IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
I TE KŌTI MATUA O AOTEAROA TĀMAKI MAKAURAU ROHE
CIV-2021-404-130
[2021] NZHC 2960
UNDER the Companies Act 1993 IN THE MATTER
of an application to set aside a statutory demand
BETWEEN
TEMPLETON KINGSLAND LIMITED
Applicant
AND
DOMINION CONSTRUCTORS LIMITED
Respondent
Hearing: 12 May 2021 Appearances:
K Kemp and J Morton for the Applicant
G Holm-Hansen and A Eager for the Respondent
Judgment:
3 November 2021
JUDGMENT OF ASSOCIATE JUDGE SUSSOCK
This judgment was delivered by me on 3 November 2021 at 3.30pm pursuant to r 11.5 of the High Court Rules
Registrar/Deputy Registrar
Solicitors:
Anthony Harper, Auckland Hesketh Henry, Auckland
TEMPLETON KINGSLAND LTD v DOMINION CONSTRUCTORS LTD [2021] NZHC 2960
Introduction
[1] The applicant, Templeton Kingsland Limited (“TKL”), applies to set aside a statutory demand served by the respondent, Dominion Constructors Limited (“Dominion”).
[2]The statutory demand was issued following TKL’s payment of only
$321,934.37 in response to a payment claim of $5,979,906.67 issued by Dominion. The claim was Payment Claim 50 issued under a contract entered into for the construction of an apartment complex in Kingsland, Auckland.
[3] TKL provided a payment schedule by the due date but Dominion submits that it is not valid (either in part or in whole) because:
(a)the Engineer to the Contract failed to value variations submitted by Dominion as required by the contract; and
(b)significant deductions were made against Payment Claim 50 with inadequate and insufficient reasons being stated as required by the Construction Contracts Act (“CCA”).
[4] If no valid payment schedule is provided in response to a payment claim by the due date, the payer (in this case TKL) is liable to pay the full amount claimed in the payment claim. If the payer does not do so, s 23 of the CCA provides that the payee may recover the unpaid portion of the amount claimed in the payment claim as a debt due together with the actual and reasonable costs of recovery.
[5] TKL submits that there is no debt owing because a fully compliant payment schedule was provided and TKL paid the scheduled amount within the time required. Increased or indemnity costs are sought on the basis that issuing the statutory demand in these circumstances is an abuse of process. In TKL’s submission the demand is an attempt to circumvent the contractual process for variations and the dispute resolution provisions in the contract and the CCA.
[6] To succeed in its application to set aside the demand TKL must establish that there is arguably a genuine and substantial dispute as to whether a debt is owing. This depends on the validity of the payment schedule. This in turn depends on whether the grounds on which Dominion says the payment schedule is invalid can be relied on to establish invalidity.
Issues
[7]To determine this application, two issues therefore need to be considered:
(a)Is the Engineer to the Contract required to value variations in the payment schedule for it to be valid under…
Keep reading for free
Create a free CaseChat account to read Templeton Kingsland Limited v Dominion Constructors Limited and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2021] NZHC 2960
- Decision Date
CaseChat Overview and Summary
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi