this was withdrawn on 26 May 2022. FZ Group says that it withdrew its statutory demand on the basis of assurances from CPB…
Keep reading for free
Create a free CaseChat account to read CPB Contractors Pty Limited v FZ Group Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2024] NZHC 3421
- Decision Date
CaseChat Overview and Summary
Regarding CPB's application, the court found that payment claim 20 was validly issued and not superseded by payment claim 21. The court held that CPB could not argue that the statutory demand was an abuse of process, even if FZ Group was aware of potential disputes and CPB's counterclaim, because issuing a statutory demand under the Construction Contracts Act 2002 (CCA) was not an abuse of process. The court also found that CPB had not established a high degree of likelihood that FZ Group would not be able to repay if a determination under the CCA went in FZ Group's favour, nor a good arguable case that it would succeed under the CCA. Thus, the application by CPB to set aside FZ Group's statutory demand was dismissed, with the compliance time extended by ten working days.
Regarding FZ Group's application, the court found that there was arguably a substantial dispute as to the existence of the debt due to a "walk away" agreement between the parties. The court held that there was a substantial dispute as to the nature, terms, and effect of the "walk away" agreement and whether it brought the contract to an end. The court also found that there was arguably a substantial dispute as to whether an estoppel arose out of the discussions between the parties. Therefore, the application by FZ Group to set aside CPB's statutory demand was granted.
The court encouraged the parties to agree on costs and directed that if they could not reach an agreement, memoranda not exceeding three pages (excluding costs schedules) could be filed, and costs would be determined on the papers.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.