Leighton Contractors Pty Limited v Sharp Concrete Cutters & Drillers Limited

Link copied
Case Copied 15 min read

IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY

CIV-2014-404-001388 [2014] NZHC 3090

IN THE MATTER OF

a statutory demand issued under s 289 of

the Companies Act 1993

BETWEEN

LEIGHTON CONTRACTORS PTY LIMITED

Applicant

AND

SHARP CONCRETE CUTTERS & DRILLERS LIMITED

Respondent

Hearing: 29 September 2014

Appearances:

A E Murray for Applicant
E St John for Respondent

Judgment:

5 December 2014

JUDGMENT OF ASSOCIATE JUDGE OSBORNE

as to statutory demand

This judgment was delivered by me at 9.00 am on 5 December 2014 pursuant to Rule 11.5 of the High Court Rules

Registrar/Deputy Registrar

LEIGHTON CONTRACTORS PTY LIMITED v SHARP CONCRETE CUTTERS & DRILLERS LIMITED [2014] NZHC 3090 [5 December 2014]

Introduction – Sharp’s demand on payment claims

[1]      The applicant (Leighton) applies for an order setting aside a statutory demand issued by the respondent (Sharp).

[2]      The demand arises out of a construction contract dated 11 September 2012 which is subject to the Construction Contracts Act 2002 (the Act).  The estimated completion date was April 2013; the work was in fact completed in July 2013.

[3]      Sharp’s demand is stated to represent the balance of payment claims issued under the Act in response to which, it alleges, Leighton failed to provide payment schedules in accordance with the Act.  Leighton accepts that each invoice issued by Sharp constituted in terms of s 20 of the Act a valid payment claim.   The parties agree as to the dates on which the payment claims were made.  With the exception of two claims of 1 July 2013, the timing of the claims and responses are such that the statutory  demand  either  entirely  stands  or  entirely  falls,  depending  upon  which

party’s  argument  succeeds.1      (The  invoices  are  listed  in  Table  1  at  [16]  below

together with other details relating to them).

[4]      It is common ground that, regardless of the Court’s determination on the parties’ arguments, the statutory demand requires adjustment (in relation to the 1 July

2013 claims). It is also common ground that the cash payment schedules issued on the dates referred to in Table 1 at [16] below constituted valid payment schedules under s 21 of the Act.

The issue

[5]      The issues in this proceeding are as to the effective date of each payment claim.   Leighton asserts that the claims became effective on the 25th day of the

month.   Sharp asserts that the effective date was 20 working days from service.

1      See below at [16]–[17].

[6]      Counsel agree that to resolve that issue, the Court must answer two questions:

(a)      did the contract provide a payment claim/payment schedule regime in place of the default regime under the Act?

(b)to the extent that the contract purports to include such a regime, were the terms of the contract invalid as being in conflict with mandatory provisions of the Act?

[7]      Two  other  grounds  of  opposition  were  not  pursued  by  Ms  Murray  for Leighton.  First, Leighton abandoned an argument that the statutory demand had not adequately identified the debt.  Secondly, Ms Murray…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Leighton Contractors Pty Limited v Sharp Concrete Cutters &... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2014] NZHC 3090
Decision Date

CaseChat Overview and Summary

Leighton Contractors Pty Limited (Leighton) applied to set aside a statutory demand issued by Sharp Concrete Cutters & Drillers Limited (Sharp). The demand was based on an alleged failure by Leighton to provide payment schedules in accordance with the Construction Contracts Act 2002 (the Act). Leighton contended that the contract between the parties provided its own payment claim/payment schedule regime, which excluded the default regime under the Act. Sharp, on the other hand, argued that the contract did not provide a payment claim/payment schedule regime and, therefore, the default regime under the Act applied. The court found that it was at least arguable that the contract provided a valid payment claim/payment schedule regime, which excluded the default regime under the Act. Consequently, the court set aside the statutory demand issued by Sharp and ordered Sharp to pay Leighton's costs on a 2B basis together with disbursements to be fixed by the Registrar.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established