IN THE HIGH COURT OF NEW ZEALAND WELLINGTON REGISTRY
I TE KŌTI MATUA O AOTEAROA TE WHANGANUI-A-TARA ROHE
CIV-2019-485-465
[2019] NZHC 3223
UNDER section 290 of the Companies Act 1993 IN THE MATTER
of an application to set aside a statutory demand
BETWEEN
ALPINE PRIME PROPERTIES LIMITED
Applicant
AND
HASKELL CONSTRUCTION LIMITED
Respondent
Hearing: 25 October 2019 Appearances:
F B Collins for applicant M Freeman for respondent
Judgment:
9 December 2019
JUDGMENT OF ASSOCIATE JUDGE JOHNSTON
Introduction
[1] The applicant, Alpine Prime Properties Ltd (Alpine), applies to set aside a statutory demand dated 31 July 2019 and served on it by the respondent, Haskell Construction Ltd (Haskell), on 1 August 2019. Haskell’s demand is for payment of a debt of $133,619.06 due pursuant to an adjudication determination under s 25 of the Construction Contract Act 2002 issued on 29 July 2019.
[2]Haskell opposes the application.
ALPINE PRIME PROPERTIES LIMITED v HASKELL CONSTRUCTION LIMITED [2019] NZHC 3223
[9 December 2019]
Background
[3] Alpine is a property developer. It owns four lots in a subdivision in Ruapehu Street, Paraparaumu. Haskell is a construction company. Its director is Mr Christopher Haskell. The company was incorporated three years ago and employs about 11 staff.
[4] On 3 August 2018, Alpine and Haskell entered into a contract for the construction of a residential dwelling on one of the lots in Ruapehu Street. The contract price was about $800,000, which was to be paid in nine stages as the development progressed. Construction commenced in August 2018. By September 2018 Haskell had completed stage one (foundations and floor structure). An invoice was issued for stage one and paid by Alpine.
[5] An issue then arose concerning the introduction of structural steel members into the building design. The consented plans upon which Haskell tendered for the contract did not include steel, but these plans were based on provisional engineering designs. The structural framing then went through several revisions, with the result that steel would be required. On 10 December 2018, Haskell received the revised design including the steel.
[6] On 29 January 2019, Haskell sought to increase the contract price to accommodate the inclusion of the steel. Alpine did not accept the proposed variation to the contract price. Meanwhile, Haskell had continued with the construction works, largely completing stage two (wall and roof framing) except for the steel work.
[7] On 13 February 2019, Haskell issued a payment claim for stage two, arguing it had achieved “substantial completion” within the meaning of the construction contract. A site meeting was held on 26 February 2019. A disagreement emerged.
[8] On 18 April 2019, Alpine purported to cancel the contract pursuant to ss 362N(2)(b) and 362O(a) of the Building Act 2004, alleging substantial breaches of contract by Haskell. On 24 April 2019, Haskell purported to accept Alpine’s cancellation as though it had been made under cl 15.2.2(c) of the contract, which
allows cancellation where the parties agree the contract has become impossible to perform or is otherwise frustrated.
[9] On…
Keep reading for free
Create a free CaseChat account to read Alpine Prime Properties Limited v Haskell Construction Limit... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2019] NZHC 3223
- Decision Date
CaseChat Overview and Summary
The court needed to decide whether Alpine could rely on its counterclaim for damages to avoid making an interim payment of the debt owed to Haskell. The legal issue was whether section 79 of the Construction Contracts Act, which restricts counterclaims and set-offs in proceedings for the recovery of a debt, applied to statutory demands under the Companies Act 1993. The court had to determine whether Alpine could set aside the statutory demand if it had a substantial counterclaim that might exceed the amount claimed.
The court held that Alpine could not rely on its counterclaim to avoid the interim payment requirement established by the Construction Contracts Act. Section 79 of the Act precluded the consideration of any counterclaim or set-off in proceedings for the recovery of a debt arising from an adjudication award. The court found that the purpose of the Act was to facilitate timely payments and resolve disputes quickly, and enforcing the adjudication award on a ‘pay now, argue later’ basis was consistent with this purpose. The court also noted that Alpine’s reliance on Kariiti Ltd v Donovan Drainage & Earthmoving Ltd was misplaced, as that case involved a different procedural context.
Alpine’s application to set aside the statutory demand was dismissed, and the court reserved costs pending further submissions from the parties. The court held that there was no scope for entertaining any counterclaim or set-off where a statutory demand was served to enforce an adjudication award under the Construction Contracts Act.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.