Watts & Hughes Construction Limited v Complete Siteworks Company Limited

Link copied
Case Copied 26 min read

IN THE HIGH COURT OF NEW ZEALAND WELLINGTON REGISTRY

CIV-2014-485-5124 [2014] NZHC 1797

IN THE MATTER OF The Companies Act 1993

BETWEEN

WATTS & HUGHES CONSTRUCTION LIMITED

Applicant

AND

COMPLETE SITEWORKS COMPANY LIMITED

Respondent

Hearing: 16 July 2014

Counsel:

R Kettelwell and R E Catley for Applicant
G J Luen for Respondent

Judgment:

31 July 2014

RESERVED JUDGMENT OF ASSOCIATE JUDGE SMITH

[1]      The  applicant  Watts & Hughes  Construction  Limited  (Watts  &  Hughes) applies to set aside a statutory demand issued by the respondent Complete Siteworks Company Limited (CSC) on 8 April 2014.

Background

[2]      Watts & Hughes is the head contractor on a development being constructed at Ferrymead in Christchurch.  Part of the development entailed the construction of a supermarket carpark, and CSC is a subcontractor engaged in the construction of the carpark.   The project developer is PD Sloan (Sloan), and Watts & Hughes’ head contract is with Sloan.

[3]      It is common ground that the subcontract between Watts & Hughes and CSC

is  governed  by  NZS  3910:2003  Conditions  of  Contract  for  Building  and  Civil

WATTS & HUGHES CONSTRUCTION LIMITED v COMPLETE SITEWORKS COMPANY LIMITED [2014] NZHC 1797 [31 July 2014]

Engineering Construction (NZS 3910:2003), and the Master Builders standard form of subcontract agreement (SC1/June 2003) (together the subcontract).

[4]      Under the terms of the subcontract, CSC was required to submit payment claims  on  the 25th   of  each  month  (the Due Date),  and Watts & Hughes  was  to provide payment schedules to CSC within 22 working days after the Due Date.  The subcontract provided that if Watts & Hughes did not respond to a payment claim submitted on the Due Date by CSC by providing a payment schedule within that 22 working  day  period,  Watts & Hughes  would  become  liable  to  pay  the  amount

claimed in the payment claim.   If a payment schedule was provided within the 22 working days, Watts & Hughes would be liable to pay the scheduled amount in the payment schedule, the amount due for payment became payable as a debt due to CSC 22 working days after the Due Date.

[5]      It is common ground that the subcontract was subject to the provisions of the

Construction Contracts Act 2002 (CCA).

[6]      The following clause in the subcontract addressed the situation where CSC

was late in submitting a monthly payment claim: 1

b) The Subcontractor shall submit monthly Payment Claims for work carried out…Each Payment Claim shall be submitted so as to be received on the Due Date specified in Schedule 1…Where a Payment Claim is received after the claim Due Date the Contractor may at its sole discretion elect to treat that  Payment  Claim  as  having been received  (and having  been due for receipt) on the next claim Due Date. (emphasis added).

[7]      Each payment claim submitted by CSC under cl 5(b) was deemed to be a “payment claim” and the amount specified for payment deemed to be the “claimed amount” for the purposes of the CCA.2

[8]      Between July 2013 and January…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Watts & Hughes Construction Limited v Complete Siteworks Com... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2014] NZHC 1797
Decision Date

CaseChat Overview and Summary

The case of Watts & Hughes Construction Limited v Complete Siteworks Company Limited involves a statutory demand issued by Complete Siteworks Company Limited (CSC) against Watts & Hughes Construction Limited. The dispute pertains to payment claims submitted under a subcontract for work on a Christchurch development. Watts & Hughes, the applicant, sought to set aside the statutory demand, arguing that there was a substantial dispute as to whether the debt was owing or due. The court was required to decide whether Watts & Hughes was obligated to communicate its decision to treat a late payment claim as having been received on the next due date, and if such communication was made. The court found that Watts & Hughes had an obligation to communicate its election to CSC and that it failed to do so. Consequently, the application to set aside the statutory demand was refused. The court ordered Watts & Hughes to pay CSC the sum of $306,077.23 within seven days of the judgment date, and in default of payment, CSC may make an application to put Watts & Hughes into liquidation. The court also requested memoranda on the issues of interest and costs.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.