Templeton Kingsland Limited v Dominion Constructors Limited

Link copied
Case Copied 34 min read

IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY

I TE KŌTI MATUA O AOTEAROA TĀMAKI MAKAURAU ROHE

CIV-2021-404-130

[2021] NZHC 2960

UNDER the Companies Act 1993

IN THE MATTER

of an application to set aside a statutory demand

BETWEEN

TEMPLETON KINGSLAND LIMITED

Applicant

AND

DOMINION CONSTRUCTORS LIMITED

Respondent

Hearing: 12 May 2021

Appearances:

K Kemp and J Morton for the Applicant

G Holm-Hansen and A Eager for the Respondent

Judgment:

3 November 2021


JUDGMENT OF ASSOCIATE JUDGE SUSSOCK


This judgment was delivered by me on 3 November 2021 at 3.30pm pursuant to r 11.5 of the High Court Rules

Registrar/Deputy Registrar

Solicitors:

Anthony Harper, Auckland Hesketh Henry, Auckland

TEMPLETON KINGSLAND LTD v DOMINION CONSTRUCTORS LTD [2021] NZHC 2960

Introduction

[1]                 The applicant, Templeton Kingsland Limited (“TKL”), applies to set aside a statutory demand served by the respondent, Dominion Constructors Limited (“Dominion”).

[2]The statutory demand was issued following TKL’s payment of only

$321,934.37 in response to a payment claim of $5,979,906.67 issued by Dominion. The claim was Payment Claim 50 issued under a contract entered into for the construction of an apartment complex in Kingsland, Auckland.

[3]                 TKL provided a payment schedule by the due date but Dominion submits that it is not valid (either in part or in whole) because:

(a)the Engineer to the Contract failed to value variations submitted by Dominion as required by the contract; and

(b)significant deductions were made against Payment Claim 50 with inadequate and insufficient reasons being stated as required by the Construction Contracts Act (“CCA”).

[4]                 If no valid payment schedule is provided in response to a payment claim by the due date, the payer (in this case TKL) is liable to pay the full amount claimed in the payment claim. If the payer does not do so, s 23 of the CCA provides that the payee may recover the unpaid portion of the amount claimed in the payment claim as a debt due together with the actual and reasonable costs of recovery.

[5]                 TKL submits that there is no debt owing because a fully compliant payment schedule was provided and TKL paid the scheduled amount within the time required. Increased or indemnity costs are sought on the basis that issuing the statutory demand in these circumstances is an abuse of process. In TKL’s submission the demand is an attempt to circumvent the contractual process for variations and the dispute resolution provisions in the contract and the CCA.

[6]                 To succeed in its application to set aside the demand TKL must establish that there is arguably a genuine and substantial dispute as to whether a debt is owing. This depends on the validity of the payment schedule. This in turn depends on whether the grounds on which Dominion says the payment schedule is invalid can be relied on to establish invalidity.

Issues

[7]To determine this application, two issues therefore need to be considered:

(a)Is the Engineer to the Contract required to value variations in the payment schedule for it to be valid under…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Templeton Kingsland Limited v Dominion Constructors Limited and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2021] NZHC 2960
Decision Date

CaseChat Overview and Summary

The matter before the Court was an application by Templeton Kingsland Limited to set aside a statutory demand issued by Dominion Constructors Limited. Dominion had issued a statutory demand after TKL paid only $321,934.37 in response to a payment claim of $5,979,906.67 issued by Dominion under a contract for the construction of an apartment complex in Kingsland, Auckland. The applicant, TKL, sought to set aside the statutory demand on the basis that there was a substantial dispute as to whether a debt was owing. Dominion argued that the payment schedule provided by TKL was invalid because it did not include values for variations submitted by Dominion. The Court found that it was arguable that the Engineer to the Contract was not required to value variations in the payment schedule for it to comply with the Construction Contracts Act. The Court also found that it was arguable that the reasons given for the deductions made against the variations were sufficiently indicated. Accordingly, the Court granted the application to set aside the statutory demand. The Court noted that it may be appropriate to award increased or indemnity costs to TKL. The parties were directed to confer and only if costs were unable to be agreed, file memoranda on behalf of TKL within 20 working days of the decision and on behalf of Dominion within a further 10 working days.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established