C&R Property Development Limited v Mr Civil Limited

Link copied
Case Copied 18 min read

IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY

I TE KŌTI MATUA O AOTEAROA TĀMAKI MAKAURAU ROHE

CIV-2020-404-000025

[2020] NZHC 1470

UNDER section 290 of the Companies Act 1993

IN THE MATTER

an application to set aside a statutory demand

BETWEEN

C&R PROPERTY DEVELOPMENT LIMITED

Applicant

AND

MR CIVIL LIMITED

Respondent

Hearing: [On the Papers]

Counsel:

D M Hughes and E Cowle for the Applicant

L L Fraser and S R Holden for the Respondent

Judgment:

26 June 2020


JUDGMENT OF EDWARDS J


This judgment was delivered by me on 26 June 2020 at 4.00 pm pursuant to r 11.5 of the High Court Rules.

Registrar/Deputy Registrar

Solicitors:    Anthony Harper, Auckland

Chapman Tripp, Auckland

C&R PROPERTY DEVELOPMENT LTD v MR CIVIL LTD [2020] NZHC 1470 [26 June 2020]

[1]        The applicant, C&R Property Development Ltd (C&R) applies to set aside a statutory demand served by MR Civil Ltd (MR Civil).

[2]        The statutory demand is for the sum of $1,015,753.36. It arises out of an adjudication determination dated 18 December 2019 under the Construction Contracts Act 2002 (CCA) (Determination).

[3]        Whether the statutory demand should be set aside turns on the following key questions:

(a)Is there a high likelihood that MR Civil will not be able to repay the debt if this Court subsequently rules in C&R’s favour?

(b)Does C&R have a good arguable case?

(c)Is the issue of the statutory demand an abuse of process?

[4]By consent, the application is determined on the papers.

Background

[5]        C&R is a development company. It owns a site in Huapai, Auckland that it is developing as a residential subdivision. In December 2017 C&R contracted MR Civil to undertake civil works and earthworks on that site.

[6]        Issues between the parties arose early in the project and continued throughout. The departure of MR Civil’s appointed representative appears to have brought the dispute to a head. On 11 April 2019, MR Civil issued Payment Schedule 16. C&R refused to pay and instead transferred the certified sum to its solicitor’s trust account.

[7]        C&R terminated the contract on 24 May 2019 relying on an alleged lack of performance by MR Civil. It claimed damages and reimbursement of costs amounting to approximately $1.9 million from MR Civil.

[8]        MR Civil disputed the validity of C&R’s termination and denied any liability for the claim. It subsequently terminated the contract on 28 August 2019, and claimed a total sum amounting to just under $1.6 million from C&R.

[9]In his Determination, the Adjudicator:

(a)Concluded that MR Civil’s termination of the contract was effective and C&R’s earlier termination was not.

(b)Ruled that C&R was to pay MR Civil the sum of $1,015,753.36 within two working days of receipt of the Determination. That sum comprised:

(i)$294,666.45 (plus GST), being the amount calculated as owing under Payment Schedule 16; plus

(ii)$25,587.40, being the interest calculated as owing on Payment Schedule 16; plus

(iii)$105,907.61 (plus GST), being the amount calculated as retentions for Payment Schedule 16; plus

(iv)$163,071.17 (plus GST), being…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read C&R Property Development Limited v Mr Civil Limited and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2020] NZHC 1470
Decision Date

CaseChat Overview and Summary

C&R Property Development Ltd (C&R) applied to set aside a statutory demand served by MR Civil Ltd (MR Civil) for the sum of $1,015,753.36, which arose out of an adjudication determination under the Construction Contracts Act 2002 (CCA). The key questions for the court were whether MR Civil had a high likelihood of being unable to repay the debt if C&R’s claims were successful, whether C&R had a good arguable case, and whether the statutory demand constituted an abuse of process. The court found that C&R could not establish a high likelihood of MR Civil being unable to repay the debt, and that C&R did not have a good arguable case for judicial review or counterclaims. The court also found that the statutory demand was not an abuse of process. The application to set aside the statutory demand was dismissed, and MR Civil was entitled to costs.