South Pacific Industrial Limited v Demasol Limited

Link copied
Case Copied 33 min read

IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY

I TE KŌTI MATUA O AOTEAROA TĀMAKI MAKAURAU ROHE

CIV-2021-404-960

[2021] NZHC 3597

UNDER Section 290 of the Companies Act 1993

IN THE MATTER

of an application to set aside a statutory demand dated 6 May 2021

BETWEEN

SOUTH PACIFIC INDUSTRIAL LIMITED

Applicant

AND

DEMASOL LIMITED

Respondent

Hearing: 11 August 2021

Appearances:

PJ Crombie and PJ Anderson for the Applicant M Russell and C Smith for the Respondent

Judgment:

22 December 2021


JUDGMENT OF ASSOCIATE JUDGE SUSSOCK


This judgment was delivered by me on 22 December 2021 at 3.30pm pursuant to r 11.5 of the High Court Rules

Registrar/Deputy Registrar

Solicitors:

CooneyLees Morgan, Tauranga Rice Speir, Auckland

SOUTH PACIFIC INDUSTRIAL LTD v DEMASOL LTD [2021] NZHC 3597 [22 December 2021]

Introduction

[1]    This dispute arises from the demolition of a large concrete tank in Penrose owned by BOC Ltd. BOC invited South Pacific Industrial Ltd (“SPI”) to provide a quote for demolishing the tank which contained materials contaminated by asbestos. The tank and all associated materials required removal.

[2]    Demasol Ltd specialises in asbestos removal so SPI asked Demasol to provide a quote to carry out the bulk of the work as its subcontractor.

[3]SPI says that the contract agreed with Demasol was for a fixed price of

$100,000.00 exclusive of GST and tipping costs. Two payment claims were issued by Demasol for a total of $390,997.29. No payment schedules were issued in respect of either. Demasol therefore issued a statutory demand relying on the provisions in the Construction Contracts Act 2002 (“CCA”) which allow a party to recover the whole of a payment claim as a debt due where no payment schedule is issued and no payment made.

[4]SPI has applied to set aside the statutory demand on the following grounds:

(a)there is a substantial dispute as to whether the debt is owing;

(b)the contract covering the works performed by Demasol was for a fixed price of $100,000.00 plus GST, plus tipping costs for foam glass blocks at a maximum of $600.00 per tonne plus GST;

(c)the payment claim issued by Demasol, which the statutory demand is largely based on, was not calculated in accordance with the agreed contract price and is therefore not a valid payment claim under the CCA;

(d)variations claimed by Demasol were neither permitted under the fixed price contract nor agreed by SPI; and

(e)SPI has paid Demasol the agreed contract price, together with variations that were agreed by it, in full.

[5]    Demasol submits in response that the contract price was an estimate only and allowed variations and that it has issued two valid payment claims to which payment schedules were not issued. It was therefore entitled to issue the statutory demand and it ought not to be set aside. In Demasol’s submission, setting aside the demand would be inconsistent with the “pay now, argue later” regime provided for in the CCA.

[6]    Furthermore, Demasol says it has reason to believe that SPI cannot pay…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read South Pacific Industrial Limited v Demasol Limited and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2021] NZHC 3597
Decision Date

CaseChat Overview and Summary

This case involved an application by South Pacific Industrial Ltd (“SPI”) to set aside a statutory demand issued by Demasol Ltd under the Construction Contracts Act 2002 (“CCA”). SPI claimed that the statutory demand should be set aside because there was a substantial dispute as to whether the debt claimed by Demasol was owing and due. SPI also claimed that the statutory demand should be set aside on other grounds. The key issues were whether the contract was a fixed price contract, whether the payment claims were valid, and whether the statutory demand should be set aside on other grounds. The court found that it was reasonably arguable that the contract was a fixed price contract and that SPI’s standard terms were not incorporated as terms of the subcontract. The court also found that it was reasonably arguable that the payment claims were not valid because they were not issued in accordance with the contract terms and because a significant portion of the claims related to variations that were not authorised. As a result, the statutory demand served on SPI was set aside. The court reserved costs but indicated that SPI, having succeeded in its application, was likely to be entitled to costs on a 2B basis. The parties were given an opportunity to agree on costs or to file memoranda if necessary.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established