IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
CIV-2013-404-2692 [2013] NZHC 2481
IN THE MATTER of the Companies Act 1993 AND
IN THE MATTER
of a statutory demand served on 10 May 2013
BETWEEN
CMP CONSTRUCTION LIMITED
Applicant
AND
ALUMINIUM TECHNOLOGY LIMITED
Respondent
| Hearing: | 12 September 2013 |
Counsel: | DW Grove for applicant PM Hunter for respondent |
Judgment: | 23 September 2013 |
JUDGMENT OF ASSOCIATE JUDGE FAIRE
[on application to set aside statutory demand]
This judgment was delivered by me on 23 September 2013 at 2:30pm pursuant to Rule 11.5 of the High Court Rules.
Registrar/Deputy Registrar Date……………
Solicitors:Ellis Law, Auckland Simpson Western, Auckland
CMP CONSTRUCTION LTD v ALUMINIUM TECHNOLOGY LTD [2013] NZHC 2481 [23 September 2013]
The application
[1] The applicant, CMP Construction Ltd, applies to set aside a statutory demand served by the respondent, Aluminium Technology Ltd, on it on 10 May 2013 and which seeks payment of the sum of $50,928.06. The sum sought in the statutory demand relates to two specific contracts, namely:
Target Court $24,681.31; and
Lovell Court $26,246.75.
[2] Mr Hunter acknowledged that the correct amount for which the statutory demand should have been issued in respect of the Target Court contract was
$20,039.56 and that the correct amount that should have been claimed in respect of the Lovell Court contract was $22,091.33 making a total of $42,130.89. The revised figures were arrived at by deleting the reference to retention sums. Mr Grove had no objection to my considering a claim for the revised amount. That is, in fact, appropriate having regard to s 290(5) and (6) of the Companies Act 1993.
[3] The application pleads three principle grounds in support of it, namely, that:
(a)There is a genuine and substantial dispute whether or not the debt is owing and is due;
(b)It has a counterclaim/set-off that is in excess of any sums allegedly due to the respondent; and
(c)Service of the statutory demand is an abuse of process.
It is also asserted that no sum is due from the applicant to the respondent. That is really not a separate ground, but is encapsulated in the three grounds that I have mentioned.
The statutory basis for the application
[4] The application is made in reliance on the three grounds specified in s 290(4)(a), (b) and (c) of the Companies Act 1993. Section 290(4) provides:
290 Court may set aside statutory demand
…
(4)The Court may grant an application to set aside a statutory demand if it is satisfied that—
(a)There is a substantial dispute whether or not the debt is owing or is due; or
(b)The company appears to have a counterclaim, set-off, or cross-demand and the amount specified in the demand less the amount of the counterclaim, set-off, or cross-demand is less than the prescribed amount; or
(c)The demand ought to be set aside on other grounds.
[5] The court’s approach to an application to set aside a statutory demand based on the Companies Act 1993, s 290(4)(a) can be shortly stated. The court…
Keep reading for free
Create a free CaseChat account to read CMP Construction Ltd v Aluminium Technology Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2013] NZHC 2481
- Decision Date
CaseChat Overview and Summary
The court examined the statutory demand and the payment claims, finding that the applicant had failed to provide payment schedules in response to the payment claims within the required timeframe. Consequently, the respondent was entitled to the amount claimed under the Act. The court rejected the applicant's arguments regarding the validity of the payment claims, finding no substantial basis for invalidating them. As a result, the court concluded that there was no proper basis for setting aside the statutory demand in respect of the sums due for the Target Court subcontract of $20,039.56 and the Lovell Court subcontract in the sum of $18,032.06, making a total of $38,071.62.
The court ordered that if the applicant did not pay the sum of $38,071.62 within ten working days of the release of the judgment, the respondent could apply to put the applicant into liquidation. The court reserved the question of costs, allowing the parties to agree on the appropriate position or file memoranda for the court's determination.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.