Watts & Hughes Construction Ltd v Complete Siteworks Company Ltd

Link copied
Case Copied 21 min read

IN THE COURT OF APPEAL OF NEW ZEALAND

CA444/2014
[2014] NZCA 564

BETWEEN

WATTS & HUGHES CONSTRUCTION LIMITED
Appellant

AND

COMPLETE SITEWORKS COMPANY LIMITED
Respondent

Hearing:

11 November 2014

Court:

Wild, Simon France and Asher JJ

Counsel:

G J Kohler QC and R E Catley for Appellant
C L Bryant and G J Luen for Respondent

Judgment:

26 November 2014 at 3.30 pm

JUDGMENT OF THE COURT

AThe appeal is dismissed.

BThe appellant is to pay the respondent’s actual and reasonable costs of the appeal with usual disbursements.

____________________________________________________________________

REASONS OF THE COURT

(Given by Wild J)

Introduction

  1. This appeal is against a judgment of Associate Judge Smith delivered on 31 July 2014 refusing an application to set aside a statutory demand the respondent (Siteworks) had issued to the appellant (Watts & Hughes).[1]  The Associate Judge ordered Watts & Hughes to pay Siteworks $306,077.23 within seven days of the judgment, failing which Siteworks could apply to put Watts & Hughes into liquidation.

  2. The statutory demand and the sum ordered to be paid arise from non-payment by Watts & Hughes of a progress payment claim made by Siteworks under a construction subcontract agreement (the subcontract).

  3. There is no real dispute as to what happened.  Counsel agree that the core legal issue for decision is:  what does cl 5, and in particular cl 5(b), of the subcontract mean?

  4. In addition to his interpretation argument on cl 5(b), Mr Kohler QC advanced for Watts & Hughes two further arguments.  Neither of these had been put to the Associate Judge in the High Court, but both were points included in the Notice of Appeal.  We deal with these points in [39] to [47] below.

The Construction Contracts Act 2002 and the subcontract

  1. P D Sloan (Sloan) contracted with Watts & Hughes as head contractor to build a supermarket in Ferrymead in Christchurch.

  2. On 30 July 2013 Watts & Hughes subcontracted the construction of the supermarket carpark to Siteworks.  The subcontract comprised the Master Builders standard form of subcontract agreement (SC1/June 2003) which incorporated the “full intent and meaning” of the Head Contract (the New Zealand Standard “Conditions of Contract for Building and Civil Engineering Construction” NZS3910:2003). 

  3. Section 12 of the Construction Contracts Act 2002 (the Act) provides:  “This Act has effect despite any provision to the contrary in any agreement or contract.”  The parties thus accept the subcontract was governed by the Act.  

  4. However, s 14 of the Act provides that the parties to a construction contract “are free to agree between themselves on” the progress payment provisions in the contract.  The subcontract contains such provisions.  They are at the heart of this appeal.  As Mr Kohler accepted, the default provisions, ss 16–18 of the Act, are accordingly displaced by the progress payment provisions in the subcontract.

  5. Sub-part 3 of pt 2 of the Act contains ss 19–24 which stipulate the procedure for making and responding to…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Watts & Hughes Construction Ltd v Complete Siteworks Company... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2014] NZCA 564
Decision Date

CaseChat Overview and Summary

Watts & Hughes Construction Ltd appealed against a decision of the High Court that dismissed their application to set aside a statutory demand issued by Complete Siteworks Company Ltd. The statutory demand arose from Watts & Hughes’ failure to pay a progress payment claim made by Siteworks under their subcontract agreement. The Court of Appeal dismissed the appeal and held that the statutory demand should not be set aside. Watts & Hughes argued that clause 5(b) of the subcontract allowed them to treat Siteworks’ late progress payment claim as received on the next monthly due date, without needing to communicate this election to Siteworks. However, the Court held that clause 5(b) did not automatically deem a late progress claim to have been received on the next monthly date, and Watts & Hughes was required to communicate any election it made under clause 5(b) to Siteworks. As Watts & Hughes failed to communicate any election by the last day on which it could have served a Payment Schedule, it became liable to pay the progress claim. The Court also rejected Watts & Hughes’ argument that Siteworks’ actions in digging up some of the metal it had laid on the carpark debarred it from making its progress claim. The Court held that Watts & Hughes needed to bring any counterclaim in respect of damage done as a separate claim, and it could not advance this matter as a reason for setting aside a statutory demand. The Court of Appeal ordered Watts & Hughes to pay Siteworks’ actual and reasonable costs of the appeal.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.