IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
I TE KŌTI MATUA O AOTEAROA TĀMAKI MAKAURAU ROHE
CIV 2020-404-000572
[2020] NZHC 1942
BETWEEN THE FLETCHER CONSTRUCTION COMPANY LIMITED
Applicant
AND
SPOTLESS FACILITY SERVICES (NZ) LIMITED
Respondent
Hearing: 19 June 2020 Appearances:
A M Callinan and D A Rowe for the Applicant
S C Price, J K Stewart & R A Donald for the Respondent
Judgment:
5 August 2020
JUDGMENT OF VAN BOHEMEN J
This judgment was delivered by me on 05 August 2020 at 12noon Pursuant to Rule 11.5 of the High Court Rules
…………………………
Registrar/Deputy Registrar
Solicitors/Counsel:
Simpson Grierson, Auckland MinterEllisonRuddWatts, Auckland
THE FLETCHER CONSTRUCTION COMPANY LIMITED v SPOTLESS FACILITY SERVICES (NZ) LIMITED [2020] NZHC 1942 [5 August 2020]
Introduction
[1] The applicant, The Fletcher Construction Company Ltd (Fletcher), seeks a declaration that notices by the respondent, Spotless Facility Services NZ Ltd (Spotless), of its intention to suspend its contract works and then suspending its contact works in the latter stages of the construction of the Commercial Bay development in downtown Auckland were invalid and of no effect.
[2] The central issue in dispute is whether a payment schedule issued by Fletcher to Spotless in January 2020 in response to a payment claim by Spotless for work performed by Spotless was valid in terms of the Construction Contracts Act 2002 (the Act). If the payment schedule was valid, Spotless’s suspension notices were invalid. Conversely, if the payment schedule was invalid, Spotless’s suspension notices were valid.
[3] Both Fletcher and Spotless argue the validity of the payment schedule on a holistic basis – the whole of the payment schedule is either valid or invalid. Neither argues that the payment schedule could be partially valid and partially invalid.
Relevant background
[4] Precinct Properties Ltd (Precinct) has been building the Commercial Bay office tower and retail precinct in the Auckland central business district which was nearing completion in the early months of 2020 prior to the arrival of the coronavirus pandemic in New Zealand. Fletcher is the head contractor with Precinct for the construction of the development. Spotless, which trades in New Zealand as AE Smith, is a subsidiary of the Australian Downer Group. Fletcher has a subcontract with Spotless for the provision of mechanical services required for the heating and cooling of the buildings, which includes ensuring fresh air intake, air quality and ventilation.
[5] Fletcher says Spotless is a critical subcontractor for the completion of the development and that its work is closely inter-related to work by other subcontractors and finishing trades, in particular Black Interiors Ltd (Black) and Alaska Construction & Interiors Ltd (Alaska). Black and Alaska have worked in close proximity to
Spotless in the tower, which is a key component of the development, and their fit-out work is related to the work by Spotless.
[6]On 24 January 2020, Spotless issued Fletcher Payment Claim No 44 (Claim
44) seeking payment of $2,067,715.86 plus GST. This was the 44th payment claim submitted by Spotless on the project to…
Keep reading for free
Create a free CaseChat account to read Fletcher Construction Company Limited v Spotless Facility Se... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2020] NZHC 1942
- Decision Date
CaseChat Overview and Summary
The High Court of New Zealand found that the payment schedule did not substantially comply with section 21 of the Act. Specifically, the Court found issues with the manner in which Fletcher calculated the scheduled amounts, the reasons for the differences between the scheduled and claimed amounts, and the reasons for withholding payment. The Court held that while the payment schedule provided some information, it did not sufficiently indicate the reasons for the deductions, particularly for the contra charges related to costs incurred by Fletcher due to delays caused by Spotless. The Court ruled that the payment schedule was invalid, and therefore, Spotless's suspension of work was valid. The Court dismissed Fletcher's application for a declaration that Spotless's suspension notices were invalid and of no effect.
As a result, Spotless is entitled to costs on a 2B basis. If the parties cannot agree on the costs, they may submit memoranda of no more than 4 pages each, with Spotless's memorandum due by 25 August 2020 and Fletcher's in reply by 8 September 2020. This decision highlights the importance of compliance with the requirements of the Construction Contracts Act 2002 and the consequences of non-compliance for both parties involved in construction contracts.