IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
CIV-2014-404-001388 [2014] NZHC 3090
IN THE MATTER OF a statutory demand issued under s 289 of
the Companies Act 1993
BETWEEN
LEIGHTON CONTRACTORS PTY LIMITED
Applicant
AND
SHARP CONCRETE CUTTERS & DRILLERS LIMITED
Respondent
Hearing: 29 September 2014 Appearances:
A E Murray for Applicant
E St John for RespondentJudgment:
5 December 2014
JUDGMENT OF ASSOCIATE JUDGE OSBORNE
as to statutory demand
This judgment was delivered by me at 9.00 am on 5 December 2014 pursuant to Rule 11.5 of the High Court Rules
Registrar/Deputy Registrar
LEIGHTON CONTRACTORS PTY LIMITED v SHARP CONCRETE CUTTERS & DRILLERS LIMITED [2014] NZHC 3090 [5 December 2014]
Introduction – Sharp’s demand on payment claims
[1] The applicant (Leighton) applies for an order setting aside a statutory demand issued by the respondent (Sharp).
[2] The demand arises out of a construction contract dated 11 September 2012 which is subject to the Construction Contracts Act 2002 (the Act). The estimated completion date was April 2013; the work was in fact completed in July 2013.
[3] Sharp’s demand is stated to represent the balance of payment claims issued under the Act in response to which, it alleges, Leighton failed to provide payment schedules in accordance with the Act. Leighton accepts that each invoice issued by Sharp constituted in terms of s 20 of the Act a valid payment claim. The parties agree as to the dates on which the payment claims were made. With the exception of two claims of 1 July 2013, the timing of the claims and responses are such that the statutory demand either entirely stands or entirely falls, depending upon which
party’s argument succeeds.1 (The invoices are listed in Table 1 at [16] below
together with other details relating to them).
[4] It is common ground that, regardless of the Court’s determination on the parties’ arguments, the statutory demand requires adjustment (in relation to the 1 July
2013 claims). It is also common ground that the cash payment schedules issued on the dates referred to in Table 1 at [16] below constituted valid payment schedules under s 21 of the Act.
The issue
[5] The issues in this proceeding are as to the effective date of each payment claim. Leighton asserts that the claims became effective on the 25th day of the
month. Sharp asserts that the effective date was 20 working days from service.
1 See below at [16]–[17].
[6] Counsel agree that to resolve that issue, the Court must answer two questions:
(a) did the contract provide a payment claim/payment schedule regime in place of the default regime under the Act?
(b)to the extent that the contract purports to include such a regime, were the terms of the contract invalid as being in conflict with mandatory provisions of the Act?
[7] Two other grounds of opposition were not pursued by Ms Murray for Leighton. First, Leighton abandoned an argument that the statutory demand had not adequately identified the debt. Secondly, Ms Murray…
Keep reading for free
Create a free CaseChat account to read Leighton Contractors Pty Limited v Sharp Concrete Cutters &... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2014] NZHC 3090
- Decision Date
CaseChat Overview and Summary
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi