For a court-ready version, please follow this link.
IN THE HIGH COURT OF NEW ZEALAND WELLINGTON REGISTRY
I TE KŌTI MATUA O AOTEAROA TE WHANGANUI-A-TARA ROHE
CIV-2019-485-593
[2020] NZHC 772
BETWEEN HASKELL CONSTRUCTION LIMITED
Plaintiff
AND
ROBERT FRANCIS ASHCROFT
First Defendant
AND
ALPINE PRIME PROPERTIES LTD
Second Defendant
Hearing: 27 February 2020 Counsel:
M Freeman for Plaintiff
F B Collins for Second Defendant (for limited purpose of abiding decision) and Third Defendant
Judgment:
21 April 2020
JUDGMENT OF GRICE J
Contents
Para No.
Introduction [1]
Grounds for judicial review [11]
Issues [17]
Judicial review [18]
Construction Contracts Act 2002 [21]
What do “rights and obligation of the parties” under the construction contract mean? [31]
The words used [37]
Implied Warranties and Statutory Remedies Under the Building Act 2004 [41]
Issue estoppel [72]
Conclusion [87]
Costs [89]
HASKELL CONSTRUCTION LIMITED v ASHCROFT [2020] NZHC 772 [21 April 2020]
Introduction
[1] In September 2018 Haskell Construction Limited (Haskell) commenced construction of an architecturally designed home for Alpine Prime Properties Limited (Alpine). They were parties to a signed construction contract for the building that was entered into in August 2018. Not long into the construction complications arose requiring further work involving structural steel framing. This work was the subject of a variation issued which added to the cost of construction. The parties disagreed on payment for the steel members. This led to Alpine purporting to cancel the contract.
[2] In February 2019 Haskell submitted a payment claim for stage two of the construction and in March gave five days’ notice that it would suspend works for non- payment. In April Alpine asserted that the contract was cancelled for breach of contract. Haskell accepted the cancellation on a without prejudice basis.
[3] The substantive dispute between the parties will be dealt with at arbitration in August 2020. The appointed arbitrator is a barrister. In the meantime the dispute has been dealt with at adjudication. Two adjudication determinations have been issued and these proceedings relate to a third adjudication claim brought by Alpine.
[4] The Construction Contracts Act 2002 (CCA) established a summary adjudication process for the determination of disputes. This was designed to provide a fast track determination process which would allow the timely determination of disputes arising in construction contracts so the construction was not delayed pending a lengthy legal process. A determination does not affect the ultimate substantive decision which will be made here at arbitration. Nevertheless, the determinations are enforceable in their terms when made.
[5] In this case two adjudication determinations have been issued. The adjudicator, Mr Hazelton, issued a determination in each the first and second adjudications on 29 May 2019. The net outcome of the adjudications was that Alpine was to pay Haskell the sum of $133,619.16 as an interim award under the contract. This amount was determined in the first adjudication.
[6] In the second adjudication the adjudicator found that Haskell was in breach of the contract. However, the adjudicator declined to change the earlier monetary…
Continue reading Haskell Construction v Ashcroft
Sign in free to access the full text
- AGLC
- Haskell Construction v Ashcroft [2020] NZHC 772
- Case
- [2020] NZHC 772
- Decision Date
CaseChat Overview and Summary
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.