IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
I TE KŌTI MATUA O AOTEAROA TĀMAKI MAKAURAU ROHE
CIV-2020-404-572
[2020] NZHC 871
BETWEEN THE FLETCHER CONSTRUCTION COMPANY LIMITED
Applicant
AND
SPOTLESS FACILITY SERVICES (NZ) LIMITED
Respondent
Hearing: 17 April 2020 Appearances:
A M Callinan for Applicant
S C Price, J K Stewart and R A Donald for Respondent
Judgment:
30 April 2020
REASONS FOR JUDGMENT OF PETERS J
This judgment was delivered by Justice Peters on 30 April 2020 at 4.45 pm pursuant to r 11.5 of the High Court Rules
Registrar/Deputy Registrar Date: ...................................
Solicitors: Simpson Grierson, Auckland
MinterEllisonRuddWatts, Auckland
THE FLETCHER CONSTRUCTION COMPANY LTD v SPOTLESS FACILITY SERVICES (NZ) LTD [2020] NZHC 871 [30 April 2020]
[1]On 21 April 2020, I issued a results judgment in this matter as follows:1
Pending further order of the Court, pursuant to s 24A(2)(e) Construction Contracts Act 2002, I order Spotless to lift its suspension on notification to Spotless that FCC has deposited the amount of payment claim 44 ($2,067,715.86 excluding GST) with a stakeholder, to be held on interest bearing deposit, and to be disbursed in accordance with further order of the Court.
[2]These are my reasons.
[3] By without notice application for interlocutory injunction dated 16 April 2020, the applicant (“FCC”) sought the following orders:
(a)Restraining the respondent from taking any step to suspend its subcontract works on the Commercial Bay Project located on the corner of Quay, Custom, Albert and Queen Streets in Downtown Auckland (Commercial Bay) until further order of the court, including restraining the defendant from taking any further steps to give effect to the Notice of Intention to Suspend dated 18 March 2020 and the Suspension Notice dated 14 April 2020 purporting to suspend its subcontract works from 5pm on 14 April 2020;
(b)For any further relief the court thinks just; and
(c)For costs.
[4] I heard the application on 17 April 2020, on a Pickwick basis. Although the application had been threatened for some time, FCC only filed its application and supporting documents, and served the respondent (“Spotless”), on 16 April 2020. Spotless was represented by counsel at the hearing on 17 April 2020 but I accept their preparation would have been hampered due to shortness of time.
Background
[5] FCC is the head contractor on the “Commercial Bay” development situated at the northern, or harbour, end of Queen Street, Auckland. The overall development is being undertaken by Precinct Properties New Zealand Limited, or an associated company (“Precinct”).
1 The Fletcher Construction Company Ltd v Spotless Facility Services (NZ) Ltd [2020] NZHC 780 at [3] (footnotes omitted).
[6]Spotless is one of FCC’s subcontractors.
[7] Commercial Bay comprises a 40-level office tower, of which PricewaterhouseCoopers (“PwC”) is the anchor tenant, and a retail development which includes more than 100 retail/food and beverage tenancies. FCC, if not Spotless, considers the development will be, or should be, completed quickly once construction work recommences on site, as to which see below. This, in turn, will enable PwC and other…
Keep reading for free
Create a free CaseChat account to read Fletcher Construction Company Limited v Spotless Facility Se... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2020] NZHC 871
- Decision Date
CaseChat Overview and Summary
The court found that there was a serious question to be tried regarding the validity of FCC's payment schedule. While there were some deficiencies in the payment schedule, the court was not convinced that these deficiencies were so significant as to render the schedule invalid. The court also found that the balance of convenience lay in favour of FCC, as the suspension of work by Spotless would result in significant delays for the project, affecting not only FCC and Spotless but also other subcontractors and tenants. Lastly, the court considered the overall justice of the position and found that FCC's delay in seeking the injunction did not prejudice Spotless, and that FCC could meet any award of damages.
As a result, the court ordered Spotless to lift the suspension on work, subject to FCC depositing the amount in dispute with a stakeholder. The case is to be called in the Duty Judge list for further directions, and the parties are required to inform the court of the steps they are taking to resolve their dispute as to the payment schedule.