IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
I TE KŌTI MATUA O AOTEAROA TĀMAKI MAKAURAU ROHE
CIV-2021-404-960
[2021] NZHC 3597
UNDER Section 290 of the Companies Act 1993 IN THE MATTER
of an application to set aside a statutory demand dated 6 May 2021
BETWEEN
SOUTH PACIFIC INDUSTRIAL LIMITED
Applicant
AND
DEMASOL LIMITED
Respondent
Hearing: 11 August 2021 Appearances:
PJ Crombie and PJ Anderson for the Applicant M Russell and C Smith for the Respondent
Judgment:
22 December 2021
JUDGMENT OF ASSOCIATE JUDGE SUSSOCK
This judgment was delivered by me on 22 December 2021 at 3.30pm pursuant to r 11.5 of the High Court Rules
Registrar/Deputy Registrar
Solicitors:
CooneyLees Morgan, Tauranga Rice Speir, Auckland
SOUTH PACIFIC INDUSTRIAL LTD v DEMASOL LTD [2021] NZHC 3597 [22 December 2021]
Introduction
[1] This dispute arises from the demolition of a large concrete tank in Penrose owned by BOC Ltd. BOC invited South Pacific Industrial Ltd (“SPI”) to provide a quote for demolishing the tank which contained materials contaminated by asbestos. The tank and all associated materials required removal.
[2] Demasol Ltd specialises in asbestos removal so SPI asked Demasol to provide a quote to carry out the bulk of the work as its subcontractor.
[3]SPI says that the contract agreed with Demasol was for a fixed price of
$100,000.00 exclusive of GST and tipping costs. Two payment claims were issued by Demasol for a total of $390,997.29. No payment schedules were issued in respect of either. Demasol therefore issued a statutory demand relying on the provisions in the Construction Contracts Act 2002 (“CCA”) which allow a party to recover the whole of a payment claim as a debt due where no payment schedule is issued and no payment made.
[4]SPI has applied to set aside the statutory demand on the following grounds:
(a)there is a substantial dispute as to whether the debt is owing;
(b)the contract covering the works performed by Demasol was for a fixed price of $100,000.00 plus GST, plus tipping costs for foam glass blocks at a maximum of $600.00 per tonne plus GST;
(c)the payment claim issued by Demasol, which the statutory demand is largely based on, was not calculated in accordance with the agreed contract price and is therefore not a valid payment claim under the CCA;
(d)variations claimed by Demasol were neither permitted under the fixed price contract nor agreed by SPI; and
(e)SPI has paid Demasol the agreed contract price, together with variations that were agreed by it, in full.
[5] Demasol submits in response that the contract price was an estimate only and allowed variations and that it has issued two valid payment claims to which payment schedules were not issued. It was therefore entitled to issue the statutory demand and it ought not to be set aside. In Demasol’s submission, setting aside the demand would be inconsistent with the “pay now, argue later” regime provided for in the CCA.
[6] Furthermore, Demasol says it has reason to believe that SPI cannot pay…
Keep reading for free
Create a free CaseChat account to read South Pacific Industrial Limited v Demasol Limited and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2021] NZHC 3597
- Decision Date
CaseChat Overview and Summary
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi