IN THE HIGH COURT OF NEW ZEALAND INVERCARGILL REGISTRY
I TE KŌTI MATUA O AOTEAROA WAIHŌPAI ROHE
CIV-2023-425-082
[2024] NZHC 1049
UNDER section 290 of the Companies Act 1993 IN THE MATTER
of an application to set aside a statutory demand
BETWEEN
TRIPLE CONNECTION LIMITED
Applicant
AND
CONCEPT BUILDERS QUEENSTOWN LIMITED
Respondent
Hearing: 23 April 2024 Appearances:
M R T Colthart for Applicant R P Conner for Respondent
Judgment:
2 May 2024
JUDGMENT OF ASSOCIATE JUDGE PAULSEN
This judgment was delivered by me on 2 May 2024 at 3.30 pm pursuant to Rule 11.5 of the High Court Rules.
Registrar/Deputy Registrar Date:
TRIPLE CONNECTION LIMITED v CONCEPT BUILDERS QUEENSTOWN LIMITED [2024] NZHC 1049 [2 May 2024]
[1] The applicant, Triple Connection Ltd (TCL), applies to set aside a statutory demand served by the respondent, Concept Builders Queenstown Ltd (Concept), relating to a debt arising from an adjudicator’s determination under the Construction Contracts Act 2002 (the Act) in Concept’s favour. TCL submits there are exceptional circumstances justifying the setting aside of the statutory demand because it is challenging the adjudicator’s determination in other proceedings, it has a good arguable case it will succeed, and considers any amount it pays to satisfy the adjudicator’s determination (and the statutory demand) may be irrecoverable from Concept. Concept opposes the application, arguing there are no exceptional circumstances justifying the Court setting aside the statutory demand.
Background
[2] TCL entered a construction subcontract with Concept under which Concept provided labour for a residential construction project in Queenstown known as Jade Lake Queenstown. Between March 2021 and June 2022, TCL paid in full the 40 invoices rendered by Concept under the subcontract, totalling $1,476,500.87 (including GST).
[3] From around June 2022, Jinlin Wang took over the day-to-day management of TCL’s operations. He sought to revisit Concept’s charges. A dispute arose which ultimately led to termination of the subcontract. In mid-December 2022, Concept commenced an adjudication under the Act with the Building Disputes Tribunal, claiming approximately $130,000 from TCL.
[4] TCL opposed Concept’s claim, including on the ground of overcharging by Concept. TCL relied upon a report prepared by quantity surveyors, Rawlinsons, which it considers shows a very significant disparity between the total number of labour hours claimed by Concept (27,240.5 hours), and the labour hours required to carry out the work (between 15,408 and 17,139 hours).
[5] By a determination dated 16 February 2023, the adjudicator determined TCL is liable to pay Concept the sum of $134,266.34 (including GST) (the interim determination).1
[6] The adjudicator, who it is accepted is a highly regarded expert in construction law, did not accept that the Rawlinsons report supported TCL’s position because of “limitations and exclusions recorded by Rawlinsons”.2 He said:
[112] The Rawlinsons report was correct to identify those limitations and exclusions. This is especially so given my findings above as to additional work, disruption and delays. Absent Rawlinsons revisiting its review and findings taking further account of those matters, I am not prepared to accord any weight to the…
Keep reading for free
Create a free CaseChat account to read Triple Connection Limited v Concept Builders Queenstown Limi... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2024] NZHC 1049
- Decision Date