SOL Trustees Ltd v Giles Civil Ltd

Link copied
Case Copied 19 min read

IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY

CIV-2014-404-000459

CIV-2014-404-000299 [2014] NZHC 1813

BETWEEN

SOL TRUSTEES LIMITED

Plaintiff

AND

GILES CIVIL LIMITED Defendant

Hearing: 5 May 2014

Appearances:

B P Molloy and R W H Kirwan-Jones for the Applicant
D M Hughes and E E Cowle for the Respondent

Judgment:

4 August 2014

JUDGMENT OF ASSOCIATE JUDGE SARGISSON

This judgment was delivered by me on 4 August 2014 at 4.50 p.m. pursuant to Rule 11.5 of the High Court Rules.

Registrar/Deputy Registrar

Date.......................................

Solicitors / Counsel: Kensington Swan, Auckland

Haigh Lyon, Auckland
B P Molloy, Auckland

Case officer:    Katrina Tauhinu

SOL TRUSTEES LIMITED v GILES CIVIL LIMITED [2014] NZHC 1813 [4 August 2014]

Introduction

[1]      Sol Trustees Limited applies for orders under s 290 of the Companies Act

1993 to set aside two statutory demands. Giles Civil Limited served Sol Trustees with  the  first  demand  on  31  January  2014,  claiming  Sol  Trustees  owes  it

$842,539.48 on its Payment Claim 13, and with the second demand on 26 February

2014, claiming $130,409.50 on its Payment Claim 14, each case for work undertaken pursuant to a construction contract.

[2]      Under the Construction Contracts Act 2002 (the Act), if a payment claim is served on a party to a construction contract and payment of the lesser of the claimed amount or the amount scheduled in a payment schedule is not made within the time allowed in the contract or otherwise within 20 working days, the claimant is entitled

to recover the amount of the claim as a debt due.1

[3]      Sol Trustees has not paid the amounts demanded of it.   It contends it is entitled to an order setting aside the statutory demands on the basis that it has responded to the payment claims by providing responses that are sufficient to constitute valid payment schedules within the time allowed pursuant to the contract, and in respect of which there is a real dispute within the contemplation of s 290(4) of the Companies Act.

[4]      The applications are opposed and the parties have requested that they be heard together.

Issues for determination

[5]      There are two overarching issues that arise for determination in deciding whether or not there should be an order to set aside the statutory demands:

(a)       Is there a substantial dispute as to whether or not the debt is owing or due?  This turns on whether Sol delivered valid payment schedules in

response to Payment Claims 13 and 14 – which also turns on whether

1      Construction Contracts Act 2002, s 23.

it is able to treat those responses and its prior response to Payment

Claim 10 as a cumulative response; and if so

(b)Whether, for the purpose of such a response, it is able to rely on a set- off or counterclaim based on its claimed entitlement to liquidation damages under the contract for costs of delay.

[6]      There   is   a   remaining   issue   that   arises   from   Sol’s   submission   that Payment Claims 13 and 14 are substantially the same and…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read SOL Trustees Ltd v Giles Civil Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2014] NZHC 1813
Decision Date

CaseChat Overview and Summary

Sol Trustees Limited applied to the High Court for an order setting aside two statutory demands served by Giles Civil Limited under section 290 of the Companies Act 1993. Giles served the first demand on 31 January 2014 for $842,539.48 on its Payment Claim 13, and the second on 26 February 2014 for $130,409.50 on its Payment Claim 14, each for work undertaken pursuant to a construction contract. Sol contended it was entitled to an order setting aside the statutory demands on the basis that it had provided responses to the payment claims that constituted valid payment schedules, and in respect of which there was a real dispute within the contemplation of section 290(4) of the Companies Act. The overarching issues were whether there was a substantial dispute as to whether or not the debt was owing or due, and whether Sol was able to rely on a set-off or counterclaim based on its claimed entitlement to liquidated damages under the contract for costs of delay. The court held that Sol had not provided valid payment schedules to Payment Claims 13 and 14, and therefore the statutory demands could not be set aside on the basis of a substantial dispute within the contemplation of section 290 of the Companies Act. The time for compliance with the statutory demands was extended to 15 working days from the date of judgment. Failing compliance, Giles may proceed with an action for liquidation. Costs followed the event. Giles was entitled to costs on a 2B basis plus disbursements as fixed by the Registrar.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.